Quiz Flashcards
a project is not used for tasks that are
reiterative and part of ordinary job
which concept is not considered as part of the process in the model of WHAT/HOW
planning
the complete project triangle contains the three parameters
costs, objective time / time resources, result (product quality calendar time resources)
the decision point between the phases is called
tollgate
what is not a mandatory governing document
requirements specification
what is normally not part of the pre-study
mini-risk analysis
which is correct order for a project planing
requirements, define result, WBS, communication plan
the project managers role and mandate is
to follow up and evaluate the ongoing project work + plan motivate and communicate with the client
who is a core stakeholder in the hym project example
the bank
your project idea is to offer a rental service of electric scooter - what can be regareded as threats within SWOT
competitors, new legislation, changes loan, interest rates
the impact goal answers the question on
why?