Exam1 Flashcards
Which is considered a project?
A temporary task undertaken to make a unique result.
The hand over of the result is part of the closure phase. Correct or Incorrect?
Incorrect
The project owner is responsible for the tasks in closure phase. Correct or Incorrect?
Correct.
In a project where a product is ready to be delivered, acceptance tests are often performed before the handover. Correct or incorrect?
Correct.
The project owner is responsible for planning the handover process. Correct or incorrect?
Correct.
The hand-over-procedure is the same as acceptance-procedure. Correct or incorrect?
Incorrect
Evaluation and assessment of the impact goals are not always part of closure phases. Correct or incorrect?
Correct.
A pre-study may include different types of activities. Which three of the following activities will most likely be part of it? (3)
- Define the acceptance procedure with answers on what, how, when and who.
- Make a project plan.
- Invite those executing the project to a kick off meeting.
- Do a SWOT-analysis
- Do a WBS to estimate the resources needed.
- Perform a stakeholder analysis.
- Define the acceptance procedure with answers on what, how, when and who.
- Do a SWOT analysis
- Perform a stakeholder analysis
Select the alternative with the correct planning order (from start to finish).
- MoSCoW-POMR-WBS-Gantt
- PBS-MoSCoW-Gantt-WBS
- WBS-MoSCoW-PERT-Gantt
- MoSCoW-WBS-Gantt-PERT
- MoSCoW-WBS-PERT-Gantt
- WBS-PBS-PERT-Gantt
- MoSCoW-WBS-PERT-PBS
MoSCoW, WBS, PERT, Gantt
Risk analysis is primarily a support for the project manager as it provides a mental preparation for the possible risks and threats that may occur during the execution of the project. Correct or incorrect?
Correct
Lack of competence within the project organization is considered as a T in the SWOT-analysis. Correct or incorrect?
Incorrect.
The Maxi risk method uses an estimation of the consequences o the risks based on the three control parametres. Correct or incorrect?
Incorrect.
The MoSCoW-analysis is one way of doing a risk analysis in the pre- study. Correct or incorrect?
Incorrect.
Your company is preparing to start a product development project with the aim to launch a new product for companies in road and bridge constructions. The project will run for a period of two years. How do you assess following factors based on a SWOT-analysis.
- An worldwide economical recession is expected to occur during the year
- The company lacks infrastructure expertise
- Few other companies are working with this type of solution
- There are several projects within the company that have a higher priority
T: An worldwide economical recession is expected to occur during the year
W: The company lacks infrastructure expertise
O: Few other companies are working with this type of solution
W: There are several projects within the company that have a higher priority
You are working in a project where the organisation wants to move forward to an agile way of working. Which two project lifecycles should be combined to create an Agile environment?
Iterative and Incremental lifecycles.