Quantification to L3 - SoE Q’s Flashcards
What are the 3 documents in New Rules of Measurement?
NRM 1 = Order of cost estimating and cost planning for capital building works
• NRM 2 = Detailed measurement for building works
• NRM 3 = Order of cost estimating and cost planning for building maintenance works
What is ICMS?
International Cost Management Standard
International standard for benchmarking, measuring and reporting construction project costs
ICMS 3 used as a tool to decarbonise construction sector in the most cost-
effective way
Globally consistent method for carbon lifecycle reporting across construction projects
What document implements ICMS?
• RICS Cost Prediction.
• Implements ICMS for cost management professionals.
How do you measure steelwork in a cost plan?
- Length & weight in kg for type of steel divided by 1000 = t
- Measure toonage using British steel weight chart
- 10% for fixings and components
How would you price preliminaries in a detailed cost plan?
• In accordance with Section 9 of NRM
1
• Include allowances as required from
Section 9
• Use rates from previous projects and benchmark data for similar projects
What is a provisional sum?
An allowance included within the contract sum for works that may not be sufficiently designed or detailed to allow accurate determination of costs
Work the employer may or may not wish to be carried out
What is included within the guidance note IPMS ALL BUILDINGS?
This document reviews the application of IPMS1, IPMS2, IPMS3 and IMPS4 advising on how they used to be referred to as GEA, GIA and NIA.
International Property
Measurement Standards
- IPMS 1 & 2 are external and internal measurements respectively for the whole or part of a building.
- IPMS 3.1 (external) and IPMS 3.2 (internal) are external and internal measurements respectively required for exclusive occupation.
- IPMS 4.1 (incl. walls and columns) & 4.2 ( excl. walls and columns) are internal measurements required for selected areas respectively including internal walls and columns and excluding external walls and columns.
Tell me the key details in IPMS1?
IPMS1 (GEA) - The sum of the areas of each floor level of a building, measured to the outer perimeter of the external wall.
Inclusions under IPMS1 but to be included separately are items such as balconies and rooftop terraces.
Exclusions under IPMS1 are items such as lightwells and open external stairways.
What are some of the inclusions and exclusions under IPMS2?
IPMS2 (GIA) - The sum of the areas of each floor level of a building measured to the internal dominant face.
Inclusions under IPMS2 but to be included separately are items such as balconies and rooftop terraces.
Exclusions under IPMS2 are items such as open lightwells and upper level voids of an atrium.
Resi
What are some of the inclusions and exclusion under IPMS 3.1 (Exclusive Use Areas)?
Must state weather measures are IMPS 3.1 or 3.2.
IPMS 3.1 (NEA) - The floor area available on an exclusive basis to the occupier measured external to any notional boundary, external walls and demising walls. Any External Floor Areas and sheltered areas are reported separately.
Inclusions under IPMS3 are all internal walls and columns within an occupants exclusive area.
Exclusions are the shared/common facilities, voids and stair openings.
What are some of the exclusions and inclusions under IPMS 3.2 (Exclusive Occupation Internal Measurement)?
IPMS 3.2 (NIA) - The floor area available on an exclusive basis to the occupier measured external to any notional boundary, IDF and demising walls. Any External Floor Areas, Mezz and sheltered areas are reported separately.
Inclusions under IPMS3 are all internal walls and columns within an occupants exclusive area.
Exclusions are the shared/common facilities, voids and stair openings, wall thickness between External Floor Area and IDF.
What are some of the inclusions and exclusions under IPMS 4.1 ?
IPMS 4.1 () - The selected floor area in a building measured to finished surfaces and to any notional boundaries, external floor area and sheltered area including all flier areas occupied by walls and columns.
Inclusions under IPMS 4.1, but to be included separately are external floor areas, shelters areas, stairs, staircase openings and lift shafts.
Exclusions are external walls and columns.
What are some of the inclusions and exclusions under IPMS 4.2 ?
IPMS 4.2 () - The selected floor area in a building measured to finished surfaces and to any notional boundaries, external floor area and sheltered area but excluding all areas occupied by walls and columns.
Inclusions under IPMS 4.1, but to be included separately are external floor areas, shelters areas, stairs, staircase openings and lift shafts.
Exclusions are external walls and columns.
What is the difference between IPMS and Code for Measuring Practice?
IPMS is measured to the Internal
Dominant Face and includes cills.
External floor areas such as balconies and terraces are included but measured separately in IPMS.
What is IPMS used for?
• Measurement of areas, such as GEA, GIA and NIA.
What is the difference between IPMS and NRM?
IPMS is relevant for all surveying disciplines, whereas NRM is focused on measurement for commercial and
construction processes.
What would you typically include within a cost plan?
• Front Cover
• Contents
• Executive Summary including basis for pricing, any assumptions and exclusions
• Drawing Register
• Area Schedule
• Measured Works
What are the advantages of using a bill of quantities?
• All tenderers are pricing the same document
• Simplifies tender analyses
• Detailed and comprehensive
• Ideal for post contract cost control
What is a bill of quantities?
Based on detailed design and specification, whereby the client provides the contractor quantities for them to price.
What are the disadvantages of using a bill of quantities?
• Potential for errors when measuring the project
• Risk sits with employer
What are the two types of
BoO?
• Firm BoQ
• Approximate BoQ
When would you use an approximate BoQ?
• Best suited to a
remeasurement form of
contract
Fixed price - where onus is on contractor to verify quantities
What are dayworks?
Work recorded on a daywork sheet together with the labour, material and plant resources used to carry out the work
How are loss & expense claims valued?
• Using bill rates
• Using star rates
• Using dayworks
• Schedule 2 Quotation
What is meant by heads of claim?
This is how loss and expense is valued:
* Prolongation
* Disruption
* Interest Charges
* Loss of Profit
* Loss of Bonus
* Increased Site Overheads
* Increase in Cost of Materials
What are the different methods of measurement for cost estimating?
- Floor area method
- Functional unit method
- Elemental method
What are the differences between NRM1 and NRM2?
NRM 1 is for quantification of building works for the purposes of preparing estimates and cost plans. Also for quantifying other elements e.g. prelims, OHP, design team fees, risk allowances, inflation.
NRM2 guidance for detailed measurement and description of building works for the purpose of tendering. Address BOQ production by setting out detail required, non-measurable and contractor design and risks.
How does a cost plan differ between Stage 1 and Stage 4?
A) RIBA 1: Order of Cost estimate
B) RIBA 2: Formal Cost Plan 1
- Initial cost plan based on elemental take off of drawings.
- identify risk allowances and potential probs sums.
- show concept design aligns with budget.
C) RIBA 3: Formal Cost Plan 2
- cost based on greater detail
- Cost increase offset against risk allowance.
- identify risk allowances and potential probs sums.
- show spatial coordination aligns with budget.
D) RIBA 4) Formal Cost Plan 3
- Cost defined by detail and procurement strategy
- Pre-Tender Estimate
- identify risk allowances and potential probs sums.
- show Technical design aligns with budget.
What are the different cost plan stages and what are the relevant levels of estimate in accordance with RICS Cost Predication?
- Formal cost plan 1 - RIBA 2 (Concept) - Level 3
- Formal cost plan 2 (Spatial Coordination) - RIBA 3 - Level 4
- Formal cost plan 3 (Technical Design) - RIBA 4 - Level 5
What is NRM2 used for?
Formal cost plan / PTE & BOQ
What are the three breakdown structures for a BOQ?
- Elemental - NRM1 elemental cost plan
- Work section -
- Work package - divided into client or contractor work packages. Can be based on trades or package containing multiple trades