Case Study - Key issue 1 Flashcards
What is the BSA?
Introduced to ensure building and fire safety is managed. New building safety regulator.
In response to Grenfell.
Was the project deemed to be a HRB, if so what is a HRB?
A residential building above 18m’s and/or 7 storeys tall.
At least 2 residential units.
What are the new rules for HRB under the BSA?
All high risk buildings are regulated by the Building Safety Regulator and need to go through a 3 stage gateway process prior to start on site and occupation.
How has BSA and HRB impacted the cost of a project?
Greater requirement for early contractor input increasing PCSA costs.
What was the cost per unit for the PBSA project in the RIBA 3 cost plan?
£17m / £159k per unit
What was included in the budget?
Measured works costs, on costs and inflation. Excluding design team costs and PCSA fees.
What was included in the cost plan to represent a targeted September 2026 go live date?
Tender Inflation- (base TPI - TPI at SoS)/TPI at SOS = inflation factor
Construction inflation - (TPI at SoS - TPI at Midpoint)/ TPI at Midpoint = Inflation factor
What was included in the cost plan to represent the high standard of living?
High amount of amenity space provided.
Allowances for interior finishes.
Allowances for FF&E.
Why did you choose Design & Build as the procurement route?
a) Challenging site so early contractor involvement into the design was required.
b) Potential for earlier start on site due to overlapping.
c) Design risk transfer to the Contractor limiting potential post contract cost increases.
Why does design risk transfer to the contractor limit the potential for cost increases post contract?
a) Once the contract has been let any changes associated with design development the cost is borne with the Contractor whereas for a traditional contract this would be with the client.
When is it appropriate to use a design and build contract?
a) When detailed ER’s have been prepared.
b) When detailed contract provisions arg necessary.
Does a design and build contract give you cost certainty?
How are discrepancies in the ER’s & CP’s dealt with within?
a) If the contractor becomes aware of discrepancies in the ER’s CP’s or Instructions, they have to give notice to the Employer.
b) Contractor notifies of proposed amendment.
c) Employer decides between discrepadcies or accept the contractors proposal.
Contractor must comply with the decision by the Employer without cost to the Employer.
Why was a traditional procurement route and contract not chosen?
a Sequential process therefore overlap between tendering and design and design and construction would not be possible.
b) Outturn cost is dependent on a fully robust design by the clients design team.
How did your cost estimates differ from a cost plan?