What are the three documents in the NRM suite?

A

NRM1 - Order of Cost Estimating and Cost Planning for Capital Building Works

NRM2 - Detailed Measurement for Building Works

NRM3 - Order of Cost Estimating and Cost Planning for Building Maintenance Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the difference between an order of cost estimate and a formal cost plan?

A

Order of cost estimate - estimate based on benchmark data based on the clients initial brief. Establishes affordability. Level 1 & 2

Formal Cost plan - estimate based on drawings and/or specifications. Level 3, 4, & 5