Contract Practice to L3 - SoE Q’s Flashcards
What Contracts are available under the JCT Suite of Contracts?
• JCT Standard
• JCT Intermediate
• JCT Minor Works
• JCT Design and Build
• JCT Construction Management
• JCT Management Building
• ]CT Major Projects
What are some differences between JCT Contracts?
D&B includes for Employers Agent, not included in Standard, Intermediate or Minor Works
D&B and Major Projects Contractor is responsible for completing the design.
D&B and Major Projects do not mention a QS.
Deferment of possession n/a to Minor Works forms.
Minor works does not include provisions for collateral warranties
Minor Works unable to include sectional completion
When would you use certain JCT Contracts?
Standard = For larger projects involving complex services installations and specialist work
Intermediate = when proposed works are simple in nature, involving basic recognised trades within the industry, without complex services installations or specialist work.
Minor Works = When works are of a
simple nature
Design & Build = When looking to transfer risk to the Contractor
What Contracts are available under the NEC Suite of Contracts?
• Option A: Priced contract with Activity Schedule
• Option B: Priced contract with Bills of
Quantities
• Option C: Target contract with Activity Schedule
• Option D: Target contract with Bills of Quantities
• Option E: Cost reimbursable contract
• Option F: Management contract
What is a contract?
Legally binding promise by one party to fulfil an obligation to another party in return for consideration.
What is a contract comprised of?
- Offer
- Acceptance
- Consideration - benefit each party involved gets or expects.
- Intention to create legal relations
What are the key differences between JCT and NEC contracts?
JCT - QS |adversarial traditional risk apportionment | Variations & Changes | programme is not contractual
NEC - collaborative | CE’s | Programme is contractual | supervisor monitors defects
What is the valuation procedure under JCT D&B?
- IVD
- 7 days after Due Date
- 5 days after Due Date Payment Notice
- Final date for payment 14 days after Due Date
- 5 days before Employer must serve Pay Less Notice
Note: D&B if application isn’t received by IVD date then Due Date is 7 days after receipt of application
What is a variation or a change?
Modifications to the contract works. Can be due to performance or instructions.
What is a change under D&B?
A Change in the ER’s which makes necessary the alteration or modification of the design or quality of the works.
Factors affecting the process of valuing change / variations
- Type of contract
- Character of work
- Conditions of the work
- Quantity
How do you value change?
- Use of BOQ, SoW or CSA - star rate
- If the work is not similar in character or nature then value is based on fair rate and prices - quotes
- Day works - labour, plant and materials with % definitions set out in the contract
What is Loss and Expense?
A claim from the Contractor for direct loss and/or expense as a result of a relevant matter occurring
What is a relevant matter?
A relevant matter is a matter for which the client is responsible that materially affects the progress of the works.
- Failure to give possession
- Failure to give access
- Delays in receiving instructions
- Failure to supply goods or materials
What is a relevant event?
Specific events or circumstances that may impact the progress, completion, or cost of a construction project. Entitle the Contractor to an EOT.