Quantification and Costing of Construction Works - Level 2 Flashcards

1
Q

Talk me through how you’ve quantified the effect of delay and disruption to a construction activity on follow-on activities and trades.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Talk me through when you’ve produced a bill of quantities.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Talk me through when you’ve produced a schedule of activities.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Talk me through when you’ve produced a schedule of rates.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Talk me through when you’ve quantified the value of construction works during the superstructure stage of a project.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Talk me through when you’ve carried out a contract sum analysis.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Talk me through when you’ve costed a variation using tendered rates.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Talk me through when you’ve costed construction works using dayworks.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why did you decide that dayworks were the most suitable method of costing the works?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Talk me through when you’ve costed work using quotation.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you determine that the quotes you received represented good value for money?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Talk me through how you’ve taken account of preliminaries in costing.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How have you measured building work items?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How have you compiled unit rates?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How have you compiled a final cost estimate report?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How have you presented a report to the client and members of the project team?

17
Q

Have you prepared a Pre Tender Estimate (PTE)?

18
Q

What are the key stages of a project requiring quantification?

19
Q

Give an example of where you have developed a Bill of Quantities / part of and the process you followed.

20
Q

What are the measurement rules for retaining walls? - How did you go about developing appropriate costs?

21
Q

Tuckenhay - Explain the process you followed to develop the schedule of work for this project.

22
Q

Tuckenhay - What was the sequence of work you followed for each element?

23
Q

Tuckenhay - How did you use NRM guidance to support you?