Contract Administration - Level 1 Flashcards

(62 cards)

1
Q

What are the timescales involved with an extension of time request on a standard JCT contract?

A

JCT contract require contractor to notify the employer “forthwith” once it becomes reasonably apparent that the progress of works is, or will be affected.
Following receipt of contractor’s notice, the employer will consider application and respond to contractor to indicate if it will award an EOT and fix a new completion date. Require employer to respond asap, within 12 weeks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Does an instruction need to have an agreed value contained within it?

A

There is no proforma format for an Architects Instruction and it does not need to include an agreed value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The contractor fails to complete the project by the completion date what measures do the CA/EA take and what are the consequences of this?

A

Issue a Notice of Non-Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The CA/EA fails to issue a non-completion certificate on an over running project what are the consequences of this?

A

The non-completion notice is formal written notice that contractor has failed to complete the works in the contract by the completion dates.
- triggers right for employer to levy liquidated damages
Three key documents required for employer to levy damages:
1) Non completion certificate
2) Employer written to contractor to notify them that intends to levy liquidated damages
3) Employer must issue pay less notice to recover LADs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is your understanding of bespoke contract?

A

A bespoke contract is one that is drafted for a specific matter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What do you understand as the difference between a bespoke contract and standard form of contract?

A

A standard form of contract like JCT or NEC have been developed for use in multiple different projects by many different parties. A bespoke contract is one that is drafted for a specific project or party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are your views on the advantages/disadvantages of using a bespoke contract?

A

A bespoke contract will be designed specifically to suit a particular client or project.
The advantage is that it is made to measure and will not need to be adapted (like a standard form contract), however, other parties will not be familiar. Standard forms have been developed over many years with input of many different experts with different roles in projects. The contract has been tested in many different projects and any potential issues already tested in courts.
All parties should be familiar with interpretation, language and processes and procedures required to follow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are your views on the advantages/disadvantages of using a standard form of contract?

A

A bespoke contract will be designed specifically to suit a particular client or project.
The disadvantage is that it is not made to measure and will not need to be adapted, and other parties will be familiar. Standard forms have been developed over many years with input of many different experts with different roles in projects. The contract has been tested in many different projects and any potential issues already tested in courts.
All parties should be familiar with interpretation, language and processes and procedures required to follow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the qualities of the NEC form of contract?

A

NEC contracts are designed to promote collaborative working, aiming to reduce conflict

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the advantages of the JCT form of contract?

A

It is most popular contract form in UK, widely known and familiar throughout industry.
The language and processes have been tested in courts and used in many projects successfully.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What changes were last made to the NEC form of contract? When were these made?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between a Relevant Event and Relevant Matter?

A

A relevant event is one which causes delay to a project and entitles contractor to EOT but without incurring potential loss and expense to contractor.
A relevant matter is one which causes delay to a project entitling the contractor to an extension of time and to claim for loss and expense incurred as a result of the event.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If a non-completion certificate is not issued what is the contractual effect?

A

Time is at large - no completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What guidance is there on contract administration?

A

RICS Contract Administration guidance has been withdrawn.
JCT publishes guidance on contract administration role.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the duties of a CA under JCT contracts? Do these include design?

A

CA duties are:
- no design responsibility, surveyor should avoid advising employer on issues relating to assembly, material choices, design or spec and shouldn’t give verbal instructions on site during early stages of project.
- determining EOT claims
- determining loss and expense claims
- issuing practical completion statements
- issuing instructions to overcome discrepancies/changes
- issuing instructions to expend provisional sums
- certifying interim payments
- administering change control procedures
- collating and issuing schedules of defects
- issuing the certificate of making good defects
- notifying partial possession
- certifying sectional completion
- certifying practical completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When authorising payment for goods or materials stored off site what must you obtain to protect your client in the event of the contractor going bankrupt?

A

A vesting certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

If you are concerned that a contractor is in financial difficulties name 3 things as CA you should do?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What key function does a contract administrator perform on a construction project?

A

Administering the contract provisions and procedures
Issuing certificates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Can you name three standard forms of contracts that can be used on a construction project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What insurance provisions are in the JCT and NEC standard forms of contract?

A

JCT insurance provisions - option A, option B or option C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is loss insurance?

A

Financial cover for losses that fall directly on the insured party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is all risks insurance?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Where is the minimum financial cover for the contractor’s liability for injury death and damages to property other than the works contained?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the three ways that benefits can be transferred under JCT contracts?

A

Collateral warranties
Assignment
Third party rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Who might want a collateral warranty?
A third party with interest in project eg funder An employer from sub-contractor
26
What are the common clauses / terms in collateral warranties?
27
Are there any alternatives to collateral warranties?
28
Who issues a letter of intent and who signs it?
Employer issues Both parties sign
29
What would you say if the client asked you to draft a letter of intent?
Advise that should get solicitor to sign If standard LOI up to limit would use pro-forma
30
What is the purpose of a final account?
31
When must the final certificate be issued?
32
What additions may there be to the FA?
32
What is the procedure for getting the FA agreed?
33
What is released to the contractor in the final certificate?
34
How is the JCT form of contract structured?
35
How is the NEC form of contract typically structured?
36
What is your understanding of retention bonds
37
What is your understanding of early possession?
38
What contractual weight does a practical completion certificate carry in a JCT contract?
It marks the point that building project is complete, except for minor defects and outstanding works that can be put right without undue interference or disturbance to occupier. Some describe as the point when building project is capable of beneficial occupation and use by Employer.
39
Tell me about some of the insurances a subcontractor would need if they were responsible for a part of the design work.
Professional indemnity insurance
40
What is your understanding of performance bond? When would it be used?
41
In the NEC form of contract talk me through five things that can lead to a compensation event.
42
In the NEC form of contract when can the completion date be adjusted?
43
In the NEC form of contract what is a defined cost?
44
In the NEC form of contract what is a disallowable cost?
45
When were changes to NEC4 last made? What changes were made?
46
What is your understanding of the difference between delay and disruption?
47
Why is good housekeeping essential for CA?
The contract contains obligations and timeframes for issuing valid notices. The CA needs to keep on top of what is required and make sure that it complies as necessary.
48
What is PC and when does it occur?
Practical completion Occurs when all matters set out on practical completion checklist are complete to satisfaction of CA. Usually all building works complete except minor defects
49
What should be taken into account in the wording of a PCSA? What might the pitfalls be?
50
What is the role of an Employer's Agent?
This is the party who is identified in the contract and who acts on behalf of the employer in all matters, effectively as if the employer's agent were the employer. When carrying out certification and decision making under contract the EA should act impartially.
51
What contract might include the role of EA?
Design and Build
52
How do the roles of CA and EA differ?
CA is solely responsible for administering contract for employer. EA acts on behalf of employer in all matters, including administering contract
53
Can you act as both CA & EA?
Not sure - would there be both roles in one contract?
54
What typical documents make up a Building Contract?
The Contract The tender documents - BQ / Schedule of works and tender drawings Pre-tender information provided to contractor
55
Under what circumstances would it be appropriate to pay for materials that are off-site?
When vesting certificate is provided. Goods should be adequately protected for employer and capable of identification (ie separate from other materials)
56
Take me through your methodology of tendering a project?
57
List some methods of ADR you may find in a JCT contract.
Adjudication Mediation Arbitration
58
What insurance provisions are you aware of in JCT contracts?
Option A, B and C
59
What are the different roles defined in the contract?
Contractor Employer QS CA Principal Designer
60
What is the role of a contract administrator pre-contract?
No role - the role is identified in the contract and only exists at the point that the contract is entered into.
61
Where is the role of a contract administrator defined?
In the contract