Contract Practice - Level 1 Flashcards

1
Q

What key function does a contract perform on a construction project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define express terms?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define implied terms?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What six conditions need to be met for a contract to be in place?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main suites of construction contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is tort?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the influences which will affect contract selection?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you name three standard forms of contracts that can be used on a construction project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you understand about the following forms of contract; FIDIC, JCT, etc …..

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does JCT stand for?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name the key components of the JCT contract suite.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When was the JCT contract suite last updated?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Tell me about some of the key changes that were made.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How was the JCT contract suite modernised through the last update?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does JCT facilitate electronic working?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How does the JCT work alongside the Construction Playbook?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How has the JCT contract suite incorporated diversity and inclusion?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the JCT Fluctuations Hub used for?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Explain the JCT Target Cost Contract to me.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What form of NEC contract might the Target Cost Contract be a good alternative for?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the main parts of the JCT contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the JCT schedules?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How are relevant events and relevant matters dealt with under NEC?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

How does NEC deal with loss and expense?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What types of insurance are required under JCT?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

How is fitness for purpose dealt with under JCT DB / CDP?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is the contractor’s design liability under JCT contracts (for CDP elements)?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What are the differences in procurement between JCT Standard Form and JCT with Contractor’s Design?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

When would you use a JCT IC or MW contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Can benefits be assigned under JCT contracts?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

When and why would you use each?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Explain the role of main sub and package contracts from the standard suites you are aware of.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

In a contract you have used explain the following; roles and responsibilities of the parties

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What client specific considerations have you taken into account when selecting a contract type?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What insurance provisions are in the JCT and NEC standard forms of contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What is a contractor’s all risk insurance or contract works insurance?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What do you understand by insurance in joint names?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What is a collateral warranty?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

What is your understanding of what a letter of intent is?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What is a comfort letter/consent to spend/recognition of contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

When might you use advance payments?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What is the final account?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Who prepares the final account in a JCT form of contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Who prepares the final account in the NEC4 form of contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

What is the purpose of a final account?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

On the issue of the final account what are the relevant time periods in a JCT form of contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

When must the final certificate be issued?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Tell me two of the information or statements that must be contained in the final certificate.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

What are the usual constituents of a final account?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What is released to the contractor in the final certificate?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

What are the usual constituents of a final account?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What are the four elements of a valid contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What third party rights might be included in a contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

How does dispute resolution work in a contract you have experience of?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

What is common law?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What do you understand by consideration in contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

What do you understand by invitation to treat in contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

How is the JCT form of contract structured?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

How is the NEC form of contract typically structured?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

What is the difference between a contract executed under seal and underhand?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

When selecting a form of contract what factors do you consider?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

What alternative forms of contract are there available and what would influence your recommendation of a form of contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Design and Build contracts - what are the 3 main forms of this contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Name 3 factors you think make this form of contract valid for your work?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Apart from JCT D&B what other forms of D&B contracts are there?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Have you ever considered a NEC D&B contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Within a JCT SBC when and why would you use a Schedule 2 quotation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

What are the timescales in a Schedule 2 quotation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

If the contractor on a D&B contract fails to issue the final account within the due period what action should you advise your client to take?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

If you had to explain the differences to your client between sectional completion and partial possession can you provide an example of the differences under a JCT D&B contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

How do sectional completion partial completion and beneficial use differ?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Define each of the following: sectional completion partial completion and beneficial use differ?

74
Q

If you client wanted to place furniture in the completed parts of a project which would you recommend sectional completion or partial possession?

75
Q

What are liquidated damages?

76
Q

What is your understanding of retention and bonds?

77
Q

What is your understanding of early possession?

78
Q

What contractual weight does a practical completion certificate carry in a JCT contract?

79
Q

Tell me about some of the insurances a subcontractor would need if they were responsible for a part of the design work.

80
Q

What do you understand by a parent company guarantee?

81
Q

When might it be used?

82
Q

What is your understanding of sectional completion?

83
Q

What is your understanding of performance bond?

84
Q

When might it be used?

85
Q

What is you understanding of limitation of liability?

86
Q

Talk me through how you’ve ensured insurances from subcontractors were at the correct level.

87
Q

What do you understand by relevant event in a JCT form of contract?

88
Q

What do you understand by compensation event in a NEC form of contract?

89
Q

In the NEC form of contract talk me through five things that can lead to a compensation event.

90
Q

In the NEC form of contract when can the completion date be adjusted?

91
Q

In the NEC form of contract what is a defined cost?

92
Q

In the NEC form of contract what is a disallowable cost?

93
Q

When were changes to NEC4 last made?

94
Q

What changes were made?

95
Q

How are NEC contracts categorised by different alternative pricing options?

96
Q

What are these pricing options?

97
Q

How is BIM integrated in a contract you are familiar with?

98
Q

Explain Secondary Option X7.

99
Q

What issue was raised by Triple Point Technology v PTT Public Co?

100
Q

How was Secondary Option Y(UK)2 updated to reflect the judgement in Rochford Construction v Kilhan Construction?

101
Q

How were Secondary Option X22 and Secondary Option Y(UK) 1 amended?

102
Q

When are NEC compensation events not time barred?

103
Q

In a NEC contract how would you detail if the contract is to be D&B?

104
Q

What does the works information is included in a NEC contract?

105
Q

What are the different types of FIDIC contract and how do they reflect different risk profiles?

106
Q

What is your understanding of the difference between delay and disruption?

107
Q

When does financial management of a project typically take place?

108
Q

Explain what happens during the post contract phase.

109
Q

How do you implement and manage cost control procedures and reporting within the scope of a contract?

110
Q

What contract legislation are you aware of?

111
Q

Explain how contracts may deal with contractor designed works.

112
Q

Explain your understanding of contracts and sub-contracting.

113
Q

What payments provisions and change procedures are you aware of?

114
Q

What factors affect the choice of security in a contract?

115
Q

What insurances are you aware of?

116
Q

What is novation and assignment?

117
Q

What is a collateral warranty?

118
Q

What are the three ways that benefits can be transferred under JCT contracts?

119
Q

Who might want a collateral warranty?

120
Q

How are they requested?

121
Q

What are the common clauses / terms in collateral warranties?

122
Q

What is the difference between a bond and collateral warranty?

123
Q

With any D&B contract there is a high probability that collateral warranties will apply where would you expect to see them and between which parties?

124
Q

Are there any alternatives to collateral warranties?

125
Q

Explain your understanding of retention.

126
Q

What is the purpose of retention?

127
Q

What items do not have retention taken on them?

128
Q

Who receives the interest accruing on retention money?

129
Q

When is the retention released to the contractor?

130
Q

What if the contract sum increases?

131
Q

Explain your understanding of liquidated and delay damages.

132
Q

Explain your understanding of claims for extensions of time acceleration and loss and expense.

133
Q

What is early possession?

134
Q

Explain your understanding of phasing.

135
Q

How can a contract be terminated?

136
Q

Explain the impact of insolvency on contracts.

137
Q

How do you deal with final accounts?

138
Q

What is a pre-construction services agreement (PCSA)?

139
Q

When are pre-construction services usually used?

140
Q

What should be taken into account in the wording of a PCSA?

141
Q

What might the pitfalls be?

142
Q

When would you recommend the use of a PCSA?

143
Q

How does a PCSA differ to a LOI?

144
Q

Explain your understanding of defects and rectification.

145
Q

How has Covid-19 affected a contract you have worked on?

146
Q

Explain the differences between cost reimbursement and lump sum contracts.

147
Q

Explain a key principle of the new RICS Guidance Note Subcontracting (1st Edition).

148
Q

What is a subcontractor defined as within this?

149
Q

What does the Guidance Note not cover?

150
Q

If an architect develops a design to a certain stage and the appointed D&B contractor then wants to use the design and develop further what do they need to do?

151
Q

Explain in this scenario xxx

152
Q

What is novation?

153
Q

How does novation affect the employer’s rights?

154
Q

What are the advantages of novation?

155
Q

Are there any disadvantages of novation?

156
Q

Do you have novation on traditional contracts?

157
Q

What measures can be taken to effectively control costs during the construction phase of a project?

158
Q

How can you control costs to keep a job under budget?

159
Q

How do NEC and JCT manage change control?

160
Q

Why is cash flow important?

161
Q

How does a cash flow help a company remain solvent?

162
Q

What is risk allocation?

163
Q

What do you understand by risk management?

164
Q

What is a risk management strategy?

165
Q

What are the benefits of risk management?

166
Q

What are the stages of risk management?

167
Q

Why is risk management needed in construction?

168
Q

What is the risk response?

169
Q

How is risk quantified?

170
Q

What are risk management techniques?

171
Q

How do you report or monitor risks?

172
Q

What are preliminaries?

173
Q

What are preambles?

174
Q

What would you include in a work schedule?

175
Q

What are the three main standard forms of construction contract?

176
Q

What is the role of contract administrator in each of these?

177
Q

How do cost complexity and time impact selection of JCT contract?

178
Q

How does quality impact the contract selection?

179
Q

What are the key differences between the JCT forms of contract?

180
Q

Why are valuing change and valuations crucial for a QS?

181
Q

What other contract procedures must the QS be aware of?

182
Q

What are the rules for valuing change?