Quantification and costing Flashcards
1
Q
You recieve a Variation or Compensation Event in the contract. How do you go about assessing that?
A
- Ascertain whether or not it is a change
- Identify if there is any works of a similar nature in the CSA or Pricing Document
- Compare the contracted drawing against the change drawing and measure the difference
- Quantify the change
- Assess whether or not the rates are fair and reasonable
2
Q
In an NEC contract how would you go about assessing and Compensation Event?
A
Option A and C can be assessed against first principles
Option B and D can be assessed against if there is the same activity in the BoQ