Contract Practice Flashcards
What is a contract?
It is a legally binding promise between 2 or more parties comprising: offer, acceptance, intention, and consideration.
How did you value Materials on Site on the Throgmorton House project?
In this instance it was MVHR units and associated ductwork. Because I judged the materials, based on comparable project data, to cost a significant amount, I judged 40% completion to be fair and reasonable.
Briefly summarise the options available for NEC for both pre-construction and construction stages
PSC for pre-construction
ECC options:
A & B: Lump sum with Activity Schedule and BoQ
C & D: Target cost with Activity Schedule and BoQ
E: Cost re-imburseable contract
F: Cost re-imburseable management contract
What is the broad difference in levying Liquidated Damages between NEC and JCT contracts
NEC: deducted from the Payment Certificate issued the Project Manager
JCT: Employer or EA notifies the contractor outsidd of the Payment Notice their intention to pay less than the amount notified.
What is the difference in QS’s role between NEC and JCT contracts?
JCT issue a valuation certificate on the due date
NEC they will make an assessment but the Project Manager will issue the Payment Certificate on the due date
What is the key difference between how works are assessed in JCT and NEC contracts?
NEC: certified on 100% completion of the activity
JCT: can cerifty based on a percentage of the works completed for esch activity