Contract Administration Flashcards

1
Q

What’s the difference between a Contract Administrator and an Employer’s Agent?

A
  1. CA administers the contract on behalf of the Employer
  2. EA acts on behalf of the client on all matters
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the disadvantages of MMC?

A
  1. Less flexibility in design
  2. Higher upfront costs
  3. Higher costs if design is changed due to upfront procurement and build
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the RIBA stages of work?

A
  1. Strategic Definition
  2. Preparation and Briefing
  3. Concept Design
  4. Spatial Coordination
  5. Technical Design
  6. Manufacturing and Construction
  7. Handover
  8. Use
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What NRM document would you use for RIBA stages 0-3?

A

NRM1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What NRM document would you use for RIBA Stage 4?

A

NRM2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What’s the format of a JCT contract?

A
  1. Agreement
  2. Recitals
  3. Articles
  4. Contract Particulars
  5. Attestations
  6. Conditons
  7. Schedules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the format of a JCT contract conditions?

A
  1. Definitions
  2. Carrying Out the Works
  3. Control of the Works
  4. Payment
  5. Changes
  6. Injury, Damages, Insurance
  7. Bonds and Warranties
  8. Termination
  9. Settlement of Disputes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly