Quantification and Costing Flashcards
On Chelsea Barracks Building 8 you mentioned tolerance of the slab. What is the typical tolerance of the slab?
5% out of tolerance.
What was your advice on the project Chelsea Barracks Building 8?
I advised the Contractor that they had to measure in accordance with NRM and measure as a m2 rather than in bags of screed. Resulting in a cost saving.
What rate did you agree for a cost /m2 for screed?
£10/m2 in the apartments, and £28/m2 for communal spaces as it would require a different solution.
What contract was used for your PWI project?
JCT SBC xQ with Amendments
You mention valuing change, what does the Contract say about valuing change?
Following the JCT Valuation Rules.
What are the JCT Valuation Rules?
You should use the Pricing Document as the basis of valuing variations if they are still valid.
What needs to be in place before paying for materials off-site?
1) Materials adequately protected
2) Check insurance is in place
3) Materials should be on site within a reasonable period
What should you check prior to valuing materials off-site?
1) Vesting certificate
2) Insurances are in place until the materials arrive on-site.
3) Ask for evidence the materials are clearly marked for the project and set apart.
4) Check the material off-site bond has been provided.
On Chelsea Barracks Building 6, you mentioned the Contractor was in delay and you reassessed the value of prelims. What are the two methods of doing this?
1) You take away the number of weeks delay from the amount complete. Ie, if 50 weeks had gone by in a 100 week programme, if the Contractor is 10 weeks late you would take the 10 weeks from the 50. So (50-10)/100.
2) You add on the number of weeks delay to the overall contract period. Ie, same example as above, 50/(100+10).
How did you reassess the Contractor’s delay on Chelsea Barracks Building 6?
I added on the number of weeks delay onto the total period of time. Ie, the Contractor was reporting a delay of 5 weeks so I added this on to the overall period length.
I am aware that by taking the number of weeks in delay away from the amount complete