Contract Practice Flashcards

1
Q

On your PwC project you mentioned “NBS Chorus”. What is that?

A

The software used to assemble the Contract Preliminaries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You mentioned the Contractor would need some insurances, could you list some insurances the Contractor might need under a JCT D&B?

A

1) Contractor’s all risk
2) Professional Indenmity
3) Bonds (Performance bonds, material off-site bond).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

On Chelsea Barracks & PWI, you stated working with Vesting certificate. What is this?

A

Used to confirm that the ownership of the goods, plant, or materials will transfer from one party to another on payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are alternatives to a vesting certificate you could use?

A

Materials off-site bond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a performance bond?

A

A performance bond is a form of security for the Employer or Developer.

It is a guarantee from the bank / insurance company to make payment to the employer should the Contractor default under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was the value of the bond

A

1% of the Contract Sum, around £225,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the typical cost of a performance bond?

A

It depends on the financial stability of the Contractor and the number of previous claims. But typically 1% of the contract sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Are you aware of any case law relating to Construction?

A

Ampleforth Abbey Trust vs Turner & Townsend

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What value did the performance bond protect the Client?

A

10% of the Contract Sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are signs a Contractor is financially unstable?

A

1) Word of mouth
2) Cashflow issues
3) Lack of personnel on site
4) Delays on site / poor quality
5) High cost in performance bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the different kinds of performance bonds?

A

Conditional and On-demand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a conditional bond?

A

The Client must provide evidence that the Contractor has not met the terms of the Contract. They must also prove they have suffered financial loss.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is required for a legally enforceable contract?

A

1) Offer
2) Consideration
3) Intent to create legal relations
4) Acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What information comprises contract documents?

A

1) Index of Contract Docs
2) Contract Amendments
3) Commercial
4) Preliminaries
5) Drawings and Specification

  • if D&B, you have ER’s and CP’s.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the valuation timelines?

A

Under JCT D&B:

1) Application Date

2) Due Date + 7 days

3) Payment Notice + 5 days

4) Final date for Payment + 14 days

5) Final date for pay-less -5 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What happens at Practical Completion?

A

1) Works certified as complete, although likely with a snag list of works to be undertaken during the rectification period.

2) The rectification period begins (snags)

3) Insurance requirements passed back to Client

4) LD’s no longer an option

5) Release of retention - typically half.

17
Q

What are the different insurance requirements under JCT?

A

EL - Employers Liability (death in construction)
PL - Public Liability
PI - Professional Indemnity

18
Q

What are the Building Insurance requirements under JCT?

A

Option A - New works, by Contractor

Option B - New Works, by Employer

Option C - Existing, by Employer

(Other - Terrorism, All-Risk)

19
Q

What are third party rights?

A

A statutory right that creates right for a party not in the original contract to have an interest.

20
Q

What do you factor/consider into your payment schedule regarding contract conditions and statutory conditions?

A

Reckoning Days - Bank holidays.

Updated for any amendments to payment timescales.

21
Q
A