Project Resource Management Flashcards
What is project resource management?
Project resource management includes processes to identify, acquire and manage the resources needed for the successful completion of the project.
- ensures that the right resources are available to the project manager and project team at the right time and place.
What are the processes in project resource management?
Processes in project resource management are:
- Plan resource management
- Estimate activity resources
- Acquire resources
- Develop team
- Manage team
- Control resources
What is plan resource management process?
Plan resource management process is the process of defining how to estimate, acquire, manage and utilize physical and team resources.
- key benefit is that it establishes the approach and level of management effort needed for managing project resources based on the type and complexity of the project.
What are inputs to the plan resource management process?
Inputs to the plan resource management process are:
- Project Charter
- Project management plan:
- 1 Quality management plan
- 2 Scope baseline
- Project documents
- 1 Project Schedule
- 2 Requirement documentations
- 3 Risk register
- 4 Stakeholder register
- Enterprise Environmental Factors
- Operational process assets
What are the tool and techniques used in plan resource management process?
Tools and techniques used in plan resource management are:
- Expert judgement
- Data representations (i.e. charts)
- 1 Heirarchical charts (OBS, RBS, WBS)
- 2 Responsibility assignment matrix (RAM) shows which project resource is responsible for a work package (eg RACI)
- 3 Text-oriented format
- Organizational theory
- Meetings
What are the outputs of plan resource management process?
Outputs of plan resource management process are:
- Resource management plan - provides guidance on how resources will be categorized, allocated, managed and released.
- team management plan and physical resource management plan
- Team charter - establishes the team values, agreements and operating guidelines for the team.
- Project documents
- 1 Assumption log
- 2 Risk register
What is estimate activity resources process?
The estimate activity resources is the process of estimating team resources and the type and quantities of materials, equipment and supplies necessary to perform project work.
What is resource planning?
Resource planning is used to determine and identify an approach to ensure that sufficient resources are available for the successful completion of the project.
What are the inputs to estimate activity resources process?
Inputs to the estimate activity resources process are:
- Project charter
- Project management plan
- 1 Resource management plan
- 3 Scope baseline
- Project documents
- 1 Activity attributes
- 2 Activity list
- 3 Assumption log
- 4 Cost estimates
- 5 Resource calendars
- 6 Risk register
- Enterprise environmental factors
- Organizational process assets
What are the tools and techniques to estimate activity resources?
Tools and techniques to estimate activity resources are:
- Expert judgement
- Data analysis i.e. Alternative analysis
- Bottom-up estimating
- Analogous estimating
- Parametric estimating
- Project Management Information system (PMIS)
- Meetings
What are the outputs of estimate activity resources?
Outputs of estimate activity resources are:
- Resource requirements
- Basis of estimates
- Resource breakdown structure (RBS, hierarchical representation of resources by category and type))
- Project document updates:
- 1 Activity attributes
- 2 Assumption log
- 3 Lessons learned register
What is resource requirements?
Resource requirements identify the types and quantities of resources required for each work package or activity in a wok package and can be aggregated to determine the estimated resources for each work package, each WBS branch and the project as a whole.
What is the Acquire Resources?
Acquire Resources is the process of obtaining team members, facilities, equipment, materials, supplies and other resources necessary to complete project work.
Key benefit of this process:
- it outlines and guides the seletion of resources and assigns them to their respective activities
What are inputs to the Acquire Resources?
Inputs to the Acquire Resources are:
- Project Management plan:
- 1 Resource management plan
- 2 Procurement management plan
- 3 Cost baseline
- Project documents:
- 1 Project schedule
- 2 Resource calendars
- 3 Resource requirements
- Enterprise environmental factors
- Operational process assets
What are the tools and techiques of Acquire Resouces?
Tools and techniques in Acquire Resources are:
- Decisiion making (multicriteria decision analysis)
- Interpersonal and Team skills
- 1 Negotiations
- Pre-assignment
- Virtual Teams