Project Management basics - 5.6 CONTROL SCOPE Flashcards
Control Scope is the process of monitoring the status of the project and which of the following?
a. Scope creep and deliverables
b. Approved change requests and document updates
c. Product scope and changes to the scope baseline.
d. Product deliverables
c. Product scope and changes to the scope baseline.
Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. The key benefit of this process is that the scope baseline is maintained throughout the project. Control Scope is also used to manage the actual changes when they occur and is integrated with the other control processes.
See Section 5.6 Control Scope
Which of the following is an output of the control Scope process?
a. Organizational process assets
b. Trend analysis
c. Change requests
d. Configuration management plan
c. Change requests
Outputs:
- Work performance information;
- Change requests;
- Project management plan updates ( scope management plan, scope baseline, schedule baseline, cost baseline, performance measurement baseline);
- Project documents updates ( lessons learned register, requirements documentation, requirements traceability matrix),
See Figure -17 on Control Scope: Inputs, Tools & Techniques, and Outputs
What is an output of the Control Scope process?
a. Verified deliverables
b. Approved change requests
c. Project document updates
d. Scope management plan
c. Project document updates
Outputs:
- Work performance information;
- Change requests;
- Project management plan updates ( scope management plan, scope baseline, schedule baseline, cost baseline, performance measurement baseline);
- Project documents updates ( lessons learned register, requirements documentation, requirements traceability matrix),
See Figure -17 on Control Scope: Inputs, Tools & Techniques, and Outputs
What output is part of the Control Scope process?
a. Change requests
b. Work performance data
c. Project scope statement
d. Requirements management plan
a. Change requests
Outputs:
- Work performance information;
- Change requests;
- Project management plan updates ( scope management plan, scope baseline, schedule baseline, cost baseline, performance measurement baseline);
- Project documents updates ( lessons learned register, requirements documentation, requirements traceability matrix),
See Figure -17 on Control Scope: Inputs, Tools & Techniques, and Outputs
Which of the following is NOT an output of the Control Scope process?
a. Project document updates
b. Work performance information
c. Change requests
d. Accepted deliverables
d. Accepted deliverables
Outputs:
- Work performance information;
- Change requests;
- Project management plan updates ( scope management plan, scope baseline, schedule baseline, cost baseline, performance measurement baseline);
- Project documents updates ( lessons learned register, requirements documentation, requirements traceability matrix),
See Figure -17 on Control Scope: Inputs, Tools & Techniques, and Outputs
which of the following is an input of the Control Scope process?
a. Change requests
b. Scope measurement baseline
c. Work performance data
d. Expert judgment
c. Work performance data
Inputs:
- Project management plan; (scope management plan, requirements management plan, change management plan, configuration management plan, scope baseline, performance measurement baseline);
- Project documents (Lessons learned register, requirements documentation, requirements traceability matrix);
- Work performance data;
- Organizational process assets.
See Figure 5-17 on Control Scope; Inputs, Tools & Techniques, and Outputs
Which of the following are tools and techniques of the Control Scope process?
a. Duration based analysis
b. Data analysis
c. Schedule network analysis
d. Reserve analysis
b. Data analysis
Control Scope & Tools:
- data analysis ( variance analysis, trend analysis).
See Figure 5-17 on Control Scope; Inputs, Tools & Techniques, and Outputs
What is the purpose of the Control Scope process?
The purpose of the Control Scope process is to monitor the status of the project scope and manage change to the scope baseline.
The key benefit of this process is:
- The scope baseline is maintained throughout the project.
- Ensure that all requested changes and corrective or preventive actions are performed through the Perform Integrated Change Control process.
Which project assets are considered appropriate input(s) for the Control Scope process?
- Organizational Process Assets;
- Work Performance Data;
- Project Management Plan;
- Project Documents
Which project assets are considered appropriate output(s) for the Control Scope process?
- Project Management Plan Updates (Scope Management Plan, Scope Baseline, Schedule Baseline, Cost Baseline, Performance Measurement Baseline).
- Project Management Updates (Lessons Learned register, Requirements Documentation, Requirements Traceability Matrix).
- Work Performance Information
- Change Requests