Project financial control and reporting Flashcards
What is a cost report?
It is a document that captures the financial information of a project during the construction stage on a monthly basis. It reports on the project’s predicted and actual costs at a given point in time.
What is the format of a cost report?
Alban cost reports:
- Executive summary:
- Authorised expenditure:
- Forecast cost:
- Contract sum.
- Less risk allowances.
- Adjustment of provisional sums/prime costs/provisional quantities/contract instruction/anticipated instructions/fluctuations/loss and/or expense
- Contractual summary:
- Contract period.
- Estimated completion date.
- Performance to date.
- Exclusions.
- Cashflow Forecast:
- Forecast costs.
- Reconciliation with previous report.
- Changes since previous report.
- Adjustment of variable costs.
- Contract instructions.
- Anticipated instructions.
- Risk allowances.
How often are cost reports prepared?
Monthly.
Can cost reports be prepared more frequently than once a month?
They can be prepared more frequently at the client’s request and in some instances if there are significant changes.
What is a cashflow?
A cashflow is a graphical or tabular prediction of the costs anticipated during the life of a project.
Why is a cashflow important?
To ensure appropriate level of funding is in place to cover works executed and there is a suitable draw-down.
How is a cashflow prepared?
- A construction programme and contract sum would be needed to populate a cashflow.
- Values associated with elements can be forecasted at times to reflect critical dates within programme.
- Split the works into different packages and include individual S-curves for each package.
- If there are any specialist sub-contractors or consultants, the obtaining their drawdowns can also assist in populating the cashflow.
- Sometimes using a cashflow from a previous project can assist or using an cashflow software however that should be taken with a pinch of salt as it may not always be accurate.
What are the advantages and disadvantages of a cashflow?
Advantages:
- Financial planning - helps anticipate cash needs and prevent shortages.
- Budget management - aids in monitoring actual expenses against budgets.
- Risk management - identify cash surplus or shortfalls in advance.
- Decision making.
- Contract management.
Disadvantages:
- Accuracy challenges - market conditions and regulatory changes can be just some of the causes of a cashflow deviating from it’s projection.
- Complexity.
- Dependency on assumptions.
- Cashflow variability - changes in scope of works, variations, delays and etc. can cause cashflows to deviate and require much planning to anticipate such changes.
- Limited scope.
Why do cashflows have an s-curve?
- Construction projects follow distinct phases and as the project progresses the level of funds will change dependent on the nature of works being undertaken during that period.
- At the start there is minimal expenditure as construction activities are winding up in preparation which will include for site setup, mobilization and enabling works.
- As the works progress, the packages of higher value are undertaken such as frame, M&E installations which will cause a peak in the curve.
- As the works come to a close, construction activities begin winding down as there are minor works such as decorations, testing, commissioning and etc. As a result, there will be minimal expenditure here and the curve will taper off.
Where actual payments fall below the forecast, what could that indicate?
- Programme delay.
- Financial difficulties of the contractor.
- Poor contractor cashflow.
- Performance of contractor.
- Re-sequencing of works.
- Materials stored off-site and not yet ready to incorporate into main works.
- Delay in delivery of materials.
What needs to be done to the cashflow in future reports if actuals are falling below the forecast?
It needs to be re-baselined moving forward.
Where actual payments fall above the forecast, what could that indicate?
- Front-end loading.
- Acceleration of work.
- Re-sequencing of works.
- Materials stored on site well in advance of installation.
- Materials off site not accounted for within cashflow.
- Inclusion of variations.
- Accuracy of cashflow prior to commencing construction.
- Market fluctuations.
What is a variation?
Changes to the design, quality or quantity of the contract works, site access or working conditions.
Why might variations arise?
- Change in specification.
- Discrepancies in contract documentation.
- Discrepancies in statutory requirements.
- Errors and omissions.
- Deficiencies in ER’s.
What about oral instructions?
Depends on the contract and if there is a mechanism that allows for oral instructions, e.g. the JCT SBC states:
- If the CA issues an oral instruction it will have no immediate effect.
- The Contractor shall confirm in writing receipt of the oral instruction within 7 days.
- If the CA does not dissent by notice to the Contractor within 7 days of receiving confirmation, then it will take effect from the expiry of the latter 7 days.
Ultimately, all oral instructions should be followed up with a formal/written response ASAP to avoid disputes and ensure clarity and certainty.