Contract Practice Flashcards
What is a contract?
It is a legally binding promise (written or oral), by one party to fulfil an obligation to another party in return for consideration.
What is the difference between an implied and express term?
- Implied Terms - These are implied by law and not necessarily written into the contract and are inferred by the actions of the parties involved. For example: going to a restaurant and ordering food, the waiter must serve the food and the customer is obliged to pay.
- Express Terms - These are terms which are explicitly agreed by both parties and stated in the contract. For example: pay, hours, holidays and etc. Important note, once an express term is established and identical implied contract cannot exist.
- Both contracts are legally binding.
- An express contract is much easier to enforce as it is in writing compared to an implied contract.
What is quantum meruit?
This is where a reasonable sum is paid for the services rendered or work undertaken if the amount due is not stipulated in the contract.
What does a typical pack of contract documents contain?
- Conditions of contract and amendments to standards forms e.g. SOA or Z-Clauses (depending on type of standard form).
- Preliminaries.
- Contract Sum Analysis/Pricing Schedule.
- Drawings.
- Specifications.
- Planning conditions/Agreements.
- Contractor’s Proposals.
What legislation are you aware of that govern construction contracts in the UK?
- Housing Grant, Construction and Regeneration Act 1996 (HGCRA).
- Local Democracy, Economic Development and Construction Act 2009 (LDEDC).
What laws does the construction industry operate under in the UK?
- Tort law.
- Contract law.
- Criminal law.
Explain some of the sanctions the HGCRA 1996 imposes on construction contracts in the UK?
- Contracts in excess of 45 days are entitled to interim or stage payments.
- Right to suspend performance for non-payment.
- Disallowing ‘pay when paid’ clauses.
- Right to adjudication.
- Right to be informed of the amount due and amount withheld.
Explain some of the sanctions the LDEDC 2009 imposes on construction contracts in the UK?
- Bolstering a payee’s right to suspend for late payment.
- Removing existing barriers to adjudication.
- Making both written and oral contracts subject to the Act.
- Right for adjudicator to correct typos and clerical errors.
Explain the understanding of the Unfair Contracts Act 1977 (UCTA)?
It regulates contracts by limiting the extent to which one party can avoid liability through the use of exclusion clauses.
For example: if one party was to raise prices without considering the rights of another would be considered unfair e.g. a utility provider increasing their prices without notifying the consumer or a landlord increasing rent without given sufficient notice to their tenants.
Name some families of contracts?
- Joint Contract Tribunal (JCT).
- New Engineering Contract (NEC).
- International Federation of Consulting Engineers FIDIC.
What are the key changes of the new JCT suite of contracts 2024?
- Gender neutral language.
- Option of ‘collaborative working’ changed to core article for parties to work together in good faith and in a spirit of trust and respect.
- Target cost contracts.
- Updating relevant events to include for the following:
- epidemics which occur after base date or before the base date but effects change after base date that affect the proper carrying out of works such as availability of labour, securing materials and etc.
- delays upon the discovery of asbestos, contaminated materials and UXO’s.
- change in law, guidance or exercise of statutory powers that affect the execution of the works.
- Duty holder obligations introduced by the Building Safety Act 2022 to comply with their respective duties under Part 2A of Building Regulations. New roles of PD and PC also recognised.
- Design liability - Contractor’s design liability has changed from ‘fit for purpose’ to ‘exercise reasonable skill and care.’
- Termination - Updated in line with the Corporate Insolvency and Governance Act 2020. List of events entitling either party to terminate a contract has been updated to include for epidemics and changes in law that affect the execution of the works.
Name some of the standard forms of JCT contract?
- Standard form with quantities (SBC/Q).
- Standard form without quantities (SBC/XQ).
- Standard form with approximate quantities (SBC/AQ).
Name some of the conditions of the SBC/Q?
- Works have been designed.
- There is a bill of quantities (BoQ).
- Is a lump sum form.
- Contractor’s risk is limited to price only.
- Employer takes risk of errors in the bill.
- Can include for CDP elements.
Name some of the conditions of the SBC/XQ?
- Works have been designed.
- There is no bill of quantities (BoQ).
- Is a lump sum form.
- Contractor takes risk for price and quantity.
- Can include for CDP elements.
Name some of the conditions of the SBC/AQ?
- Is a remeasurement form of contract.
- There is no contract sum.
- Design is incomplete at time of contract execution.
- Approximate bill of quantities (BoQ) has been prepared.
- Can include for CDP elements.
When is it most ideal to use the JCT SBC form of contracts?
Ideal for project with the following:
- Value in excess of £1m+.
- Programme duration of 12 months or more.
- For large complex projects.
- Administered by the contract administrator (CA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an SBC, the QS is appointed and named.
What is the JCT intermediate building contract, it’s conditions and when it’s most suitable for?
The IBC is a contract that is more detailed than the minor works building contract but not as extensive as the standard building contract. Is usually administered on projects that are procured via the traditional method and call also contain elements of CDP.
It is best suited for projects with the following conditions:
- Procured via the traditional route.
- Design is complete prior to tender.
- Can include elements of CDP, if so, then IBC with CDP must be issued.
- Is a lump sum contract.
Ideal for projects with the following:
- Value in between £250k - £1m.
- Programme duration of up to 12 months.
- For moderate sized projects although some complex areas can be included through CDP.
- Administered by the the contract administrator (CA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an IBC, the QS is appointed and named.
What is the JCT minor works building contract, it’s conditions and when it’s most suitable for?
The MW is a contract that refers to small, relatively straight forward construction projects that are less than £250k in value. Is usually administered on projects that are procured via the traditional method.
It is best suited for projects with the following conditions:
- Procured via the traditional route.
- Design is complete prior to tender.
- Can include elements of CDP, if so, then MWBC with CD must be issued.
- Is a lump sum contract with periodic payments.
Ideal for projects with the following:
- Value up to £250k.
- Programme duration of up to 12 months.
- Administered by the the contract administrator (CA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an MW, the QS is not appointed and named.
What is the JCT Design and Build (D&B) contract, it’s conditions and when it’s most suitable for?
The D&B is a contract where there is a need for a single point of responsibility for delivering the entire project. Is usually administered on projects that are procured via the design and building method.
It is best suited for projects with the following conditions:
- Procured via the D&B route.
- Design can overlap during the tender/construction and thus a programme saving can be offered.
- Is a lump sum contract with periodic payments.
Ideal for projects with the following:
- Value in excess of £500k+.
- Programme duration of 12 months or more.
- Contractor’s proposals form the basis of the contract.
- Enhances collaborative working, sustainability, 3rd party rights, bonds, collateral warranties and etc.
- Administered by the Employer’s Agent (EA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an D&B, the QS is not appointed and named.
Name some of the elements of a JCT contract?
- Recitals - describes the purpose of the contract and contextualises the agreement such as:
- describes the works required by the employer.
- confirmation of a priced schedule has been provided.
- identifies the contract design information and etc.
- Articles - set out what is required between the parties of the contract such as:
- contractor to deliver the works.
- client to pay the sum under the contract and etc.
- Contract Particulars - sets out the details specific to the contract such as:
- the contract sum.
- retention percentage
- Interim payment method.
- Completion dates and sectional completion dates and etc.
What are some of the differences between the JCT and NEC forms of contract?
- JCT:
- Forms of Contract.
- Legal language.
- QS referenced in SBC, not in D&B.
- Programme is not a contractual document.
- Variations.
- Loss and expense (L&E), extensions of time (EOT).
- Provisional sums.
- Administered by either CA or EA.
- NEC:
- Six main options including ‘mix and match’.
- Layman terms.
- No QS reference.
- Programme is part of the contract.
- Compensation events (CE).
- Time and cost claims covered within CE.
- No provisional sums.
- Administered by PM.