Contract Administration Flashcards
What is nomination?
- This is when the client has chosen a particular sub-contractor to carry out works.
- Provides the client with greater control of material choice and quality.
- In doing so, the main contractor is relieved of liability of design and compliance with the works that have been nominated.
What is a named sub-contractor?
- Is when the client provides the main contractor with a list of named sub-contractors for a portion of the works.
- Once appointed, they become a domestic sub-contractor.
- In doing so, this allows the client to have more control over quality and costs.
Can the contractor object to a nominated sub-contractor?
- Any objections need to be made during the tender period.
- The MC can reject if they have found out the nominated party is having financial difficulties or is going insolvent.
What is novation?
- It is the transfer of rights and obligations of one party to another.
- In doing, there is rescission of one contract for another.
- Novation can’t be done without consent.
- Is popular on D&B projects where the design team or part of the team is novated from the client to the contractor.
What is assignment?
- Unlike novation, this transfers the benefits under the contract from one party to another but not the burden.
- In doing so, the original contract still remains.
- Assignment does not require consent unlike novation.
What is consultant switch?
- As an alternative to novation, it transfers the consultants from working for the client to the contractor.
- In doing so, the original contract remains in place unaltered.
After a valuation, the certificate is issued, the client then advises they have insufficient funds to make payment, what do you do?
- As the certificate has been issued to the contractor, the client is obligated to honour payment and can’t withhold any monies without a valid reason.
- If this is the case, then contact the client and contractor ASAP to arrange a form of payment and if it can be delayed by a few days from the final payment date.
- Failing this, then the client would need to source the funds to honour the certificate.
Under a valuation, if a contractor is claiming for monies for materials off-site and there is no provision in the contract for claiming such monies, what would you do?
- Firstly I would inform the contractor there is no contractual provision for them to claim for monies of materials off-site.
- If the contractor is insistent for claiming these monies, I would then contact the client and advise they’re not contractually obligated to pay for these as these had not been set out in the contract originally.
- However, if the client, does wish for these to be paid, then an instruction would be needed for the valuation of materials off-site.
- I would then ensure the necessary provisions are in place for valuing materials off-site e.g. vesting certificate, insurances and etc.
What is the defects liability period?
- It is the period at the end of a contract usually 12 months after practical completion has been issued.
- During this period, the contractor rectifies any defects that arise within the structure at their own expense.
- In the event the contractor does not do this, then the client may employ another contractor to do so and recover the costs of doing so from the main contractor.
- The retention monies may be used to cover the costs for making good any defects.
What are patent defects?
- Defects that visible upon inspection during the commissioning stage.
What are latent defents?
- Defects that are not visible upon inspection and may occur some time after completion.
How do contracts deal with latent defects?
Usually claims can only be brought about during the limitation period which is 6 years if the contract is executed under hand or 12 years if executed under a deed.
What is a final account and what are the timelines associated with agreeing a final acount?
A final account is usually prepared upon completion of the works and it includes agreeing all financial aspects including any adjustments to the contract sum to determine the value of the project.
Note: A final account may not just be money owed to the contractor but could also entail money owed to the client.
In an unamended JCT SBC contract, usually the contractor submits all documents no later than 6 months after issue of PC Certificate. The CA or QS will prepare a final statement showing all adjustments no later than 3 months of receipt of documents from the contractor.
In an unamended JCT D&B contract, the contractor submits a final statement within 3 months of issue of PC Certificate. The due date for final payment is one months after receipt of the final statement to agree all adjustments.
What is the process of issuing a final certificate?
- CA/EA issues a schedule of defects to the contractor no later than 14 days following expiry of the rectification period.
- Contractor has reasonable amount of time to rectify defects.
- Once rectified, CA/EA will issue certificate of making good.
- CA/EA issued final certificate releasing 2nd half of moiety of retention.
- Due date for final payment is 1 month after issuing the latter of rectification period or issue certificate of making good.
Once the final certificate is issued, what is triggered?
- Release of the 2nd half of moiety of retention.