Procurement and Tendering Flashcards

1
Q

What is procurement?

A

The overall act/process of acquiring construction works and activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the factors affecting procurement choice?

A
  • Specifics of a project such as:
    • Design constraints.
    • Technical constraints.
    • Economic constraints.
  • Client objectives regarding:
    • Cost.
    • Time.
    • Quality.
    • Risk appetite.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main methods of procurement?

A
  • Traditional.
  • Design and Build.
  • Management contracting.
  • Construction management.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain traditional procurement and when it’s appropriate?

A
  • Traditional is when the design is completed by the client’s design team before tenders are invited and the main contractor is employed to build what the designers have specified.
  • It is most appropriate in the following scenarios:
    • The client has had the design prepared.
    • If the design is substantially complete at the time of contractor selection.
    • The client wishes to retain control over the design and specification.
    • If cost certainty is of importance.
    • Programme or rather the shortest overall programme is not of much significance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the advantages and disadvantages of traditional procurement?

A

Advantages:
- Retaining control over design can lead to higher quality.
- Increased levels of cost certainty before commencement.
- Changes are relatively easy to arrange and value.
- Competitiveness fairness and transparent process.
- Familiar and understood.
- Pricing can be simple and comparative through documents such as schedule of works and/or bill of quantities.
Disadvantages:
- Overall project duration is longer due to sequential process and no parallel working e.g. overlap of design and construction.
- Lack of buildability due to no early involvement of contractor.
- Strategy based on priced competition which can lead to adversarial relations.
- Dual point of responsibility - design with designers and construction with contractor.
- Incomplete design prior to tender could lead to reduced cost and time certainty.
- Client could be inclined to pay higher premium for works not identified such as refurb works.
- Client held responsible if discrepancy in BoQ, although this can be transferred through schedule of amendments (SOA).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Explain design and build and when it’s appropriate?

A
  • The contractor is responsible for the design, construction and planning of the works to the employer’s requirements.
  • It is most appropriate in the following scenarios:
    • There is a need to make an early start on site as it allows for parallel working where the design can overlap with the construction.
    • The client wishes to minimize their risk by transferring the design risk to the contractor.
    • Ideal for complex projects which can utilize the contractor’s expertise thereby enhancing buildability.
    • The client does not wish to retain control over the design.
    • Client intends to have a single point of responsibility.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the advantages and disadvantages of design and build procurement?

A

Advantages:
- Single point of responsibility.
- Early commencement on site.
- Early price certainty achieved prior to start on site provided ER’s are sufficiently described and changes are not introduced.
- Increased buildability.
Disadvantages:
- Difficulty in preparing ER’s to ensure design meets requirements.
- Client commits to concept design at an early stage.
- Variations from original brief are difficult to arrange and can be expensive.
- Contractor may prioritize cost and time over quality.
- Difficulty in comparing tenders and obtaining value for money as each design is different and prices and programme will vary across different designs, although this can be mitigated if the design has been progressed sufficiently by the client prior to tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How much design input will the contractor have?

A
  • This is dependent on the following:
    • How much of the design has been completed by the client prior to tender.
    • Can either be full design or production of information and coordination only.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who carries out the design for the contractor?

A
  • It may be outsourced to a separate design company.
  • The contractor may have an in-house design team.
  • The client may novate their design team to the contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Explain management contracting and when it’s appropriate?

A
  • When the works are constructed by a number of different works contractors who are contracted to a management contractor (MC) that contributes their expertise to design and manage construction for a fee.
  • It is appropriate in the following scenarios:
    • Where cost certainty is not important prior to start on site.
    • Early start on site is of priority.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the advantages and disadvantages of management contracting procurement?

A

Advantages:
- Overall project duration is shorter due to overlap of design and construction.
- Increased buildability through contractor contribution to design and planning.
- Changes can be accommodated in packages not yet let provided they have no further design impact.
- Works are let at competitive current market prices on a firm basis.
Disadvantages:
- Price for works is not received until final package is let.
- Changes to design of later packages could affect packages already let which could be costly.
- Little incentive for the MC to reduce costs.
- MC has little legal responsibility for the default of the works contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Explain construction management and when it’s appropriate?

A
  • When the works are constructed by a number of trade contractors that are in direct contractual link with the client but managed by a construction manager (CM) on a consultancy basis.
  • It is appropriate in the following scenarios:
    • Large complex projects where the CM’s expertise can be utilized.
    • Early start on site is key.
    • Flexibility in design and construction strategy.
    • Where cost certainty is not important prior to start on site.
    • Where the client is experienced in construction.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the advantages and disadvantages of construction management procurement?

A

Advantages:
- Overall project duration is shorter due to overlap of design and construction.
- CM can contribute to design and planning.
- Roles, risks and relationships of all parties are clear.
- Changes can be accommodated without having to pay for a premium.
- Prices may be lower due to direct contracts with trade contractors.
- Client has a means of redress to trade contractors through direct contractual links.
Disadvantages:
- Price for works is not received until final package is let.
- Changes to design of later packages could affect packages already let which could be costly.
- Requires the client to be proactive.
- Heavily admin based as client has many consultants and contractors to deal with.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does one identify the client requirements prior to recommending a suitable procurement route?

A

Have a detailed discussion with the client and design team to identify priorities/objectives in terms of cost, time, quality, risk, control and experience.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If the client wishes to start on site ASAP, what route would you recommend?

A

My recommendation would need to take into account other factors such as cost, quality and risk appetite.
If time was the only driving factor then I would suggest either management contracting or construction management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If the client wishes for an early start on site and cost certainty, what route would you recommend?

A
  • Design and build would offer the best solution.
  • As well as allowing parallel working through overlap of design and construction it is based on a lump sum price thereby giving the client cost certainty.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a lump sum contract?

A

It is the most traditional and most common form of procuring construction works.
In simple terms, a lump sum contract is when a price for all the works is agreed before the works are executed.
That is not to say that it is a fixed price however there is more certainty over the final cost as there are mechanisms that allow the sum to change such as variations, change to scope of works and etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is Guaranteed Maximum price and what does it mean?

A
  • It is a lump sum contract under which there is no adjustment to the tender price unless design changes are requested by the client.
  • The contractor includes the additional risk involved in the design development process in his tender price.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the risks associated with lump sum forms of contract?

A
  • Gives greater risk to the contractor as there are fewer mechanisms for them to adjust price.
  • Due to the increased risk profile, contractors may be inclined to increase their tender price.
  • Preparing the tender may be more expensive for the contractor which is heightened if unsuccessful in their bid.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the risks associated with GMP contracts?

A
  • Heightened risk profile for the contractor as they’re not able to exceed the budget stated.
  • Any costs that exceed the budget are borne by the contractor which can eat into their profits.
  • Could potentially lead to contractor insolvency due to increased risk profile.
  • Contractor will be inclined to increase their tender price to pick up for any fluctuations in price which can be problematic on projects with a long programme.
  • Fewer mechanisms for costs to change such as client requested changes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is tendering?

A

The process of obtaining a cost for the works in addition to the method of appointing a suitable contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the main methods of tendering?

A
  • Open tendering.
  • Selective tendering:
    • Single Stage.
    • Two Stage.
  • Negotiated tendering.
  • Serial tendering.
23
Q

What is open tendering?

A

Is the process of allowing any tenderer to submit a bid for the works and there are no entry requirements to be invited to tender.
In doing so, projects can be advertised through public portals such as technical press, local papers/council sites and etc.

24
Q

What are the advantages and disadvantages of open tendering?

A

Advantages:
- Provides opportunities to companies which the client may not have previously considered.
- Offers greatest level of competition from the open market as there is no restriction to a pre-selected list of tenderers.
- Ideal for new emerging tenderers to secure works.
Disadvantages:
- Relatively slow and costly due to attracting relatively large number of tenderers.
- Risk of tenderers being unsuitable for proposed works or to meet the employer’s requirements.
- Some tenderers could be inexperienced as well as financially unstable.

25
Q

What is selective tendering?

A

Unlike open tendering, selective tendering restricts the number of tenderers to a pre-selected list of tenderers to bid for the works.

26
Q

What is single stage tendering?

A

Is the most traditional route of tendering where all the information necessary to calculate a realistic price for the works is available and is issued to a pre-selected list of capable tenderers.
In doing so, tenderers are pre-selected based on:
- Financial standing.
- Qualifications and certifications.
- Previous track record, history.
- References.
- Organisational structure.
- Capacity and resources.
- Size of work previously undertaken.

27
Q

What are the advantages and disadvantages of single stage tendering?

A

Advantages:
- Offer is based on most competitive price.
- Client is able to obtain a lump sum for the works.
- Ensures only capable tenderers submit a tender.
- Reduces the aggregate cost of tendering if pricing documents are provided to enable lean tendering analysis.
- Reduces risk of receiving tenders from firms that are unsuitable for the works.
Disadvantages:
- Programme implication to include tender period.
- No buildability from contractor.
- Price is heavily reliant on quality and accuracy of information issued to contractors.
- Tenderers are reluctant to engage in single stage tenders due to bidding risk and the process of it being long and costly.

28
Q

What is two stage tendering?

A

The client first seeks to appoint a contractor based on outline scope of works that are not fully defined.
Then the selected contractor is engaged under a pre-construction services agreement (PCSA) to further develop the design and agrees a price.
It is ideal on projects where the client could use the contractors expertise to enhance buildability as well as early contractor involvement.

29
Q

What is the purpose of the first stage of two stage tendering and what is submitted?

A
  • Client provides an outline project design to each of the tenderers.
  • Tenderers will submit the following:
    • Schedule of rates that will be used to calculate a realistic price during stage 2.
    • Price for assisting the client with design development and buildability expertise during stage 2 (PCSA) on a consultancy basis.
    • Confirmation of OH&P.
    • Quality of team.

The tenderers submit:
- A detailed build-up of prices for the preliminaries.
- Percentage additions for OH&P.
- Construction programme.
- Proposed sub-letting of the works.

30
Q

What is the purpose of the second stage of two stage tendering?

A

The appointed tenderer then enters into a PCSA with the client on a consultancy basis to further develop the design and obtain the following:
- Fixed lump sum.
- Contract conditions.
- Programme.

31
Q

What are the advantages and disadvantages of two stage tendering?

A

Advantages:
- Early contractor involvement and enhanced buildability.
- Enhanced project team collaboration during second stage.
- Programme benefit as there is overlap of design and tender.
- Possibility of early start on site.
- Contractor can help identify and manage risk.
- Greater client involvement in selecting supply chain.
Disadvantages:
- Risk of cost certainty not achieved during second stage thereby leaving the client with no fallback option.
- Lack of competitiveness during second stage.
- Contractor not obligated to submit a second stage tender.
- Contractor could take advantage of second stage negotiation and increase costs.
- Additional fee incurred for PCSA period.
- Risk of re-tendering if parties do not agree.

32
Q

How can a client retain some degree of negotiation during the second stage of a two stage tender?

A

The roles and responsibilities under the PCSA can be clarified to give the client a greater degree of negotiation during the second stage as they will be able to set the terms and conditions of the parties.
Also the consultant team (QS) will work collaboratively with the contractor and review packages of works on an open tender basis and compare so an average and competitive price can be obtained.
The QS can also engage with the selection of the sub-contractors too.

33
Q

When should two stage tendering be used?

A
  • With complex projects.
  • Where a significant magnitude of work is unknown at time of contractor selection.
  • When early completion is priority.
  • Where the design team can make use of the contractor’s expertise on buildability issues.
34
Q

What is negotiated tendering and when is it used?

A

This is when the client has a preference for appointing a specific tenderer and negotiating with only one.
It is used when there is already an existing relationship between the client and tenderer based on previous works undertaken.
The contract sum is arrived through a process of negotiation and a schedule of rates or prices from previous projects may be used as a basis for negotiating a price for the works.

35
Q

What could selecting the wrong contractor lead to?

A
  • Bad client and contractor relationship.
  • Dissatisfied client.
  • Insolvent contractor.
36
Q

What are included in a set of tender documents?

A

According to the JCT tendering practice note 2017:
- Invitation to tender (ITT).
- Instruction to tenderers with:
- Date and time for return, to whom, site visits, programme, errors procedures, scoring matrix.
- Conditions of proposed contract.
- Pricing documentation.
- Specifications.
- Drawings.
- Project information (preliminaries/works information/employer’s requirements).
- Typical appendices (Pre-Construction information/H&S information/Planning and etc.).
- Form of tender.

37
Q

What is a form of tender?

A

It is a document which the tenderer includes when submitting their bid in which they state their name, address, and sum of money for which they offer for delivering the works.

38
Q

What are the Employer’s Requirements?

A
  • Document/s that set out the client’s requirements such as function, size, accommodation and quality requirements of the project.
  • The level of detail is dependent on how much design has been developed prior to tender.
  • May include the current state of planning permission.
  • It will also include the level of design, structure and specification required by the tenderers.
39
Q

What are the contractor’s proposals?

A
  • It is the contractor’s response to the employer’s requirements.
  • It is a key document to consider during the tender review.
  • Will include drawings and specifications of materials and workmanship.
40
Q

What is typically included within a prequalification questionnaire (PQQ)?

A
  • Company details and legal status.
  • Details of insurance, provision of bonds, warranties and PCG’s.
  • Financial information, accounts.
  • Relevant experience and key personnel.
  • H&S information.
  • Capacity/Workload/Capability.
  • References.
  • Management and organisational structure.
  • Quality assurance and environmental policies.
41
Q

What was the value of the error you identified in the GMV 401 & 403 tender and how did this affect the price?

A
  • The value of the error was approximately £4,000.
  • I addressed this to the contractor through the post tender query process and they accepted the error and adjusted their price accordingly, albeit, in the grand scheme of the works, it did not affect the price much.
42
Q

What option was available for error checking on GMV 401 & 403?

A
  • Alternative 2.
43
Q

What is the risk associated with alternative option 1 for error checking?

A
  • The tendered price prevails and the tenderer is invited to either accept or withdraw from the tender.
  • If the tenderer accepts then documents need to be amended to reconcile the error.
44
Q

On 2PWR, you mentioned you advised on traditional so the client could maintain control of the design. Could this not also be done if they opted for a D&B route also?

A
  • It could be achieved if the project was tendered via a two-stage D&B route. When the chosen contractor is employed under a PCSA, the client can set the terms and conditions under the PCSA and who controls what aspects of the design.
  • Alternatively, it could be tendered at stage 4 where majority or all of the design is complete prior to tender.
  • However, given majority of the design had been developed at the time and only a few elements were outstanding therefore a traditional route was considered more suitable with elements of CDP.
  • Also, due to strict budgeting pressures it was imperative to obtain cost certainty prior to start on site. This was of more significance to the client than having the overall shortest programme.
  • Lastly, the contractors appetite of risk on a complicated D&B project could risk not getting contractors to tender due to level of uncertainty of the existing site conditions.
45
Q

On 2PWR, what was the reason you advised on the client adopting a traditional procurement route?

A
  • Client was insistent of retaining control of the design to ensure quality.
  • Obtaining cost certainty.
  • Risk of D&B that the contractor will prioritize cost and time over quality.
  • Risk of not getting contractors to tender on a complicated refurbishment project.
  • Risk of contractors submitting a relatively high tender when there was already budgeting constraints.
46
Q

You further assisted the Client’s PM in preparation of the tender documents namely the schedule of works (SoW) to assist pricing and analysis. What are the risks associated with using a schedule of works (SoW)?

A
  • It can be difficult to assess tender returns if there are significant variances on certain items between different tenderers as there are no pre-determined quantities.
  • Also, in some instances contractors can front load their price to aid their cashflow.
47
Q

What are the risks associated with using a bill of quantities (BoQ)?

A
  • The client takes liability of any quantities scheduled in the works as oppose to the contractor.
  • Any discrepancy in the bill is borne by the client.
  • Can be time consuming and costly to produce to ensure accuracy of information contained within.
  • However, it helps provide a better comparison for analysis as tenderers will only be compared against their different rates.
48
Q

On GMV 401 & 403, what information did you include within the pre-qualification question (PQQ) when shortlisting suitable contractors?

A
  • Company details and legal status.
  • Details of insurance, provision of bonds, warranties and PCG’s.
  • Financial information, accounts.
  • Relevant experience and key personnel.
  • H&S information.
  • Capacity/Workload/Capability.
  • References.
  • Management and organisational structure.
  • Quality assurance and environmental policies.
49
Q

Why should tenders be opened by more than one person including by individuals from different organisations?

A
  • To prevent any collusion.
  • To be open and transparent.
  • To ensure fairness to all tenders submitted.
  • To prevent any conflict of interest.
50
Q

How do the tender documentation vary from a traditional and design and build procurement?

A

Traditional includes the following:
- Bill of quantities or pricing document.
- Preliminaries.
- Design information.
Design and Build includes the following:
- Employer’s Requirements.

51
Q

What did the tender documentation on 2PWR consist of?

A
  • Invitation to tender (ITT).
  • Form of tender (FOT).
  • Client guidance for tenderers.
  • Award criteria.
  • Scoring matrix.
  • ER’s - consisting of:
    • Pricing documents (SoW).
    • Fees breakdown.
    • VE Schedule.
    • Preliminaries.
  • Specification - consisting of:
    • Drawings.
    • Pre-construction information.
    • Building control statement.
    • Indicative programme.
    • Fire strategy.
    • Planning.
  • Proposed Contract documents:
    • JCT SBC XQ 2016.
    • Schedule of Amendments.
52
Q

If a project is tight on programme and the design is incomplete what advice would you give to your client?

A

If programme is tight then I would advise the client to proceed with the tender based on the information available to date and any subsequent information would follow as an addendum.

53
Q

What information did you include within the tender report for GMV Bugsby Way?

A
  • Introduction to the project.
  • Tender procedure.
  • Tenderer’s return packages.
  • Tender review including arithmetical check, post tender queries.
  • Summary of final offers.
  • Commentary on programme.
  • Recommendation.
  • Appendices/Supplementary Information:
    • Tender addenda.
    • Tender opening form.
    • Post tender queries schedule.
    • Tender sum analysis comparison.
54
Q

On what basis did you advise on the selection of the proposed tenderer?

A

The tenders were reviewed by myself and others and using a scoring matrix, each tender was evaluated against the multiple criteria and assigned scores which were collated and an overall score was assigned which led to the recommendation of the proposed tenderer. In summary, the split of the scores were as follows:
- Cost - 60%
- Quality - 40%
Scores of the tenders:
- JB Riney - 35%
- SB Civils - 75%
- EVO - 85%