Design Economics and Cost Planning Flashcards

1
Q

What is design economics?

A

It is the study of how changes in a building affect costs for example:
- Design factors:
- Building shape
- Circulation space
- Height and etc.
- Site factors:
- Location
- Topography
- Economic factors:
- Amount of construction work involved
- Availability of resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain to me your understanding of how design factors such as building shape affect costs?

A

The simpler the shape of a building, the lower the cost due to the simplicity of the design. The most efficient design is a square or rectangular shape as oppose to an L-Shape and etc.
The reason for this is because an L-Shape building would require more external wall to encapsulate the same floor area than a square or rectangular shape building would.
More excavation would be required due to the additional perimeter of the building.
This would increase costs for drainage such as pipe runs.
There would also need to be additional roofing too.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain the same for circulation space?

A

This is also referred to as dead space which can inadvertently affect profitability of a built asset. The reason for this is because circulation space involves costs such as air-conditioning, lighting, decorating and etc.
Therefore reducing circulation space from an economic layout can help drive profitability as this affects net internal area (net lettable/useable area) of a built asset.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain the same for height?

A

The more height there is in a building will incur additional costs such as vertical transportation (lifts, stairs).
It also affects other factors such as substructure as the taller the building is, will impose more load which would require extensive foundations to support the building.
Important point to note, less storey’s does not always entail cost savings. Costs can also be minimized by reducing plan sizes and increasing building heights.
However, there comes a point where the building has reached a height which should not be exceeded as the costs far outweigh the need for an additional storey.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain how site factors such as location affect costs?

A

Urban/Metropolis areas such as cities will attract higher value compared to rural areas due to higher wages, access costs, material storage, cost of land and etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Explain the same for topography?

A

Depending on the nature of the site, ground conditions, obstructions and etc. will impact design and construction of a built asset which subsequently affects costs.
Brownfield sites such as sites which have previously been built on are likely to incur more costs due to demolition, site clearance and remediation costs. Other site factors include slopping and grounds with poor loadbearing capacity which could indicate extensive foundation works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Explain how economic factors such as amount of construction work involved affects costs?

A

This is determined by the cost of productivity of the resources employed in its production. Such costs include:
- Labour
- Materials
- Plant
- Competition and etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Explain the same for availability of resources?

A

This comes down to the capacity of the contractors being able to carry out the entire works in-house and not having to outsource elements/portions of the works to sub-contractors.
In addition, locality is also important as it can minimize unnecessary costs such as transportation, accommodation and etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You mention in your document that you’re aware of NRM. Why do you use NRM for preparing cost plans/estimate?

A
  • I use NRM as it is considered as best practice by competent and conscientious practitioners in the industry.
  • It can also serve as a form of defence should a client make a claim against me.
  • It also provides a consistent basis for preparing cost plans/estimates which gives added confidence to the client.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is wall-to-floor ratio?

A
  • It is the relationship between the wall area and floor area to show the cost efficiency of the building.
  • The lower the ratio, the more cost efficient it is as there is less external wall to construct in comparison to floor area.
  • It is more expensive to construct an external wall than it is to lay screed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is an ideal wall-to-floor area ratio?

A
  • Office buildings - between 0.4/0.5, less than 0.4/0.35 is regarded as very efficient.
  • Residential buildings - between 0.45/0.6, less than 0.4 regarded as very efficient.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is net-to-gross ratio?

A
  • It is the relationship between a building’s lettable and non-lettable area.
  • Net-to-gross = GIA/NIA, where:
    • NIA = Net Internal Area
    • GIA = Gross Internal Area
  • In doing so, it also helps understand what is considered as common areas such as stairways, corridors, lifts and etc.
  • Typically the higher the ratio, the more lettable area there is which in turn drives productivity for the Client.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an ideal net-to-gross ratio?

A

Office buildings - between 0.7/0.8, note, that this will vary depending on the height and number of storeys of the building.
Residential buildings - between 0.8/0.85.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is cost planning/estimating?

A
  • It is about establishing if a project is affordable.
  • In doing so, one sets a realistic cost limit which represents a fair price for the project.
  • Deciding how the money is being spent and where and for its intended purpose.
  • Determining option costings such as alternative building types or building designs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between an order of cost estimate (OCE) and a cost plan?

A
  • An OCE or cost estimate is a document that is prepared at a given point in time. Typically prepared earlier in the design process between RIBA stages 0 to 2. Usually prepared with limited design information and priced on either a cost per m2 or functional unit basis.
  • A cost plan is an evolving document and usually prepared from RIBA stage 2 onwards. As the design develops, more information/detail can be inserted into a breakdown of costs such as sub-structure, superstructure and etc. to set a more realistic cost limit for the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between cost and price?

A
  • Cost is the total of the following:
    • Labour
    • Plant
    • Materials
    • Management for a specific activity.
  • Price is the amount a purchaser or client will pay for an item or product and is made up of the above costs including any overheads and profits (OH&P).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What would you do if a cost plan exceeds the project budget?

A
  • Analyse the costs to assess the source/origin of the increase and identify whether any element is abnormally high against the OCE.
  • When the element is identified that is driving the cost high then methods such as value engineering (VE) can be suggested as an option to the client and design team to bring the cost within budget.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the format of a feasibility estimate or OCE?

A
  • Typically presented on a cost per m2, functional unit or elemental basis.
  • Could also be presented on a range for example £700-£800/m2.
  • Can also be based on elemental rates of a building such as sub-structure, frame, external wall and etc.
  • Any site abnormal costs or enabling works are considered to.
  • Includes for preliminaries, contingency, inflation and location factor adjustments.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is a functional unit?

A
  • It is a unit of measurement that considers the prime/intended use of a building.
  • For example in a hotel or hospital a functional unit could be expressed as cost per bedroom or cost per bed respectively.
  • In a retail space a functional unit could be expressed as net lettable retail space.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Where would you get your rates from for a preliminary estimate?

A
  • Previous similar projects and historical data such as previous tender submissions or a contract sum analysis.
  • Other sources would include estimating pricing books such as Spons/Laxtons, Building Cost Information Service (BCIS) or specialist contractors/supplier quotations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What information do you need to carry out an OCE?

A
  • Building location.
  • Type of building.
  • Floor area or number of functional units.
  • Storey height.
  • Initial floor plans, roof plans, elevations and sections.
  • Indication of specification and quality.
  • Indicative programme, procurement and contract strategy.
  • Budget and cashflow constraints.
  • Site/Ground conditions.
  • Indicative M&E design.
  • Details of professional fees, development costs, VAT and treatment of inflation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the principal components of a cost plan?

A
  • Construction costs.
  • Preliminaries.
  • Contractor’s OH&P.
  • Contingency.
  • Inflation.
  • Assumptions.
  • Exclusions
  • Area Schedule.
  • List of drawings and specifications adopted.
23
Q

Name some typical exclusions from a cost estimate?

A
  • Professional fees.
  • VAT.
  • Client decant costs.
  • Loose fixtures and fittings.
  • Inflation (if programme is known then usually inflation would be included).
  • Site acquisition costs.
  • Section 106 agreements.
  • Removal of asbestos.
24
Q

Why is VAT excluded?

A
  • Because different clients will incur different levels of VAT, for example charities may not incur VAT.
  • As a QS, I am not a VAT advisor and therefore advise should be sought from a qualified VAT advisor.
25
Q

What is contingency?

A
  • A sum of money included within an estimate to deal with unknown circumstances or unmitigated risks during the project.
26
Q

How is contingency assessed?

A
  • During the early stages of a project a contingency allowance can be included as an overall percentage of the estimate.
  • As more detailed information becomes available a risk register can be compiled with each risk assigned it’s own probability and cost impact. The total cost from the register can then be inserted into the cost plan.
27
Q

What is TPI and when should one take account of it when preparing an OCE?

A
  • TPI is tender price inflation. It reflects the changes in the level of pricing contained in the lowest accepted tenders for new work to take account of market conditions and compares against base rates.
  • The price adjustments take into account the level of inflation depending on current and forecasted market conditions.
  • It would be factored in from the estimate base date to the anticipated tender return date.
28
Q

When should one take account of construction inflation when preparing an OCE and why?

A
  • It would be factored in from the date of the tender return to the mid-point of construction.
  • The reason why is because by mid-point much of the major works packages would have been procured and so inflating to mid-point accounts for the fluctuations in materials, labour and plant during that period.
29
Q

What is meant by base date within a cost estimate?

A
  • It refers to the date on which rates and prices contained within the estimate are based on.
  • This can help with the basis of calculations such as adjusting for inflation when using rates for other projects. The base date can be used as a starting point from which inflation can then be used to adjust accordingly.
30
Q

Where can TPI be obtained from?

A
  • BCIS.
  • Some large consultancies produce their own in-house tender price forecasts.
31
Q

When adjusting prices, what adjustments do you allow for?

A
  • Inflation.
  • Location.
32
Q

Why do you need to adjust for inflation?

A

This is to ensure accuracy of information that is presented to the client as well as ensuring the project remains within the cost limit established.

33
Q

Why do you need to adjust for location?

A

Prices vary according to regions and location is necessary to account for changes in cost of materials, labour and plant.

34
Q

What is Value Engineering (VE)?

A

It is a method at providing the necessary functions of a building and delivering the client’s objectives at the least possible cost without compromising quality, reliability, performance or delivery.
Examples of this include:
- Reduction in scope of works.
- Alternative materials/products.

35
Q

What is Value Management (VM)?

A

It is a strategy for defining what value means to a client and putting procedures in place that ensure the client obtains maximum value every time.
VE is a tool of VM in that it is a reactive procedure to bring the anticipated cost of the development back in line with the budget when a potential overspend is identified.
Other examples of VM include:
- Identifying items which can be omitted or serve no benefit to the client and are just considered a cost surplus.
- Identifying items that can have their specification changed.
- Identifying items which could later be reinstated in the programme provided there is budget to allow this.

36
Q

What is value and what does it mean?

A
  • It is a measure of worth taking into account the overall usefulness and benefits that are delivered in relation to the cost being paid for it initially.
  • Value differs from client to client.
  • For example a short term developer looking to sell a building on completion will place greater value on a cheaper out-turn cost whereas an occupier will place more emphasis on higher quality and lower operating costs.
37
Q

What was the location factor on 91-113 Powis Street and the inflation factors?

A
  • Location factor - Outer London Borough - Greenwich - 124 index.
  • Inflation factors:
    • Option 1 - Mid-point April 2023 - 355 index - 5.65% increase
    • Option 2 - Mid-point September 2023 - 358 index - 6.55% increase
    • Option 3 - Mid-point December 2023 - 363 index - 8.04% increase
38
Q

Name three exclusions from the estimate you prepared for 91-113 Powis Street?

A

General exclusions from all options:
- Land costs.
- Professional fees.
- VAT.
- S.106 contributions.
- Legal fees.
- Asbestos removal/contamination unless stated.
- Option 1:
- Works to existing fence to rear of development.
- Structural modification to existing superstructure.
- Walls, floors and ceiling finishes to existing retail units.
- Option 2:
- Facade retention to facade being retained.
- Below ground attenuation tank.
- Repairs to existing MEP services.
- Underpinning to existing nearby foundations.
- Option 3:
- Below ground attenuation tank.
- Repairs to existing MEP services.
- Underpinning to existing nearby foundations.

39
Q

What was the location and inflation factor for GMV 401 & 403?

A
  • Location factor - Outer London Borough - Greenwich - 124 index.
  • Inflation factors:
    • Stage 3 OCE - BCIS Base Date March 2022 ((394-349)/349) - Mid-point Q42024 - 13% BCIS uplift.
    • Stage 3 OCE Alban In-house TPI - 11.75%.
    • Stage 4 PTE Alban In-house TPI - 4.63%.
40
Q

What were the construction costs and cost/m2 on GMV 401 & 403?

A

Stage 3 OCE:
- Construction Cost approximately £72.6m
- £/m2 approximately £3,048/m2
Stage 4 PTE:
- Construction Cost approximately £73.6m
- £/m2 approximately £3,075/m2

41
Q

Name three exclusions from the stage 3 cost plan for GMV 401 & 403?

A
  • UXO surveys and delays associated if found.
  • Extra over costs for FF&E to show Flats/Marketing Suites.
  • VAT.
  • Professional Fees.
  • Legal Fees.
  • Underfloor Heating to Affordable units.
42
Q

What were the construction costs and cost/m2 on 91-113 Powis Street?

A
  • Option 1:
    • Construction Costs - £3m
    • £/m2 approximately £1,437/m2
  • Option 2:
    • Construction Costs - £10.7m
    • £/m2 approximately £3,223/m2
  • Option 3:
    • Construction Costs - £20.4m
    • £/m2 approximately £3,471/m2
43
Q

What was the location and inflation factors for 2PWR?

A
  • Location factor - Inner London Borough - Camden - 130 index.
  • Inflation factors:
    • Stage 4 OCE - Base Date March 2023 - Mid-point Q42023 - 388 - 2% uplift.
44
Q

What were the construction costs and cost/m2 on 2PWR?

A

Stage 4 PTE:
- Construction Cost approximately £2.67m
- £/m2 approximately £2,968/m2

45
Q

Name three exclusions from the stage 4 cost plan for 2PWR?

A
  • Site investigation costs.
  • Professional fees.
  • VAT.
  • Repairs to neighbouring owners roofs.
  • Raised access floor system.
  • Graphics/Images on wall.
46
Q

What were the cost variances on 2PWR and what was the overall difference between the cost plans?

A

Substructure:
- additional works to forming ground floor R/C slab.
- rates updated to reflect current market conditions.
Frame:
- Additional beams/lintels
Upper floors:
- Additional floor/ceiling joists allowed for.
Roof:
- Forming openings for ductwork.
- Introducing turret works.

Overall difference from previous stage 3 estimate to stage 4 PTE was approximately circa £20k uplift in costs.

47
Q

How did you go about collating the benchmarked data of other projects and presenting them to the Client?

A
  • I trailed through various projects and captured their headline information such as location, GIA, no. of apartments and a brief description of the type of project.
  • I also noted the duration of the programme in weeks and the number of storeys of the building.
  • For costs I noted the contract sum for some of the projects which were either complete or currently undergoing works. As for others which have either recently been tendered or a stage 3/4 cost plan had been produced I noted our figures for the estimates/cost plans produced.
  • For on costs I inserted the main contractor’s preliminaries and OH&P and retrospectively calculated the percentage uplifts of these costs.
  • Lastly, before presenting to the client I made sure to remove any sensitive information regarding each project as each project was to a specific client and I ensured to remove any information which could be traced back to the original client.
48
Q

What is benchmarking and why is it so important?

A
  • Benchmarking is a tool for measuring project performance such as costs against a point of reference to determine whether value for money is achieved.
  • It is important for a number of reasons such as:
    • Improve predictability/forecasting.
    • Can inform decision making.
49
Q

You mentioned that you used historical data for the benchmarking exercise, what other sources of cost data are you aware of and why weren’t these used?

A
  • Other sources of cost data include:
    • Pricing books such as Spons and Laxtons.
    • BCIS.
    • Supplier quotations.
  • The reason why these weren’t used because at Alban we had historical data of past projects that we have worked on and are considered the most reliable.
  • In addition to that, it had been market tested as some of the projects had either been delivered/completed or just recently had their tenders returned from the market.
50
Q

How can costs be used to control the design process?

A
  • As the design develops and more information/detail is available, budgets can be allocated to specific elements of a building. These can then be compared to previous projects of a similar nature to benchmark against to ensure the costs are within an acceptable limit of that particular element.
  • Through regular design team meetings, this information can be fed to the wider project team and inform them of the cost limits of that particular element and any design changes could result in either a cost surplus or reduction.
51
Q

What is the current inflation rate of 2024 and what would you allow on cost plans for 2025?

A

Current index 1Q2024 = 390
- On year = 2.9%
- On Quarter = 0.5%
Future index 1Q2025 = 398
- On year = 2.1%
- On Quarter = 1.0%

52
Q

Why was there a difference in inflation across the three options for 91-113 Powis Street?

A
  • There was a difference in inflation because each of the three options varied in levels of work which incurred different lengths of programme and the inflation was to the mid-point of construction for each of the different options.
53
Q

Why do you inflate to the mid-point of construction for?

A

The reason why is because by mid-point, all of the procurement, specifically, the major works packages would have been procured in order to give better indication of a fixed price. Therefore inflating to mid-point accounts for the fluctuations in materials, labour and plant from the tender return date up to the mid-point of construction.

54
Q

On GMV 401 & 403, why did you only adjust for inflation and not location?

A
  • I only adjusted for inflation as the data used to prepare the cost plan was taken from a project that was within the same locality as GMV 401 & 403 and was in fact a similar scheme for the construction of residential blocks.