Project Finance Flashcards
What is cost control?
The process of managing a projects finances and planning for potential financial risks.
How do you control and monitor cost during a project?
- Regular cost reports in format agreed with the client
- End of stage cost reports by QS
- Contractor cash flow monitoring
- VE exercises
- Minimising change and defining provisional sums
- Regularly update cost plan
- Monitor construction risks
What is a cost plan?
- Plan that determines the fiscal feasibility of a project
- Sets out the life cycle budget - provides an estimate of what the project cost will be
- Sets out cost control methods
- Set over a certain period of time
Why is it important to effectively manage cost during the construction phase of a project?
- Role of PM is to ensure project success in regards to time, cost and quality
- Important to deliver the project within the agreed budget through controlling and monitoring costs
- Advise the client of appropriate risk allowances with the QS and project team and capture these within the CapEx
- Ensures client can plan their internal finances effectively
- Assist with staying on top of project costs - risk mitigation
What are the processes / mechanisms for establishing a project budget?
- CapEx and reporting
- Cash flows
- Value management and engineering
- Design reviews
- Early warning process
- Change control procedures
- Clear project brief
- Project execution plan
- Cost plans and cost trackers
How do you report and forecast during the construction phase? Think L2 - Blossom Street e.g.
- QS produces a cost report, tracking spend vs agreed sum
- Identifies monthly burn rate driven by programme - what works are being done and associated cost
- Contractor issues cashflow forecast, aligning with works programme
- Monthly review meetings of programme and cost review, with work inspections
- Payment process includes mechanisms to ensure works have been done (and in line with ER’s / works information)
How would you reduce costs in a project?
- Value engineering
○ Process of reducing cost without affecting function or quality
○ Achieving best value design in line with strategic objectives identified in the value management process
○ Value engineering focuses on:
§ Building space/ area
§ Building elements and components - Can be done in RIBA stage 2,3 and 4
What is value management?
- Conducted in the initial stages of a project to define what value means to the client and how this will be achieved
- RIBA stages 0 & 1
- Defining what value means to the client in the briefing process e.g. quality of fit out or functionality of the building
- Setting objectives and carrying out options appraisals that help identify how value can be maximised
- Understanding what aspects of the brief can and cannot be changed
Impact of legislation on project cost?
- Legislation may change the design requirements or which products can be used, therefore driving up costs and requiring contingency
- For example, new legislation came in after Grenfell banning the use of combustible materials on external facades, driving up design costs e.g. ‘the bug’ on Fitzroy Street
Tell me about payment under construction contracts and any relevant legislation you are aware of?
- Payment under construction contracts / invoicing is defined by the construction acts:
○ Housing Grants, Construction and Regeneration Act 1996
○ Local Democracy, Economic Development and Construction Act 2009 - Relatively uniform across construction contract forms, this is in order to maintain solvency down the supply chain and to eradicate ‘pay when paid’ culture
- Allows for interim, periodic or stage payments
What is the typical payment process under a construction contract?
- Application made by contractor for works done since last interim
- Site walk held with PM/ QS/ contractor QS and EA/CA
- PM or EA/CA will review application and either certify it or issue a pay-less notice
- Invoice issued in line with the valuation
- Payment must be made in line with payment date as outlined in the contract
- If payment not made by the date then contractor has the right to suspension under Construction Act ‘09
What did the Housing Grants, Construction and Regeneration Act 1996 do?
- Includes provisions to ensure that payments are made promptly through the supply chain. Provision includes ‘the right to be paid in interim, periodic or stage payments’
- Payment due date – the date provided within the contract as the date on which payment is due.
- If payment is not made on or before the final date for payment the payee can give notice under section 112 of the Act to suspend performance of the contract.
- The payer (Client) must issue a payment notice within five days of the due date for payment, even if no amount is due, setting out the sum that the payer considers to be or to have been due at the payment due date, and the basis on which that sum is calculated.
- Key changes included:
- Remove ‘pay when paid’ culture.
- Allows for interim, periodic or stage payments
- Gave all a right to arbitration
What is change control?
The tools to record change
Why is change control important?
- Change can be managed through a system including: undertaking SI, confirming client brief, identifying risks, considering relevant legislation
- Managed through compensation events/ relevant events & matters
Where would a change control process be documented on a project?
- The change control process would be set out in the project execution plan
- It would then be formally documented either:
- Through the project brief - until RIBA stage 2
- Post RIBA stage 2:
Change control tracker
EW system
Process for agreeing change control processes on a project?
- Building contract wouldn’t usually stipulate a process for implementing change
- Good practice to agree a process with the contractor pre-contract and this should be include agreeing the contents of a pro-forma, means of controlling and recording requests and the process for signing off costs before any changes are instructed
- QS should provide initial cost estimates for any proposed change to inform the client of likely costs
- EA should always obtain written confirmation from the client of acceptance of the contractors price before issuing an instruction
- On major projects - regular change control meetings are recommended to discussed progress on change requests and to agree instructions
- Duty of EA to confirm if an instruction constitutes a change
Talk me through a typical change control process? (D&B)
Employer led change
- EW raised
- EA fills out change request form and issues to contractor
- EA logs change with CRF number
- Contractor confirms any cost, programme and quality implications within typically 10 days of initial CRF being raised
- EA reviews with employer, QS and CMT
- Approved / rejected
- Instruction issued
Contractor led change
- EWN raised and issued to EA
- EA reviews to assess whether a change under the contract
- EA rejects / approves
- If approved
§ Contractor completes CRF and issues to EA
§ EA logs change and provides CRF number
§ Contractor confirms any cost, programme and quality implications within typically 10 days of initial CRF being raised
§ EA reviews with employer, QS and CMT
§ Approved / rejected
- Instruction issued
What is a cost plan?
- Presents the estimated cost into a structural elemental or functional format
Shows how the design team proposes to distribute the funds available on the elements of the proposed building.