Project Finance Flashcards

1
Q

What is the contract sum?

A
  • Amount specified at the outset (ex VAT) for completion of the works
  • Can only be altered as the work proceeds according to the contract conditions (changes, loss and expense, expenditure against provisional sum, acceleration, fluctuations)
  • Errors in the computation of the contract sum, whether arithmetic or not, are deemed to be accepted by both parties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are preliminaries and what are included as standard (NRM2)?

A

Items that are not directly related to any component, element, or work section (i.e. measured works). Split in contract between:

1) Information and requirements
2) Pricing schedule

Includes as standard:

  • management/staff
  • site establishment
  • security
  • safety and environmental protection
  • control and protection
  • mechanical plant
  • temporary works
  • site records
  • completion and post-completion requirements
  • cleaning
  • fees and charges
  • insurances, bonds, guarantees and warranties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is an order of cost estimate?

A

A high-level cost estimate usually based on a single quantity (e.g. cost per m2)

  • Determines possible construction costs of project
  • Used to establish whether project is viable
  • Makes employer aware of likely financial commitment
  • Completed in RIBA Stages 0&1
  • % for professional fees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a provisional sum and how is it expended?

A

A provisional sum is an allowance included at tender for a specific element of the works that is not yet defined in enough detail to accurately price.

Needs to be instructed (JCT) by Contract Administrator and should be add/omit on instruction.

Defined: PS accounted for in contractor’s price and programme. Prelims assumed to be included.

Undefined: Might relate to work not designed. PS not accounted for in contractor’s price, client takes the risk and contractor may be entitled to EoT and loss/expense.

No PS in NEC contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of cost planning?

A
  • Ensure employers are provided with value for money
  • Make employers and designers aware of the cost implications of their proposals
  • Keep expenditure within cost limit approved by the employer
  • Provide robust cost information upon which the employer can make informed decisions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a cost plan?

A
  • Estimated cost into a structural element or functional format
  • Provides a comprehensive economic picture of the whole building project
  • Used by the QS to control the development of the design
  • Identifies the client’s agreed cost limit and how the money is going to be allocated to different parts of the building
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the key cost planning stages?

A
  • RIBA 0/1: Order of cost estimate
  • RIBA 2: Formal cost plan 1 - based on £/m2 elemental breakdown
  • RIBA 3: Formal cost plan 2 - based on detailed measured quantities, £/m2 per item
  • RIBA 4: Formal cost plan 3 - send to tender
  • Pre-tender estimate
  • Post-tender estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Name some factors that can impact project costs?

A

Procurement:

  • Proportion of risk allocation (contractors will price for risk)
  • Contract type - lump sum / target / reimbursement

Design:

  • Complexity
  • Specification
  • Use of BIM
  • Value engineering

Construction:

  • Construction method
  • Volume of variations

External:
- Legislation / planning obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What benefit does client get out of cost planning?

A
  • Affordability
  • Helps develop design to meet budget
  • Value management tool
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What risk allowances should be included within a cost plan?

A
  • Design development risks
  • Construction risks
  • Employer change risks
  • Employer other risks (e.g. acceleration, postponement, availability of funds, etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is benchmarking and what sources of benchmark cost data can be used?

A

The use of historical data from projects of a similar nature as a comparison or cost check of the cost of a project.

  • In house (previous projects)
  • Building Cost Information Service (BCIS)
  • Benchmark from previous client projects
  • Pricing books (SPONS)
  • Cost models / published data
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the options for different types of pricing documents?

A
  • Bill of Quantities
  • Schedule of Rates
  • Contract Sum Analysis
  • Schedule of Work / Activity Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the different ways to price a project?

A
  • Lump Sum
  • Cost reimbursable
  • Re-measurement
  • Target Cost
  • Guaranteed Maximum Price (GMP)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a lump sum contract?

A
  • Fixed sum

- Used when the employer can define what is required, e.g. drawings and specifications, or performance specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a re-measurement contract?

A
  • Contractor paid for the actual work done (quantities)
  • Price based on approximate quantity rates in BoQ or Schedule of Rates provided
  • Actual work is priced against agreed rates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a reimbursable / prime cost contract?

A
  • Contractor completes work then is paid for their costs plus a pre-agreed mark up
  • Used where the definition of work is inadequate for the contractor to price, yet an early start is required
  • Suitable for maintenance / refurbishment / emergency work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a target price contract?

A
  • Reimbursable contract with target price to incentivise the contractor
  • Target price includes contractor’s cost plus % for OH&P
  • Risk is shared through pain/gain
  • At end of contract the contractor is paid (or pays) his share of difference between target and actual cost plus OH&P
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a Guaranteed Maximum Price (GMP) contract?

A
  • A lump sum contract under which there is no adjustment of tender price unless the scope changes
  • Contractor includes additional risks involved in the design development process in tender price
  • Savings made on packages are shared on an agreed basis - gain share - but extras are the contractor’s responsibility
19
Q

What are the advantages and disadvantages of a reimbursable contract?

A

Advantages:

  • Flexibility to alter design, programme and quantum of work
  • Enables early start on site
  • No premiums for abnormal risks in tender

Disadvantages:

  • No time or cost certainty
  • No incentive for efficiency
  • Difficult to monitor true costs
20
Q

What are the advantages and disadvantages of a Guaranteed Maximum Price (GMP) contract?

A

Advantages:

  • Greater price certainty, contractor carries development risk
  • Greater cost control; contractor’s interest to alert team to expensive items of design development
  • Quicker settlement of final account

Disadvantages:

  • Client may pay too much; contractor’s risk allowance could be inflated
  • Scope changes are expensive
  • Adversarial
21
Q

What are prime cost sums?

A
  • Allowance for the supply of work or materials to be provided by a contractor or supplier that will be nominated by the client
  • Allowance is exclusive of any profit mark up or attendance by the main contractor
22
Q

What is a Bill of Quantities?

A
  • Document consisting of all items which make up components of a building as well as preliminaries
  • Includes measures and rates for each items
  • Usually based on full production of drawings and project specifications
  • Used to manage variations (provide rates) and monitor expenditure
  • Contractor paid on basis of BoQ not quantities used
  • Any inconsistency between BoQ and drawings would be a variation

Consists of:

  • Preliminaries
  • Preambles (description of works / workmanship)
  • Measured works
  • Provisional sums
  • Prime Cost sums
  • Dayworks
  • Appendices (bonds, warranties, etc)
23
Q

What’s the benefit of cashflow forecast for the Employer?

A
  • Understanding of financial requirements over duration of project
  • Check against valuations
  • Can indicate whether the project is ahead/behind schedule
  • Plan expenditure
  • Ensures appropriate level of funding in place / suitable draw-down facilities available
24
Q

What would payments being either behind or ahead of the cashflow forecast imply?

A

Behind: Project behind programme or under-budget

Ahead: Ahead of programme or contractor has been claiming more than due/ahead of when due

25
What is the purpose of a financial report?
- Report against budgeted values and act as a working cost check on the project budget - Give client an understanding of any savings or additional monies required - Report on contract progress against pre-contract predictions
26
What should be included in a financial report?
- Executive summary - Contract sum - Instructed variations - Potential future variations - Provisional sums - Claims - Anticipated final account (forecast) - Risk allowances - Cashflow forecast - Next steps and recommendations
27
How is a risk register used in the post contract phase of a project?
- Any risks that have not materialised can be closed down | - Risk register can be used to reallocate client risk allowances, or obtain additional risk allowances if required
28
Why might a project have a cost overrun?
- Employer's requirements unclear or changed - Unrealistic cost estimates - Risk allocation is ambiguous - Inadequate management control - Design doesn't meet Statutory requirements - Uncoordinated design - Buildability of design - Design doesn't meet procurement strategy - Unforeseeable events
29
What is a valuation?
- A detailed breakdown of the works - Appraisal of the price of the works carried out to date - Pre-cursor to issuing an Interim Certificate
30
What are the main elements of a valuation?
- Preliminaries - Measured work - Variations - Materials on/off site - Loss and expense - Provisional sums (JCT only) - Retention
31
How are interim valuations evaluated?
- Site review of valuation with contractor - Check work done, materials on/off site - Value preliminaries, agreed variations and any claims - Valuation amount is gross valuation, less retention, less previous payment - Send a recommendation to Contract Administrator to issue the payment certificate
32
What is a gross valuation?
- Calculating the total amount of works completed to date, then deducting the previous month's total - Gives the value of work completed in the current month
33
When would Dayworks rates be used to value the works?
- Used when work cannot be priced in the normal way - No comparative rates in a bill of quantities - Fair and reasonable rate cannot be agreed
34
What is a variation?
An alteration to the original scope of works: - Addition - Substitution - Omission
35
What is the final account?
- Financial statement of all of the adjustments to the contract sum - Total amount the employer is liable to pay - End financial position of the contract - Includes all additions and omissions
36
What if the employer doesn't pay a sum due to the contractor under JCT?
- In addition to the unpaid sum, the employer must pay interest on that amount until the payment is made - Contractor can exercise right to suspend works
37
What happens to contingency as the project progresses?
Design development - reduced as design develops Construction risk - assessed based on construction risk, adjusted when more info is available, kept through construction phase. Any leftover = saving for client Employer change risk - reduces as design develops and likelihood of client changing decreases. Kept during construction for any employer changes, leftover = saving Employer other risk - kept through construction, allowance for any issues caused by client that have commercial implications
38
How did you go about creating the cost estimate for the NT?
- Determined which roles were required and whether they could be identified within or external to the client organisation - Identified specialist roles, such as Conservation Accredited designers - Identified survey and other professional fees required - Used estimated or known day rates - Created a schedule - Mapped out the likely consultant involvement against the master programme
39
How did change control work on the F1MP project?
- I completed a change request form and issued to the contractor - The form included the details of the change, design drawings and specification (if applicable), priority, and time for response - The contractor would then issue a quotation - Quotation reviewed alongside the QS, I did a check for overall reasonableness, plus checked against the contract specification documents - I would then review the change with the client to get approval for the spend, then issue an instruction to the contractor
40
On F1MP, what did your change tracker include?
- The change reference, shared with the contractor - The description of the change - The contractors quotation - The PM's assessment if different - Status: New, Accepted, Rejected.
41
How did you manage expenditure of a provisional sum on F1MP?
- Once provisional package was identified I established a brief for the works, and got a design prepared - Defined PS: contractor made allowance in price and programme - I requested a quote from the contractor - Reviewed the time aspects of the quote and liaised with QS to review the costs - If the costs were higher than the PS I would make the client aware, and the reasons for this - Once verified I instructed the contractor to omit the PS and replace with the quoted work
42
How did you develop cash flow forecasts?
1) Developed a schedule showing - consultant costs - client direct costs - construction costs 2) Gathered cost information - consultant costs: based on invoicing schedule provided by consultants - client direct costs: based on quotations provided to client - construction costs: based on pre-tender estimate from QS 3) Ongoing monitoring and updating of the cash-flow throughout the project
43
What is the difference between a Prime Cost and Provisional Sum?
Prime cost - an allowance for the supply of labour, plant and materials to be provided by the contractor that will be nominated by the client. The allowance is exclusive of OH&P. A prime cost contract (cost plus or cost reimbursement) - contracts in which the contractor is paid the prime cost (actual cost) and a fee for OH&P. Provisional sum - an allowance, usually estimated by a cost consultant, that is inserted in tender documents for a specific element of the works not defined in enough detail for tenderers to accurately price. This is a called a defined provisional sum and includes OH&P.
44
What is an S-Curve?
- Chart showing construction cash-flow over a project lifecycle - % of value of work completed vs % time completed - At beginning of a project the % time is greater than % value, therefore contractor cash flow will remain flat before increasing towards the middle of the project