Managing Projects Flashcards

1
Q

What information would you expect from the design team at RIBA Stage 4?

A

Technical design.

  • Fully coordinated services, structure & architecture
  • Fully detailed
  • Specialist subcontractor design & spec
  • Construction issue - in Traditional procurement this is what is priced and built against
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What’s the difference between RIBA Plan of Work 2013 and 2020?

A
  • Adapted to increased use of BIM
  • Aftercare activities starting in Stage 6: Handover
  • Different options for planning permission depending on the procurement route
  • Reinforces intention that Stage 4: Technical Design includes all the design information required for construction
  • New Sustainability guidance
  • Reinforces requirement to appoint a sustainability champion to create a sustainability strategy at the outset of the project
  • Stage name changes: Developed design is now Spatial Coordination; Construction is now Manufacturing and Construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What level of information would you expect at Stage 2?

A
  • Architectural Concept incorporating Strategic Engineering requirements and aligned to Cost Plan, Project Strategies and Outline Specification
  • Final project brief issued
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What level of information would you expect at Stage 3?

A
  • Spatially coordinated design
  • Updated proposals from structural design and building services systems
  • Aligned with Cost Plan and Outline Specification
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is ISO 9001?

A

A certified quality management system for organisations who want to prove their ability to provide products and services that meet the needs of their customers and other relevant stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What information is included in a PEP?

A
  • Project overview
  • Project programme
  • Project organisation
  • Control procedures
  • Stakeholder management
  • Communication strategy
  • H&S strategy
  • Quality assurance approach
  • Soft landing approach
  • Commissioning / handover strategy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a project audit?

A
  • An opportunity to review project challenges, risks and processes
  • Reflect on whether the project is still meeting core objectives
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What could be included in a post-project audit (lessons learned) review?

A
  • Quality of briefing documents
  • Quality of design
  • Quality of cost information
  • Effectiveness of communications
  • Performance of the project team
  • Construction issues - quality, H&S, programme
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is value engineering?

A
  • Method to eliminate any unnecessary costs and/or increase the value of a specification or product
  • Could be related to design, specification or cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the benefits of value engineering?

A

1) Improved performance
2) Identification of alternative designs or solutions
3) Reduced costs
4) Added value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the risks associated with value engineering?

A
  • Becomes detached from Value Management
  • Undertaken too late to be effective
  • Inadequate information causing incorrect assumptions
  • Insufficient participation by stakeholders (buy-in)
  • Insufficient time allocated for the process
  • Unknown knock-on effects to other elements of the design
  • Reduced ability to meet project brief
  • Reduced design performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Value Management?

A
  • Overall concept of managing the balance between benefits and costs throughout the project
  • Clearly defining a client’s strategic objectives
  • Considering optimum solutions
  • Deciding which provides the optimum lifetime value to the client
  • Includes value engineering as part of the process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What advice would you give a client on how to deliver a project with no scope creep?

A
  • PEP including control processes (change control, stage gate governance)
  • Stakeholder Management
  • Effective communication
  • Effective project management
  • Robust Project Brief
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How would you go about managing a site manager who is really excellent at managing the operatives on site but very poor at communication and project administration?

A
  • Be proactive - set up regular meetings, develop simple reporting tools
  • Recommend a contract administration system
  • Offer constructive feedback on reports, etc.
  • Scrutinise the programme
  • Maintain good records and communication
  • Maintain a client-side reporting structure
  • Issue early warnings and escalate poor performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Imagine I’m a client and I give you a project very similar to your case study project, what advice would you give me on what needed to be in a feasibility study for that project?

A

1) A feasibility study is completed at RIBA 1 to determine whether or not a proposed project is practical and affordable, and to select a preferred option if there are different solutions.
2) It should contain:
- Project objectives
- Site details / constraints
- Statutory requirements, e.g. Planning
- Options appraisal
- Space requirements
- Sketch arrangement plans
- Order of cost estimate
- Conclusions and recommendations (preferred option)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When would you implement a change control process and what would you do?

A

Usually from RIBA 3 when the Project Brief is fixed

Process:

1) Identify the need for change, using a form
2) Design solution is explored
3) Cost impact evaluation
4) Report to client
5) If rejected, design solution revisited
6) If accepted, project management action to instruct the change, direct detailed design, update cost documents and programme

17
Q

Earned Value Management is one of the tools we can use in project controls – can you explain how you used it?

A

A technique used to assess project progress by comparing the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.

This gives a good indication of how the project is progressing compared to what was planned and enables forecasts to be made about the eventual cost and time that will be required to complete the project.

18
Q

There are two indicators of Earned Value, do you know what they are?

A
  • Cost Performance Index (CPI) is the Budgeted Cost of Work Performed divided by the Actual Cost of Work Performed (BCWP / ACWP)
  • A negative number indicates that the project is overbudget, a positive indicates that its underbudget
  • Schedule Performance Index (SPI) is the Budgeted Cost of Work Performed divided by the Budgeted Cost of Work Scheduled (BCWP / BCWS)
  • A negative number indicates that the project is behind schedule
19
Q

In earned value analysis, what is ACWP, BCWP and BCWS?

A

You must first understand the duration of an activity, the cost/day and the total cost of the activity.

Actual Cost of Work Performed (ACWP) - the actual cost of the work completed

Budgeted Cost of Work Performed (BCWP) - the budgeted cost of the work completed

Budgeted Cost of Work Scheduled (BCWP) - the budgeted cost of the work scheduled to complete

Cost Variance (CV) = BCWP - ACWP

Schedule Variance (SV) = BCWP - BCWS

20
Q

What is the Earned Value metric?

A

The money we should have spent for the work we have actually completed, i.e. the Budgeted Cost of Work Performed

21
Q

What is Soft Landings?

A

A collection of processes to ease the transition between Project and Operations in order to drive maximum benefit.

22
Q

What are Statutory Consents?

A

Consents you must obtain by law. I.e., Planning and Building Regulations

23
Q

What is a S106 Agreement?

A

The legal agreement between an application and authority to implement a mitigation of the development. I.e., a bus stop, junction or provide money.

24
Q

What is a Section 278 Agreement?

A

Legal agreement between Highways Authority and Application to create an interface to the national network.

25
Q

Can you explain what an EIA is?

A

Environmental Impact Assessment - an assessment undertaken by applicant that looks at all facets of the development impact on the environment.

26
Q

What are the project strategies?

A
Strategies to support the design process, generally developed in parallel with the design stages (Stage 2-3) and to respond to the Business Case or Project Brief:
• Conservation Strategy
• Cost Strategy
• Fire Safety Strategy
• Health and Safety Strategy
• Inclusive Design Strategy
• Planning Strategy
• Plan for Use Strategy
• Procurement Strategy
• Sustainability Strategy.
These strategies are usually prepared in outline at Stage 2 and in detail at Stage 3,
27
Q

What is a responsibilities matrix?

A
  • Maps out activities required to develop the design information and assigns to specific team members or to external bodies
  • Should make clear where the boundaries between responsibilities lie
  • Ambiguity between roles and design liability must be resolved early
  • Clarity on how contractor’s design and others will be provided for in the design
28
Q

How can the impact of design changes be managed?

A

1) Have well-defined systems for coping with change
2) Limit the time at which changes occur by dealing with problems that give rise to the change, and then implement a ‘change freeze’ to allow the design to be developed to remove the impact of the problems

29
Q

How is it best to manage client approvals to design changes?

A
  • Once design team has completed design to a logical point, i.e. end of stage
  • Client approval is a gateway to the next stage
  • Client approvals should be planned and managed carefully so as not to delay the start of the next stage
30
Q

What is the link between design management and cost control?

A
  • Should be integrated throughout design stage to ensure design isn’t incompatible with the budget
  • Contingency sums should be understood by designers so that when a solution for risk items is identified it can be managed efficiently
31
Q

What should be included in a risk monitoring and control process?

A

1) Monthly reviews of the current risk profile and identify changes in risk probabilities and impacts
2) Monthly monitoring of risk responses/mitigations
3) Update of risk register with new risks
4) Review level of project risk management maturity of project

32
Q

What statutory requirements before starting construction?

A

1) F10 notification
2) Planning permission
3) Building control notice