Development and project briefs Flashcards
What advice would you give a client on the consequences of not having a robust project brief?
- Risk of scope creep
- Ineffective concept design / requirements not effectively met
- Design unable to meet time/cost/quality requirements
- Considerable changes to the brief required at end of RIBA 2
- Cost plan inaccurate
- Overall delays to programme and increased costs (abortive design)
- Reputational damage
How does a project brief differ to a business case?
- Project brief: document outlining the client’s requirements; detailed enough to appoint consultants; developed further with benefit of consultant’s comments
- Business case: provides the rationale behind the initiation of a new building project necessary to enable decision-making bodies to reach a reasoned decision
How would you collate the opposing views of stakeholders into one project brief?
- Stakeholder Management approach in the PEP
- Understand stakeholders’ influence by assessing their relative power/interest
- Views to be assessed in relation to this
- Set up a workshop to review opposing views
- Refer decision to Project Board or a Senior Officer or responsible person who could deliberate on points of disagreement
What would you include in an Outline Business Case?
Approves the investment required to develop the project from RIBA 0 Strategic Definition to complete feasibility studies and to develop the Project Brief.
- Benefits appraisal
- Risk assessment
- Procurement strategy
- Programme and phasing
- Risk allocation
- Financial case
- Management case
What would you include in a Business Case / Full Business Case?
Builds on the OBC using inputs from feasibility studies, and any consultants that have been appointed. Additional input:
- Identification of a preferred option (from feasibility)
- Confirmation of affordability
- Statement of design intent
- Projected financial forecasting
- Plans for next stage
Approves the project to proceed into design (Concept Design), and costs to end of design.
FBC provides a post-tender contract sum, and approves the project to proceed into construction.
When is the Project Brief developed?
- RIBA Stage 1: Preparation and Briefing
- Stage outcome is the Project Brief being approved by the client
- Project Brief revisited in RIBA Stage 2: Concept Design
- Architectural Concept is approved and aligned to the Project Brief
- Project Brief is finalised at this stage
What should be included in a Project Brief?
- Description of client
- Strategic brief
- Site information
- Spatial requirements
- Technical requirements
- Component requirements
- Project requirements / other issues
What should be included in a Project Brief - Description of client?
- Client’s purpose, vision, values
- Client’s main priorities
- Client’s KPIs
- Organisational structure / decision-making processes
- Interfaces with other projects
- Client policies / procedures
What should be included in a Project Brief - Site information?
- Building surveys
- Site surveys
- Information about ground conditions
- Location and capacity of utilities
- Access and other constraints
- Legislative constraints
What should be included in a Project Brief - Spatial requirements?
- Schedules of accommodation
- Schedules of users
- Required adjacencies / groupings / separations
- Circulation guidelines
- Phasing
What should be included in a Project Brief - Technical requirements?
- Servicing requirements
- Comfort conditions
- ICT requirements
- Specialist processes or plant
- Fire compartments
- Maintenance requirements
- Sustainability requirements
- Durability / life-span
What should be included in a Project Brief - Component requirements?
- Long-lead items
- Specialist design / specialist contractor’s design
- Cladding strategy
What should be included in a Project Brief - Project requirements?
- Planning requirements
- Budget
- Programme / key milestones
- Risks
- Post-occupancy evaluation / targets
- KPIs
What was the change control process used to manage changes to the Project Brief on the Bicester Village project?
- Any change in requirements may involve a change to the design
- The Project Brief is fixed at RIBA Stage 2
- The change is logged on a tracker, then assessed by different disciplines
- QS assesses the cost impact
- Architect / engineers assess design impact
- CA assess the programme impact
- Client approves the change
- Updates made to the Project Brief
Give an example of a change to the Project Brief and how would you handle it?
- Depends upon scale of the change / when change is issued
- Advise client that any changes following the end of RIBA Stage 2 are likely to have cost/programme impacts as will involve abortive design
- If client still wants the change, if it is a large scale change, assess it, then update the design and Project Brief
- Go through stage gate again
- If minor, manage as a change to the Spatial Coordination stage