Not used Flashcards
What is assignment?
When the benefit of a contract is transferred from one party to another, but the burden of the contract remains with the original party to the contract
What is a bond and what type of bonds are available?
An arrangement where a contractual duty owed by one party to another is backed by a third party. Types include:
- Performance bond (protects against contractor default, typically 10% of contract sum)
- Retention bond
- Off-site materials bond
- Advance payment bond
- Tender bond
When would you use a JCT Major Project Construction Contract?
- D&B procurement route
- Lump-sum
- Large-scale construction projects
- Employers who regularly procure large-scale construction work
- Contractors with experience and ability to take greater risk
- Sectional completion
What is partial possession?
- Contract may allow the employer to take partial possession of part of the works before they have formally completed
- Contractor must give consent
- Not agreed in advance
- Completion deemed to have occurred for that section
What are the main features of the NEC contracts?
- No reference to QS in contract
- PM assumes full responsibility on behalf of the employer
- PM controls time and cost as an administrative function
- PM updates the risk register and issues instructions
- Programme is a contract document
- Requirement for parties to give early warnings
- Changes managed via Compensation Events
- No provisional sums
What are the 6 main options NEC3 EEC?
Option A: Priced contract with activity schedule
Option B: Priced contract with bill of quantities
Option C: Target contract with activity schedule
Option D: Target contract with bill of quantities
Option E: Cost reimbursable contract
Option F: Management contract
What are the key features of NEC EEC Option A: Priced contract with activity schedule?
- Financial risk borne by the contractor
- Lump sum contract
- Project usually well defined at tender
- Payment on completion of defined activities (no partial payments)
- Suitable for traditional or design & build
What are the key features of NEC EEC Option B: Priced contract with bill of quantities?
- Price risk borne by the contractor
- Project usually well defined at tender
- Payment on % completion of BoQ
- Suitable for traditional or design & build
What are the key features of NEC EEC Option C: Target contract with activity schedule?
- Financial risk shared between client and contractor in agreed proportion
- Target cost agreed between parties - contractor’s estimate of ‘defined cost’ plus a fee
- Target costs is set by the activity schedule
- Target moves if there are Compensation Events
- Pain / Gain mechanism for sharing risk
What are the key features of NEC EEC Option D: Target contract with bill of quantities?
- Financial risk shared between client and contractor in agreed proportion
- Target cost agreed between parties - contractor’s estimate of ‘defined cost’ plus a fee
- Target costs is set by BoQ
- Target moves if there are Compensation Events
- Pain / Gain mechanism for sharing risk
What are the key features of NEC EEC Option E: Cost reimbursable contract?
- Employer largely takes financial risk
- Contractor reimbursed for actual costs plus a pre-agreed OH&P %
- Might be used where nature / scope of work cannot be defined at the outset (e.g. emergency work)
What are the key features of NEC EEC Option F: Management contract?
- Reimbursable contract, employer largely takes financial risk
- Works are designed/constructed by multiple sub-contractors who are contracted to a management contractor
- MC is responsible for the work and is paid a fee - cost that it pays the works contractors plus an additional fee
Rank the NEC contract options from highest to lowest financial risk for the employer?
Option E: Cost reimbursable contract
Option F: Management contract
Option D: Target contract with bill of quantities
Option C: Target contract with activity schedule
Option B: Priced contract with bill of quantities
Option A: Priced contract with activity schedule
Rank the NEC contract options from highest to lowest financial risk for the contractor?
Option A: Priced contract with activity schedule
Option B: Priced contract with bill of quantities
Option D: Target contract with bill of quantities
Option C: Target contract with activity schedule
Option F: Management contract
Option E: Cost reimbursable contract
What are the Secondary Options under NEC3 EEC?
Secondary option clauses include payment and risk-related options:
W1, W2 clauses - Dispute resolution
X1 - X20 clauses - pre-defined options (e.g. X5 - Sectional Completion, X13 - Performance Bond)
Y(UK)1 - Y(UK)3 - options dealing with national legislation
Z clauses - contract amendments
In NEC how can the completion date be changed?
- Acceleration (forward)
- Compensation Event (back)
In NEC what is the difference between Planned Completion and the completion date?
Planned completion - date that the contractor plans to finish
Completion date - the date in the contract, or date changed as a result of Compensation Events
The duration between Planned Completion and completion date is called terminal float, and it is owned by the contractor (i.e. cannot be used to mitigate the effect of a compensation event)
What are the key responsibilities of the Project Manager under an NEC contract?
- Duty to manage the contract on behalf of the employer
- Issues all instructions, notifications and communications required under the contract
- Only person who can change the Scope
- Monitors execution of the project and ensures all parties adhere to conditions of contract