Project Cost Management Flashcards

1
Q

Plan Cost Management

A

The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Estimate Costs

A

The process of developing an approximation of the monetary resources needed to complete the project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Determine Budget

A

The process of aggregating the estimated costs of individual activities or work packages to establish a cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Control Costs

A

The process of monitoring the status of the project to update project costs and manage changes to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the inputs to the cost management plan?

A

Project charter, project management plan, EEF, OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the tools and techniques to the cost management plan?

A

Expert judgement, data analysis, meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the outputs to the cost management plan?

A

Cost management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is estimate costs?

A

The approximation of the cost of resources needed to complete the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the inputs to estimate costs?

A

Project management plan, project documents, EEFs, OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the tools and techniques for estimate costs?

A

Expert judgement, analogous estimating, parametric estimating, bottom up estimating, three point estimating, data analysis, PMIS, decision making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is analogous estimating?

A

Using a previous project that is similar to the current project to estimate scope, cost, budget, and duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is parametric estimating?

A

Uses historical data and other relevant variables to calculate a cost estimate for project work. More accurate than analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is bottom up estimating?

A

Estimating the cost at a work package level and rolling up to higher levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is three point estimating?

A

Uses three estimates, most likely, optimistic, and pessimistic to define an approximate range for the activities cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

cM

A

Most likely

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

cO

A

Optimistic = best case scenario

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

cP

A

Pessimistic = worst case scenario

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the basis of estimates?

A

Supporting documentation to provide a clear understanding of how to estimate was derived

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the outputs to cost estimate?

A

Cost estimates, basis of estimates, project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is the rough order of magnitude?

A

-25% to +75%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is definitive estimate?

A

-5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is +/- 3 sigma?

A

99.73%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is +/- 2 sigma?

A

95.46%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is +/- 1 sigma?

A

68.26%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is the formula for triangular distribution?

A

cE=(cO + cM + cP)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is the formula for beta distribution?

A

cE = (cO + 4cM + cP)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is determine budget?

A

The process of collecting all the estimated costs of individual activities to establish a cost baseline. Includes all the funds authorized to execute a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are the inputs to determine budget?

A

Project management plan, project documents, business documents, agreements, EEFs, and OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What is reserve analysis?

A

Establishes the management reserves for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What are the tools and techniques of determine budget?

A

Expert judgement, cost aggregation, data analysis, historical information review, funding limit reconciliation, financing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What are management reserves?

A

Are an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within the project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is management reserve intended to do?

A

Address the unknown unknowns that can affect a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Is management reserve part of the cost baseline?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What is cost aggregation?

A

A collection of the cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What is the output to determine budget?

A

cost baseline, project funding requirements, project document updates

36
Q

What two things make up the aggregated activity costs?

A

Activity cost estimates & Activity Contingency Reserves

37
Q

What two things make up the aggregated work package costs?

A

Work package cost estimates & Contingency Reserves

38
Q

What two things make up control accounts?

A

Work package cost estimates & Contingency Reserves

39
Q

What makes up the cost baseline?

A

The summation of control accounts

40
Q

What makes up the project budget?

A

Cost baseline & management reserves

41
Q

The total funding required includes:

A

The cost baseline plus management reserves

42
Q

What is control costs?

A

Process of monitoring the status of the project to update costs and manage changes to the cost baseline

43
Q

What is the key benefit of controlling costs?

A

The cost baseline is maintained throughout the project

44
Q

What relationship does control cost look at?

A

The relationship between the consumption of project funds and the work being accomplished for such expenditures.

45
Q

What are the inputs to control costs?

A

Project management plan, project documents, project funding requirements, work performance data, OPAs

46
Q

What are the tools and techniques to control costs?

A

Expert judgment, data analysis, PMIS (project management information system)

47
Q

What is earned value analysis (EVA)?

A

Compares the performance measurement baseline to the actual schedule and cost performance

48
Q

What does EVM stand for?

A

Earned value management

49
Q

EVM develops and monitors which 3 things?

A

Planned value (PV), earned value (EV), and actual cost (AC)

50
Q

What is planned value (PV)?

A

Is the authorized budget assigned to the schedule work. Does not include management reserve

51
Q

What is the total of PV defined as?

A

The performance measurement baseline (PMB) or Budget at Completion (BAC)

52
Q

What is earned value (EV)?

A

The budget associated with the authorized work that has been completed

53
Q

Can the EV be greater than the authorized PV?

A

No

54
Q

What is used to calculate the percent complete of a project?

A

EV

55
Q

What is actual cost (AC)?

A

Is the total cost incurred in accomplishing the work that the EV measured

56
Q

What is variance analysis?

A

Is the explanation (cause, impact, and corrective actions) for cost, schedule, and variance at completion

57
Q

What is the formula for cost variance analysis?

A

CV = EV -AC

58
Q

What is the formula for schedule variance analysis?

A

SV = EV - PV

59
Q

What is the formula for variance at completion analysis?

A

VAC = BAC - EAC

60
Q

What is schedule variance (SV)?

A

It is the amount by which the project is ahead or behind the planned delivery date

61
Q

SV is best used in conjunction with which other method?

A

Critical path method

62
Q

What is cost variance (CV)?

A

Is the amount of budget deficit or surplus

63
Q

What does BAC stand for?

A

Budget at completion

64
Q

What is schedule performance index (SPI)?

A

Measures how efficiently the team is accomplishing the project work

65
Q

A SPI > 1.0 means?

A

More work was completed than planned

66
Q

A SPI < 1.0 means?

A

Less work was completed than planned

67
Q

What is the formula for SPI?

A

SPI = EV/PV

68
Q

What is cost performance index (CPI)?

A

The measure of the cost efficiency of budgeted resources

69
Q

What is the most critical EVA measurement?

A

CPI (cost performance index)

70
Q

A CPI > 1.0 means?

A

Indicates a cost under run of performance to date

71
Q

A CPI < 1.0 means?

A

Indicates a cost overrun of performance to date

72
Q

What is the formula for CPI?

A

CPI = EV/AC

73
Q

What does EAC stand for?

A

Estimate at completion

74
Q

Why is forecasting used in control costs?

A

It is used when the BAC is no longer viable and the EAC must be used to forecast what the project costs will be in the future based on current performance information

75
Q

What does ETC stand for?

A

Estimate to complete

76
Q

What is the most common EAC forecasting approach?

A

Bottom up summation

77
Q

What is the formula for a EAC bottom up summation?

A

EAC = AC + Bottom-up ETC

78
Q

What does the EAC forecast for ETC work performed at the budgeted rate do?

A

It accepts the actual project performance to date as represented by actual costs and predicts all the future ETC work that will be accomplished at a budgeted rate

79
Q

What is the equation of EAC forecast for ETC work performed at the budgeted rate?

A

EAC = AC + (BAC - EV)

80
Q

What does the EAC forecast for ETC work performed at the present CPI do?

A

Assumes what the project has experienced to date can be expected to continue in the future

81
Q

What is the equation for EAC forecast for ETC work performed at the present CPI?

A

EAC = BAC/CPI

82
Q

What does the EAC forecast for ETC work considering SPI and CPI factors do?

A

ETC work will be performed at an efficiency rate that considers both the cost and schedule performance indices

83
Q

What is the equation EAC forecast for ETC work considering SPI and CPI factors?

A

EAC = AC + [(BAC - EV) / (CPI x SPI)]

84
Q

What is the to-complete performance index (TCPI)?

A

The cost performance that is required to be achieved with the remaining resources in order to meet a specified measurement goal

85
Q

What is the equation for TCPI based on BAC?

A

TCPI = (BAC - EV) / (BAC - AC)

86
Q

What is the equation for TCPI based on EAC?

A

TCPI = (BAC - EV) / (EAC - AC)

87
Q

What are the outputs to control costs?

A

Work performance information, cost forecasts, change requests, project management plan updates, project document updates