Project Cost Management (3) Flashcards

1
Q

What are the processes in the project cost management knowledge area?

A

Plan cost management, estimate costs, determine budget, and control consts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the concept of earned schedule?

A

Emerging trend that uses earned schedule - actual time to calculate schedule variance. Indicates efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are tailoring considerations for project cost management?

A

Knowledge management, estimating and budgeting, earned value management, agile approach, and governance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a cost baseline?

A

Approved version of time-phased project budget, excluding management reserves. Can be changed only with formal change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the input for the plan cost management process?

A

Project charter, PMP (schedule MP, risk MP), EEFs (culture, market, currency exchange rates, PMIS), OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the tools used for the plan cost management process?

A

Expert judgement, data analysis (alternative), meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the outputs of the plan cost management process?

A

Cost MP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the inputs for the estimate costs process?

A

PMP (cost MP, quality MP, scope baseline), project docs (lessons learned, project schedule, resources requirements, risks), EEFs (market, exchange rates), OPAs (policies, templates, historical info)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the tools used for the estimate costs process?

A

3 point estimating, analogous estimating, parametric estimating, bottom-up estimating, expert judgement, data analysis, decision making, PMIS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is progressive elaboration?

A

Costs become more clear and estimates more accurate as project goes on

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is parametric estimating?

A

Uses statistical relationship between historical data and other variables (e.g., square footage) to calculate cost estimate (# units x cost per unit)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is bottom-up estimating?

A

Takes detailed estimates at work package level then rolls up costs to higher level for reporting and tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the outputs of the estimate costs process?

A

Basis of estimates, cost estimates, project doc updates (assumption log, lessons learned, risks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the inputs to the determine budget process?

A

PMP (cost MP, resource MP, scope baseline), project docs (basis of estimates, cost estimates, project schedule, risk register), business docs (business case, benefits MP), agreements, EEFs (exchange rates), OPAs (policies, historical info, lessons learned, tools and methods)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the tools used for the determine budget process?

A

Expert judgement, cost aggregation, data analysis (reserve analysis), historical information review, funding limit reconciliation, financing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the outputs of the determine budget process?

A

Cost baseline, project funding requirements, project doc updates (cost estimates, project schedule, risks)

17
Q

How is the cost performance baseline typically displayed?

A

S-curve

18
Q

What are the inputs for the control costs process?

A

Project docs (lessons learned), OPAs (policies, tools, methods), PMP (cost MP, cost baseline, performance measurement baselines), work performance data, project funding requirements

19
Q

What are the tools used for the control costs process?

A

Expert judgement, data analysis (earned value, variance, trend, reserve), PMIS, to-complete performance index

20
Q

What are the outputs of the control costs process?

A

change requests, PMP updates (cost MP, cost baseline, performance measurement baseline), cost forecasts, project doc updates (assumption log, basis of estimates, cost estimates, risks), work performance information

21
Q

What is variance at completion?

A

Different between budget at completion and what the estimate was

22
Q

What is work performance information?

A

Information on how project work is performing compared to cost baseline

23
Q

What is budget at completion (WPI)?

A

Total budget allocated to project

24
Q

What is estimate at completion (WPI)?

A

Expected total cost of completing all work

25
Q

What is earned value analysis?

A

Forecast total cost of project
3 key dimensions:
1. planned value = authorized budget
2. earned value = measure of work performed until a specific date
3. actual cost = budget spent until specific date

26
Q

What is complete performance index?

A

measure of cost efficiecny
CPI = EV/AC
>1 under planned cost
<1 over planned cost

27
Q

How is cost variance calculated?

A
CV = earned value - actual cost
CV= EV - AC
28
Q

If cost variance is negative is project over or under budget?

A

Over budget

29
Q

What is planned value (PV)?

A

Authorized budget assigned to scheduled work

30
Q

What is earned value (EV)?

A

Sum of planned value of completed work up to that point

31
Q

What is variance at completion?

A

budget at completion - estimate at completion

32
Q

What is to-complete performance index?

A

Cost that must be achieved with remaining resources to meet goal
TCPI = (BAC - EV)/(BAC - AC)
>1 harder to complete
<1 easier to complete