Project Calculations Flashcards

1
Q

What are the four steps to calculating project performance?

A

Calculate earned value (1), cost performance index (2), schedule performance index (3), and interpret the results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is EV (earned value) calculated?

A

EV= total budget * % project complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How is CPI (cost performance index) calculated?

A

CPI=EV/Actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How is SPI (schedule performance index) calculated?

A

SPI= EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does the CPI indicate, and what is the ideal number of this metric?

A

CPI indicates project budget health/how efficiently the budget is being used. A value greater than one is ideal. It indicates the project is doing better than planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the SPI indicate, and what is the ideal number of this metric?

A

SPI indicates project health/how efficient the schedule is. A value greater than one is ideal. It indicates the project is doing better than planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the uses of the Performance Evaluation and Review Technique (PERT)?

A

Estimating durations
Defining accurate times lines
Managing risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 3 different types of estimates used for calculations?

A

Optimistic (O)
Pessimistic (P)
Most likely (M)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Calculate TE (expected duration)

A

TE=(O+4M+P)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Calculate EMV (Expected Monetary Value) for cost & for time

A

EMV (for cost)= Probability * C
EMV (for time)= Probability * T

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does EMV indicate?

A

EMV quantifies how the project is impacted if the risk occurs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the benefits of EMV?

A

Assess risk mitigation
Prioritize and allocate resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define the critical path.

A

Identifying the time sensitive activities that would delay the project timeline if they’re not done on time. These tasks have zero slack/float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What at the benefits of doing a “forward” or “backward”

A

Identify the latest start & finish times for activities
Identify tasks with slack/float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Calculate the number of communication channels.

A

N=n(n-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define present value (PV)

A

Value of a project over time

17
Q

Calculate Present Value (PV)

A

PV=FV(future value)/(1+r[interest rate])^n(# of yrs)

18
Q

What are the benefits of knowing the present value?

A

Let’s you know what amount need to be invested today
Helps evaluate if the cash flow is worth it

19
Q

How is cost variance calculated?

A

EV-AC

20
Q

How is schedule variance calculated?

A

EV-PV

21
Q

Calculate Estimate at Completion (EAC)

A

EAC=BAC/CPI

22
Q

Calculate Variance at Completion (VAC)

A

VAC= BAC-EAC

23
Q

Calculate Estimate to Completion

A

ETC= EAC-AC

24
Q

Calculate To-Complete Performance Index

A

T-CPI= (BAC-EV)/(BAC-AC)

25
Q

T/F: T-CPI greater than 1 is good.

A

F. Unlike other PIs, a smaller number is better in this case