Project and Practice Management Flashcards

1
Q

5 considerations in scheduling

A
cost
time
aesthetics
function
sustainability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

GANTT CHART

A

bar chart with float indicated; shows flow/order but not critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CRITICAL PATH SCHEDULE

A

shows activities and indicates duration with dependencies

tasks illustrated as arrows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

DUMMY

A

in critical path chart, a dotted line to separate 2 tasks otherwise defined by the same point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

7 major elements in cost estimating

A
site acquisition
construction
professional services
inspection and testing
contingencies
financing
misc. (atty, listing for bids, permits...)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

estimating method by project phase

A

programming: unit cost
schematic design: major elements and building subsystem options compared
design development: more detail with suggested changes
construction documents: components, assemblies, and systems (used to verify pay applications)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

FEE CALCULATION: DSE

A

Multiple of Direct Salary Expense

multiply by factor to cover fringe benefits, overhead and profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

FEE CALCULATION: DPE

A

Multiple of Direct Personnel Expense

fringe benefits and salary multiplied by a factor to cover overhead and profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

FEE CALCULATION: PROFESSIONAL FEE PLUS EXPENSES

A

professional services separated from specific identified costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

FEE CALCULATION: HOURLY BILLING RATE

A

billed at standard rate for hours worked - often on a “not-to-exceed” basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

FEE CALCULATION: STIPULATED / LUMP SUM

A

total payment amount is agreed upon

may be as a percentage of construction cosst

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

FEE CALCULATION: UNIT PRICE CONTRACT

A

based on acceptance of unit price quotes for various elements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

architectural fees as percentage of construction cost

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

mechanical fees as percentage of construction cost

A

15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

electrical fees as percentage of construction cost

A

12.5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

civil fees as percentage of construction cost

A

10.5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

structural fees as percentage of construction cost

18
Q

contractor fees: general overhead

A

8-10% firm value

19
Q

contractor fees: project overhead

A

4-10% construction cost

20
Q

contractor fees: profit

A

15-20% small
10-15% medium
5-10% large

21
Q

cost estimating: pre-planning/ proposal

A

unit cost bsis

22
Q

cost estimating: programming

A

unit cost based on similar building types and function of spaces

23
Q

cost estimating: schematic design

A

based on major elements of building systems

24
Q

cost estimating: design development

A

based on detailed components

25
cost estimating: construction documents
based on unit rates for components, assemblies and systems
26
project phases as percentage of entire project duration
``` schematic design: 15% design development: 15% construction documents: 35% bidding and negotiation: 5% construction administration: 30% project closeout might be 2-5% ```
27
5 factors that impact schedule
``` project size budget complexity number of people on project reaction time ```
28
FLOAT
in a critical path schedule, range of time during which a non-critical activity can start and end without affecting the overall schedule
29
FAST TRACK SCHEDULE
CDs issued in bid packages so that construction can begin while design is being completed 10-30% reduction in time to complete
30
PROJECT SCHEDULING: BRIDGING
a type of design-build. Owner secures price early and contractor contributes knowledge of construction methods and materials and relationships with suppliers. Contractor controls detailing and architect provides advice. Lower up-front cost / overal cost effective contractor solely responsible for product of construction
31
SHUTTLE DIPLOMACY
revising written document over and over until 2 parties agree time-consuming but effective when far apart on opinions
32
GROUPTHINK
decision by deference - mediocre result because ideas aren't challenged and refined
33
BRAINSTORMING
generat as many ideas as possible without considering feasibility and with no criique
34
LATERAL THINKING
non-linear thinking that creates a number of alternatives for later evaluation
35
PROFESSIONAL LIABILITY INSURANCE
held by architects/design professionals | for negligence in meeting standard of care expected (ex: not meeting ADA compliance)
36
WORKER'S COMPENSATION INSURANCE
help by almost everyone | liability to employees for injury or sickness as a result of work
37
PROPERTY/BUILDERS RISK INSURANCE
held by owner | covers damages, loss of work on site, off site, or in transit
38
LOSS OF USE INSUTANCE
held by owner | covers financial loss due to delay in construction because of damage, accidents, fire and other hazards
39
PRODUCT AND COMPLETED OPERATIONS INSURANCE
held by contractor | liability for damages caused by installed goods after construction and transfer of title
40
CONTRACTUAL/INDEMNIFICATION INSURANCE
liability assumed by contract where contractor agrees to hold owner and architect harmless for damages as a result of specific events