project admin old study guide Flashcards
Which document is used to allocate the estimated costs for the items listed and for
requesting progress payments?
A. Schedule of Values
B. Construction Schedule
C. Contract Change Order
D. Labor and Material Bond
a
Which document is issued to the Contractor for failure to perform according to the
specifications?
A. Stop Work Order
B. Change Directive
C. Stop Work Notice
D. Performance Bond
a
Which document is signed in agreement by the Owner, A/E and the Contractor informing
the Contractor to modify the agreements terms and conditions?
A. Addenda
B. Change Directive
C. Contract Change Order
D. Contract Change Order Proposal
c
Which document is signed in agreement by the Owner and the A/E and instructing the
Contractor to make a change prior to agreeing on the adjustment in scope or price?
A. Change Directive
B. Extra Work Order
C. Contract Change Order
D. Contract Change Order Proposal.
a
Which document establishes the actual start date from which the beginning of the project
is calculated?
A. Notice of Award
B. Notice to Proceed
C. Contractor’s Proposal
D. Supplementary Conditions
b
Which document terminates any liquidated damages from being assessed any further?
A. Notice of Award
B. Stop Work Notice
C. Contract Change Order
D. Certificate of Substantial Completion
d
Which of the following items is contained in the Certificate of Substantial Completion?
A. Process payment schedule
B. Starting date of the project
C. A list of items to be completed
D. A list of contract documents to be submitted
c
What is an amount withheld from progress payments to ensure satisfactory completion of
the work called?
A. Lien
B. Retainage
C. Cost Plus Expenses
D. Liquidated damages
b
Assume that the Contractor has not been paid according to the contract payment due date.
According to the contract documents, which document must the Contractor complete and
submit to the Owner to inform them that they will be leaving the job site if the late
progress payment is not received?
A. Sworn Statement
B. Stop Work Order
C. Stop Work Notice
D. Schedule of Values
c
According to the project documents, which document lists the itemized content required
for submitting a Contract Change Order Proposal?
A. General Conditions
B. General Requirements
C. Instructions to Bidders
D. Supplementary Conditions
d
According to the project documents, after the signing of the Agreement which documents
must be submitted by the Contractor within fourteen days of executing the Agreement?
A. Performance Bond and Labor/Material Bond
B. Extra Work Order and Contract Change Order
C. Construction Schedule and Schedule of Values
D. Stop Work Notice and Contract Change Order Proposa
c
Which document lists the Contract Documents that shall be utilized to interpret the
contract?
A. General Conditions
B. Technical Specifications
C. Supplementary Conditions
D. Owner/Contractor Agreement
d
Which position is typically responsible for verification of all materials, field
measurements and field construction criteria on the shop drawings?
A. Architect
B. Subcontractor
C. Project Engineer
D. Project Manager
c
Which document explicitly tells the reader the specific shop drawings, product data, and
reference standards required on a project?
A. In Part 1 of each Section of the General Requirements
B. In Part 1 of each Section of a Technical Specification Division
C. In Part 2 of each Section of a Technical Specification Division
D. At the beginning of the first Section of each Technical Specification Division
b
Which of the following items that must be submitted show the fabrication and erection
process?
A. Pella Windows, Kitchen Cabinets, Furniture and Pre-hung Doors
B. Structural Steel, Rebar, Formwork Design, Glazing and Frames for Store Fronts
C. Plumbing Fixtures, Heating Fixtures, Electrical Fixtures and Prepackaged Equip
D. Prepackaged Equipment, Brick Block, Roofing Membrane, and Kitchen Cabinets
b
Which of the following items that must be submitted show the fabrication and erection
process?
A. Sheet Metal Isometrics, Plumbing Isometrics, and Electrical Isometrics
B. Acoustical tile, Paint Colors, Plumbing Fixtures and Prepackaged Equipment
C. Kitchen Cabinets, Pella Windows, Prehung Doors and Interior Trim
D. Plumbing Fixtures, Heating Fixtures, Electrical Fixtures and Prepackaged
Equipment, Piping Isometrics, Plumbing Isometrics, and Electrical Isometrics
a
What are the names of the parties signing an Extra Work Order?
A. Owner and Contractor
B. Surety and the Owner
C. Architect and the Subcontractor
D. Architect and the Superintendent
d