material and method old study guide part 2 Flashcards
Which party is normally responsible for estimating and pricing the temporary structures?
A. Owner
B. Vendor
C. Contractor
D. Architect/Engineer
c
Which party is normally responsible for designing the temporary structures?
A. Owner
B. Vendor
C. Contractor
D. Architect/Engineer
C. Contractor
Which of the following systems is designed to restrain horizontal temporary loads such as
soil and water?
A. Steel Piling
B. Sheet Piling
C. Wood Piling
D. Concrete Piling
b
Which of the following systems is designed to carry the vertical load of the structure?
A. Piling
B. Cofferdam
C. Timber Shoring
D. Cribbing and Tie-backs
a
Which of the following systems is utilized for supporting an existing structure when the
new excavation will be below the existing structures foundation while the extension to the
existing foundation is being placed?
A. Piling
B. Cofferdam
C. Underpinning
D. Cribbing and Tie-backs
c
Which of the following systems is utilized for restraining a vertical wall of soil and other
loads where it is impractical to slope the soil, such as in a downtown area where the
excavation and new substructure are below the street level?
A. Piling
B. Cofferdam
C. Underpinning
D. Cribbing and Tie-backs
d
Which of the following systems is designed as an enclosed structure to restrain soil and
water, therefore allowing workers to work inside safely?
A. Caisson
B. Jin Poles
C. Cofferdam
D. Underpinning
c
In construction, what is the proper terminology for transporting the off road equipment to
the job site?
A. Hauling
B. Mobilization
C. Militarization
D. Transportation
b
What is the lifting system called which consists of two vertical towers with a cross beam on
top with the intended purpose of lifting an unusually long piece of equipment which was
transported horizontally and is lifted into its permanent vertical position?
A. Caisson
B. Jin Pole
C. Cofferdam
D. Tower Crane
b
What are the components of a cofferdam or a support system?
A. Sheeting, Wales, and Cross Braces
B. Posts, Stringers, Joists and Pans
C. Posts, Stringers, Joists and Plyform
D. Wall forms, Wall Ties, Wales, Hairpins and Braces
a
What is a toe in relationship to a Cofferdam?
A. The Tie Back extension beyond the Cribbing at least 2 feet
B. The horizontal Wales which extend beyond the wall at least 2 feet
C. The braces set at a 45-degree angle and extended into the ground at least 2 feet
D. The vertical sheeting extended below the bottom of the excavation at least 2 feet
d
According to the OSHA Construction Safety Standards, what is required for shoring
systems more than 20 feet deep?
A. The Architect shall design the protection system
B. The Project Engineer shall design the protection system
C. The designated Competent Person shall design the protection system
D. The Registered Professional Engineer shall design the protection system
d
What is another name for Sheeting?
A. Piles
B. Struts
C. Uprights
D. Caissons
c
What does “close sheeting” mean in relationship to a shoring system?
A. The span across the width of an excavation
B. The spacing between timber planks not to exceed ½ inch
C. Tongue and groove timber planks at least 3 inches thick
D. The use of a trench box or trench shield while working in the excavation
b
Which piece of equipment and attachment would be the most efficient method to excavate
inside a cofferdam?
A. Shovel with a 3-CY bucket
B. Backhoe with a 3-CY bucket
C. Crane with an Auger attachment
D. Crane with a Clamshell attachment
d