A Gant chart is which type of scheduling
tool?
A. bar chart
B. activity on arrow network
C. activity on node network
D. precedent diagram
A. bar chart
What classification of activity would “shop
drawing rejection” be?
A. acceleration
B. design
C. procurement
D. construction
C. procurement
Which of the following defines the term trade
stacking?
A. the loss of worker productivity from
overtime work
B. the inefficiency from redoing work
C. the loss of productivity in the seasoned
workforce from training new hires
D. the loss of productivity by placing too
many workers in too small a space
D. the loss of productivity by placing too
many workers in too small a space
What type of relationship would best
describe “installing the scratch coat of
stucco” and then “installing the top coat of
stucco”?
A. finish to start
B. start to start
C. finish to finish
D. start to finish
A. finish to start
. What classification of activity would
“building programming” be?
A. acceleration
B. design
C. procurement
D. construction
b
Which of the following is the proper Design Activity Sequence that is used for every
design discipline (such as mechanical, electrical and structural) on a Design/Build logic
network according to acceptable legal practices?
A. Engineer, Design, and Build
B. Design, Procurement, and Construction
C. Prepare Schematic Diagrams, Prepare Preliminary Plans, Develop Contract
Documents, and Issue Bid Plans
D. Obtain Construction Contract, Request Plans, Receive Plans, Award Subcontracts,
Procure Materials, and Construction Activities
C. Prepare Schematic Diagrams, Prepare Preliminary Plans, Develop Contract
Documents, and Issue Bid Plans
Which of the following is the proper Procurement Activity Sequence that is used for
every Vendor or Supplier ( such as Rebar, Structural Steel and Sheet Metal) on a
Design/Build logic network according to acceptable legal practices?
A. Design, Procurement, and Construction
B. Order and Deliver Materials, Place Forms, Place Rebar, Pour Concrete, and Strip
Forms
C. Award Vendor Contract, Vendor Prepares Shop Drawings, Contractor Reviews
Shops, A/E Reviews Shops, Vendor Fabricates and Delivers
D. Prepare Design Plans, Award Vendor Contract, A/E Approves Design, Order
Materials, Fabricate, A/E Approves Shop Drawings, Contractor Approves Shop
Drawings, Vendor Delivers Materials
Award Vendor Contract, Vendor Prepares Shop Drawings, Contractor Reviews
Shops, A/E Reviews Shops, Vendor Fabricates and Delivers
Many times the contractor must indicate a sequence of activities as consecutive because
of crews or equipment available, What is the term for this sequence called?
A. Restraints
B. Total Float
C. Critical Path
D. Project Duration
A. Restraints
Leadtimes are used to determine the estimated time durations for what type of activities?
A. Design Activities
B. Procurement Activities
C. Construction Activities
D. Project Closeout Activities
Questions 5 and 6 are based on the following information. A list of sequential activities
with a Finish to Start relationship and their estimated durations are provided below:
ACTIVITY DESCRIPTIONS DAYS
Prepare the Reinforced Concrete Schematic drawings 28
Prepare the Preliminary Plans for the Reinforced Concrete Structure 32
Develop the Reinforced Concrete Bid and Contract Documents 12
Issue the Plans for Bidding and A/E Obtains bids 22
Award Rebar Vendor Contract 7
Vendor Prepares Rebar Shop Drawings 24
Contractor Reviews Rebar Shop Drawings 10
A/E Reviews Rebar Shop Drawings 10
Vendor Fabricates the Rebar according to Approved Shop Drawings 33
Deliver the Rebar to the Job Site 6
Contractor moves the Rebar from the storage area to the Placement Area (Rehandles) 1
Contractor installs the Rebar for the Footing Columns 3
Contractor calls for a Footing Inspection and the Inspector Inspects and Approves Rebar 2
Contractor Pours Concrete for the Columns 1
Contractor installs the Rebar for the Elevated Slab 6
5. What is the total estimated time in days for the Design of the Rebar?
A. 60
B. 94
C. 184
D. 197
B. 94
Questions 5 and 6 are based on the following information. A list of sequential activities
with a Finish to Start relationship and their estimated durations are provided below:
ACTIVITY DESCRIPTIONS DAYS
Prepare the Reinforced Concrete Schematic drawings 28
Prepare the Preliminary Plans for the Reinforced Concrete Structure 32
Develop the Reinforced Concrete Bid and Contract Documents 12
Issue the Plans for Bidding and A/E Obtains bids 22
Award Rebar Vendor Contract 7
Vendor Prepares Rebar Shop Drawings 24
Contractor Reviews Rebar Shop Drawings 10
A/E Reviews Rebar Shop Drawings 10
Vendor Fabricates the Rebar according to Approved Shop Drawings 33
Deliver the Rebar to the Job Site 6
Contractor moves the Rebar from the storage area to the Placement Area (Rehandles) 1
Contractor installs the Rebar for the Footing Columns 3
Contractor calls for a Footing Inspection and the Inspector Inspects and Approves Rebar 2
Contractor Pours Concrete for the Columns 1
Contractor installs the Rebar for the Elevated Slab 6
What is the total estimated in days for the Rebar Leadtime?
A. 90
B. 94
C. 103
D. 197
A. 90
How should the nodes on a logic network be numbered?
A. Consecutively
B. Separated by a minimum of five numbers
C. The preceding node is greater than the following node
D. The following node is greater than the concurrent node
D. The following node is greater than the concurrent node
How is Free Float defined?
A. The amount of slack in a node
B. The amount of slack between acrtivities
C. The amount of slack within a path (series) of activities
D. The amount of slack accumulated throughout the logic network
B. The amount of slack between acrtivities
What is the name of the term called for shortening a logic network?
A. Crashing
B. Fast tracking
C. Resource Leveling
D. Timed scaled networking
A. Crashing
- What types of activities are considered first when shortening the length of a project?
A. Zero float and least cost
B. Zero float and highest costs
C. Highest floats and least cost
D. High floats and highest costs
A. Zero float and least cost