Programming & Planning Flashcards
Concurrent Delay
Where two or more events happen at the same time that are caused by different parties causing delay.
There is no dominant cause of delay
Critical Path
The longest sequence of activities that must be completed to deliver a project.
Identifies where the bottlenecks in the project are.
Project can only be reduced if an activity on the critical path is reduced.
Benefits of Critical Path
Visualise Dependencies
Float Calculation
Improve organisation
How to compile a programme for a new project
Understand purpose
List all the activities
Assign durations to activities
Identify the relationship between activities
Float and critical path is to be highlighted
RIBA Stages
0 - Strategic Definition 1 - Feasibility 2 - Concept Design 3 - Spatial Coordination 4 - Detailed Design 5 - Construction 6 - Handover 7 - Use
What is the programme float
Amount of time an activity can be delayed without impacting the critical path.
Drop-Line Programme
Identifies what activities are ahead or behind.
Delayed activities are those that deviate to the left.