JCT

A

Made between employer and contractor
Building project only
Standard set of clauses
Relevant Events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

NEC

A

New Engineering Contract
Building and civil engineering projects
Can be edited to a number of bespoke contracts
Compensation Events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Letter of Intent

A

Instructing the contractor to proceed with the works before the main contract has been agreed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Advantages of NEC

A

Flexibility - Adaptable forms of contract
All Disciplines - building and civil
Written in plain English

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Advantages of JCT

A

Standardisation over common issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a compensation event

A
Events that do not rise from a contractors fault and can be compensated in the form of additional time and money.
Access to site
PM Stops work
Force Majure
Adverse weather
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Early Warning Notices

A

NEC

Notices issued that could affect completion and the cost of the project.