Contract Practice Flashcards

1
Q

What are EOT’s

A

Adjustment of the completion date and relived the contractors liability to pay liquidated damaged for the period of extension.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Procedure to Claim an EOT

A

As soon as the delay is apparent it needs to be informed of
This needs to identify the cause of the delay and if any of the causes are relevant events, giving an indication of the likely delay.
This is to be reviewed by the Project Manager where further information can be requested.
Notify the decision in writing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are Relevant Events

A
These are set out in the contract and some exmaples are:
Variations
Instructions
Loss or damage from Specified Events
Terrorism
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Purpose of a Valuation

A

To provide advice on the certifier to allow them to issue their interim certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly