PROGRAMMING AND PLANNING - Level 3 Flashcards
Who owned the float in your Westhorpe Gardens project?
In this JCT contract it was silent, in industry this is said to be owned by the project if this is silent.
What is float
describes the amount of time that an event or activity can be delayed without delaying the overall completion of the works
What different types of float are there?
NEC Principals
- Total Float
- Free float
- Terminal Float
What is total float
Total float is the amount of time a task can move without impacting the final project delivery date
what is free float
amount of time that a schedule activity can be delayed without delaying the start date of any immediately following schedule activities
what is terminal float
• Terminal: the duration between planned completion and the current contract Completion Date.
What are the fundamental difference between JCT and NEC with regards to programmes?
JCT
• Not a contract document
• requires the contractor to submit a master programme for execution of the works as soon as possible after the contract is executed.
• There are no details as to what sorts of things such programme should show and there are no requirements to submit revisions of this programme
NEC
• Key contract document
• NEC demands a more detailed set of documents that make up the programme to be submitted at the regular basis prescribed by the employer.
• When accepted by the project manager, this becomes the tool by which change is assessed, progress is monitored and assists the management of early warnings and compensation events (see later).
How can you differentiate concurrent delay from other delays?
Concurrent delay” means a situation where a construction project is delayed by two events at the same time, one being an event for which the employer takes responsibility under the contract and the other for which the contractor takes responsibility.
Are there any alternatives to using a Gantt Chart?
- Critical path analysis
* Information release schedules
On your White City project, you mentioned that the interim application was less than the forecasted cash flow. What did you do to assess if the programme was in delay?
- Reviewed programme against site progress
* Also queried with the contractor if there was any reasoning for this such as re-squencing or material delays
Talk me through your understanding of term critical path in relation to a construction programme.
- the longest sequence of tasks that must be completed to successfully conclude a project, from start to finish on time.
- The tasks on the critical path are known as critical activities because if they’re delayed, the whole project will be delayed.
Can you give me a few examples of different programming and scheduling techniques including any computer software you are aware of in order to create these programmes and schedules.
Scheduling techniques –
• Gannt charts: It utilizes the bar charts to depict the plan as well as the progress of the project.
• Critical path method: sequence of tasks and projects following the specific path
• Q scheduling: It focuses on scheduling the materials and equipment
• Line of Balance : repetitive activity.
Software – Microsoft Project and Asta
What is your understanding of acceleration when it comes to construction project programming?
speeding up the work of a contractor so that an activity, or the project as a whole, can be completed before the date required under the contract.
Are you aware of any acceleration techniques that may be able to be implemented should a project require accelerating?
- Working overtime.
- Adding new shifts.
- Providing additional labour.
- Providing additional resources, such as plant and equipment.
- Re-sequencing work activities (also known as project crashing or fast tracking).
- Adopting alternative construction methods, such as off-site manufacturing.
- Changing the design or specification.
- Reducing the scope of the works
- Early procurement of key items.
Talk me through the process you go through when preparing to create a project master programme. What information would you typically need and where would you expect to get this information from?
- Client approval dates,
- Design programme
- design freezes
- planning application timescales
- Procurement and tender timescales