CONTRACT PRACTICE - Level 3 Flashcards
What is Insurance Option A:
Contractor takes out and maintains joint names all risks insurance of the works
What is Insurance Option B:
Employer takes out and maintains the joint names all risks insurance of the works
What is Insurance Option C :
the Employer to maintain a joint names policy for existing structure
Letter of Intent main types
1) Comfort Letter - not legally binding
2) Agreement to spend - Legally binding
3) Recognition of entering contract - Legally binding
Commerce Road - Client chose not to Levy LD’s how would this be recorded
In the Final Account Statement
Give an example of when you have advised a Client on Contract Selection.
- Colville 2C – Proposed procurement route options (Traditional, D&B, Contract Management, Management Contracting, Partnership) – prepared in a report.
- Parkhouse Street – Demo (Int) or Demo + Works (D&B)
You mentioned that the Contractor failed to complete works by the Contract Completion Date on Commerce Road. What did you do?
Issued Certificate of Non Completion, and notice that Employer may wish to levy LD’s
You’ve mentioned JCT in your write up, but what other Suites of Contract are you aware of?
- NEC
- FIDIC
- ACA
What are the differences between a JCT and NEC?
- PM Vs CA/EA
- JCT use England and Wales, NEC Internationally
- NEC programme key contract document and prescriptive what is included
- EOT Vs Compensation Events (How time and money are managed)
Can you give me an example of some of the Bonds you are aware of? Have you experience any of them?
- Performance Bond (Yes)
- Advance Payment Bond
- Retention Bond
- Off site materials bond
On Colville Phase 2C, what was the procurement route recommended in your report, and what were the principle reasons?
- Use of a framework – able to select tenders with relevant experience and would reduce timescales.
- And use Design and Build procurement using JCT contract – two stage tender
- Design and Build as client wanted Contract Sum before starting works
- wanted to transfer design risk to contractor
- Familiar with form of contract
On Varcoe Road, did you have to issue a payment notice even though it was a nil cost.
Yes as the contractor had submitted an application for Payment, no this was required in line with the Construction Act.
On Varcoe Road, what works were complete (approx. value) before the performance bond was in place?
Demo had commenced and piling, I advised my client of there available options and risks associated with doing so.
Varcoe Road: Also, what contractual terms were your advice based on, was it an amendment to the standard contract?
I was not party to agreeing the contract terms, however yes there was an amendment.
On Varcoe Road, was there any other alternatives, rather than issuing a nil valuation?
- I advised my client they may wish, by agreement with the contractor to hold a total of 10% retention until the Bond was in place.
- Or terminal as contractor was in breach of contract