Programming and Planning Flashcards

1
Q

What is Acceleration?

A

The mechanisms for bringing forward the Completion/key date to before the contractual completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the critical path?

A

The longest path from start to finish; it indicates the minimum time necessary to complete the entire project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name 5 Delay Analysis methodologies?

A

Impacted as Planned
Collapsed As Built
As Planned v As Built
Time Impact Analysis
Window Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is concurrent delay?

A

where delay to project completion is caused by two or more factors, one of which is the contractor’s responsibility and one of which is the employer’s responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly