How have you provided good client care on a project?
How do you identify client requirements
How do you identify how often and in what ways to communicate with your client?
What KPIs have you used for performance feedback and why?
What was in your scope of services and appointment documents?
What techniques have you used to calculate risk?
Used Several mechanisms
Used a set contigency amount - 10%
Quantitative Risk Analysis - cost and schedule
P80 value from Monte Carlo - used Primavera risk analysis
Monte carlo use impact duration ranges for risk events
- need fully quantified risk register - 3 point estimate for impact min, most likely and max value
Expected monetary value - probably x cost
Qualitative RAG rating