Contract Practice Flashcards
What is a Tort?
A body of law that creates & provides remedies for civil wrongs that do not arise out of contract
What is the difference between statutory and contract provisions
Statutory - implied by law and be complied with regardless of contract
Contract - relates to contract, specific to project
What is a contract?
A legally binding agreement between parties enforceable by law.
Sets out details of agreement and mechanisms to be used during the course of a project
What is contract administration?
Administering the provisions of the contract such as:
- payment
- change control and variations,
- substantial completion,
- extension of time,
- resolving disputes
- settlement of the final account
What do you need to make a contract?
- Invitation-Employers invitation to tender (scope of works, design, proposed Ts&Cs)
- Offer-Contractors tender (proposed amendment to terms/agreement terms)
- Acceptance-Employers acceptance of tender
- Intention (to enter into contract)-Intention of the parties to create legal relations
- Consideration-Some right, interest, profit or benefit accruing to the one party, or some forbearance, detriment or loss undertaken by the other
- Must be lawful-Not an illegal act
What are express terms?
Those set out in writing in the contract
What are implied terms?
Those not specifically set out in the contract but which are implied
How can terms be implied in a contract?
- Implied in fact (not set out in the contract)
- Implied by law (legal requirements)
- Implied by custom
- Implied by routinely part of business
What are the two different ways a contract can be signed?
- Under-hand
2. A deed
What is the difference between an information requirement schedule & an information release schedule?
Information Required Schedule - asks contractor to provide dates when design information is required.
Information Release Schedule - tells contractor when the design information will be available
What are the provisions under the Construction Act? (HGCRA 96)
Payment: The Act requires payment to be made within a certain timeframe, which is set out in the contract. It also allows parties to submit payment applications, and provides for the right to suspend performance if payment is not made.
Adjudication: The Act provides for a statutory right to adjudication, which is a fast-track dispute resolution process. Parties can refer disputes to adjudication at any time, and the decision of the adjudicator is binding, although it can be challenged later in court or arbitration.
Notices: The Act requires certain notices to be served at various stages of the construction process, such as notices of payment due and notices of intention to withhold payment.
Retention: The Act provides for the use of retention, which is a percentage of the payment that is held back by the payer as security for the performance of the contract. The amount of retention is limited, and there are strict rules on when and how it can be released.
Suspension and Termination: The Act allows parties to suspend or terminate the contract in certain circumstances, such as non-payment or failure to proceed regularly and diligently with the works.
Why was The Housing, Grants, Construction and Re-generation Act (HGCRA) 1996 introduced?
To improve the payment practices in the construction industry and to provide a framework for dispute resolution.
When does the Construction Act 1996 apply?
Applies to all contracts for works classified as ‘Construction operations’
Give some examples of works not classified as ‘construction operations’ and excluded from the Construction Act
Drilling for oil/gas
Extraction of minerals
Tunnelling
Artistic works/scuptures
Manufacturing of components
Give some examples of the 2011 Amendments to the Construction Act
The Act now applies to all construction contracts, whether they are in writing, partly in writing, or entirely oral (previously it was just written contracts)
Clients must issue a payment notice even if no payment is due and this must be issued within five days of the payment being due
If works are suspended by contractors due to non-payment they are now allowed to recover costs and expenses incurred in doing so and are to be granted extensions of time where applicable to cover the programme effects of suspension
Contracts can no longer define which party is to bear the costs of the adjudicator. (was viewed as a disincentive to commence proceeding). It is now generally up to the adjudicator who pays their fees.