Programme (Additional) Flashcards

1
Q

PERT

A
  • Programme Evaluation and Review Technique
  • Flow chart diagram sequences all tasks
  • Records earliest and latest start and finish date for each task
  • Determines float and critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical Path Analysis

A

Identifying the activities necessary to complete a task, the time necessary to finish each activity and the relationships between the activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who owns float?

A
  • Controversial question – typically contractor, answer of ‘whoever gets there first’ dubious
  • JCT: contractor owns float as only start and finish dates in contract
  • NEC: float owned by project, more collaborative approach
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is lead and lag?

A

Lag – delay between start dates of two tasks

Lead – overlap of the two tasks until first one finishes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly