Product portfolio management & Aggregate project planning Flashcards

1
Q

Product portfolio management can be divided into three parts, which are they?

Which tools can be used in each
part?

A
  • Maximize value of portfolio
    Tool: Scoring models
  • Achieving a balanced portfolio
    Tool: Bubble diagrams
  • Strong link to strategy
    Tool: Strategic buckets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Aggregate project planning can be divided into 8 steps, which are they?

A

Has a focus on resource allocation

  1. Define the types or classes of development projects that are to be covered by the aggregate project plan
  2. Determine a typical example project in each class
  3. Compute how many projects that can be undertaken at the same time
  4. Compute resource allocation
  5. Compute the resources available
  6. Establish the desired future mix of products
  7. Choose projects to pursue
  8. Implement changes implied by previous steps