Procurement and Tendering Flashcards

1
Q

What is Procurement?

A

The overall process of acquiring construction work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are advantages of Traditional Procurement?

A

Higher quality
Cost certainty
Design control and change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What disadvantages of Traditional Procurement?

A

Longer duration
No buildability
Dual responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are advantages of Design and Build?

A

Single responsibility
Cost certainty
Buildability
Earlier site commencement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What disadvantages of Design and Build?

A

Comprehensive brief required
Early design commitment required
Design change difficult
Harder to compare tenders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the advantages of Management Contracting?

A

Shorter duration
Buildability
Design change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What disadvantages of Management Contracting?

A

Cost certainty only at end
Little incentive to reduce costs
MC has little legal responsibility for contractor defaults

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the advantages of Construction Management?

A

Shorter duration
Buildability
Design change

Clear roles
Direct contractual links with contractors (lowering costs; means of redress)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the disadvantages of Construction Management?

A

Cost certainty only at end
Client must be proactive and deal with a lot of consultants and contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Partnering?

A

An approach of structuring business relationships to achieve mutual objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Project Partnering?

A

Contractors are included in the partnering process from design stages with both owning risk and delivering solutions [negotiated contract? serial tendering?]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Strategic Partnering?

A

A long term partnership for purposes of undertaking several projects over time, using framework agreements setting out terms and conditions [serial tendering? measured term contracts?]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Tendering?

A

The process of generating quotations from contractors looking to obtain an award of business.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Open Tendering?

A

An indiscriminate request on the open market for tenders to be submitted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Selective Tendering?

A

A selective request for tenderers from those pre-selected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the advantages of Two Stage Tendering?

A

Buildability
Collaboration
Early start
Management of risk

[Design and Build: 2 Stage ie PCSA]

17
Q

What are the disadvantages of Two Stage Tendering

A

No cost certainty
Pre-construction fees [D&B: 2 Stage ie PCSA]
Parties not agree

18
Q

Why use Two Stage Tendering?

A

For complex building [Not D&B: 1 Stage]
Early completion
Buildability

19
Q

What is Serial Tendering?

A

Tenderers asked to bid on the basis of if complete initial project successfully [KPIs], other similar projects will follow using the same rates.

20
Q

What are Employer’s Requirements?

A

They set out the requirements of the Employer:
Function
Size
Accommodation
Quality
Submission details required from the Contractor

21
Q

What are the Contractor’s Proposals?

A

They are the response to the Employer’s Requirements and often include:
Drawings
Specifications
Workmanship

22
Q

Categories of information typically required in a Pre-Qualification Questionnaire (PQQ)?

A

FQERSCS

Project details
Contract to be used
Turnover and accounts [capacity]
H&S records
QA and Environmental Policies
Bonds and Warranties required
Parent Company Guarantees required

23
Q

What are the Sections in a Tender Report?

A

Refer to Key Documentation Flashcard Deck