Design Economics and Cost Planning Flashcards

1
Q

What is Buildability?

A

Harnessing the contractor’s expertise during the design stage for efficient methods of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Section 106 Agreement?

A

Agreements between local authorities and developers negotiated for planning consent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Shell and Core?

A

The basic structure, services, and envelope with fit-out to common areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a CAT A fit out?

A

Generic fit out to lettable areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a CAT B fit out?

A

Bespoke fit out to lettable areas ready for occupation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an Order of Cost Estimate?

A

Determination of possible cost early in design in relation to fundamental requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Purpose of an Order of Cost Estimate?

A

To establish if affordable and the maximum expenditure the client is prepared to spend.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Functional Unit?

A

A unit of measure that considers the prime use of a building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Cost Plan?

A

A presentation of the estimated costs in an elemental format showing how costs are distributed across different elements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Purpose of a Cost Plan?

A

To control the development of the design to the agreed cost limit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Principle components of a Cost Plan? (Report)

A

CPOCIAEAD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Main elements of an estimate? (elemental)

A

EDF FUERISE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Contingency?

A

A sum to cover unknown expenses or unmitigated risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Value Engineering?

A

An approach aimed at providing the necessary functions of the building at the lowest cost without detrimental affects to quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Value Management?

A

A process of defining what value means to the client and putting in procedures to ensure maximum value first time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Value?

A

A measure taking into account the benefits in relation to cost.

17
Q

Phases of the VE process?

A

ISEDP

18
Q

Why is Value Management needed?

A

Each client has own specific objectives and defining value avoids risk of failure.

19
Q

What is Contingency?

A

A sum included to cover i) unknown expenses, or ii) unmitigated risks.

20
Q

How is Contingency assessed?

A

A reflection of the i) unknown specific items, or ii) the risks

21
Q

How is Contingency calculated?

A

5-10% at early design stages
As more detailed information becomes available - a Risk Register with probability x cost impact (totalled for all risk items)

22
Q

What are the Stages of the RIBA Plan of Works?

A

Sd Pr.Br CdScTd Ma.Co HaUs

23
Q

The expected design information available at each of the stages?

A

Refer to mu other flashcards

0 -
1 -
2 -
3 -
4 -