Procurement and Tendering Flashcards

1
Q

Can you explain to me a two stage tendering strategy?

A
  • First stage tender enquiry issued at RIBA Stage 2-3
  • Contractor selected on quality of bid, quality of team
  • Prelims price and OH/P allowance.
  • Preferred contractor joins design team on pre-construction services agreement and develops project to RIBA Stage 4, then presents bid for delivering project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the pros and cons of Two stage Tendering?

A

Pros
- Ability to overlap design and tendering / Quicker start on site
- Benefit of Contractor knowledge/builability through design
- Increase opportunity to Value / Risk management with the contractors’ input.

Cons
- Lack of competitiveness during 2nd stage
- Time/continuity implication to re-tender if second stage unsuccessful.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Pre-Consruction Services Agreement?

A

Used between employer and contractor on two-stage tendering. Appointment follows period between first stage appointment to submission of definitive second stage tender / entry into the main contract for the Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain Single Stage Tendering?

A
  • Competitive open tender when identical ITT issued to number of contractors who submit tender by notified date.
  • Decision made on cost/quality and preferred bidder appointment made for the main works.
  • Usually at RIBA Stage 4 to ensure bid most reflects the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the key advantages of single stage tendering?

A
  • The employer benefits from a competitive tendering process which can lead to more competitive pricing
  • The employer can benefit from a fixed price through this tendering process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key disadvantages of single stage tendering?

A
  • No buildability input from the contractor (at the point of tender)
  • The price is only as good as the design information
  • Contractors may be unwilling to tender in a good economic climate (too much competition)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Negotiated Tender?

A

A negotiated tender is effectively a selective single-stage tender carried out between the client employer and just one contractor.

Negotiated tenders are obtained by the client, inviting one contractor of their choice to submit a tender response for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the key advantages of negotiated tender?

A
  • Simplicity
  • Speed, a negotiated process can have programme advantages if undertaken in good faith
  • The employer has flexibility in terms of choosing their preferred contractor
  • Time and cost savings involved in comparing and analysing multiple tender submissions
  • The process can allow early contractor involvement.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the key disadvantages of negotiated tender?

A
  • Possibility of delay if contract negotiations are protracted
  • Potential cost premium due to lack of competition
  • There is a heavy reliance on trust between parties
  • It can be seen as anti-competitive and exclusive - may put off potential other tenderers in future.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How could you justify value for money in a negotiated tender?

A
  • Insist on an open book approach when agreeing the package
  • Benchmark where necessary using BCIS/current market knowledge.

subcontract packages and a minimum of 3 quotes to be provided for each element of the works (this would need to be agreed upfront with the contractor).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Procurement?

A
  • The overall act of obtaining goods and services for a construction project.
  • There are several routes by which the design and construction of a building can be procured. The selected procurement route should follow a strategy which fits the project criteria and objectives.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the main factors that typically govern procurement route selection?

A
  • The key is to identify the client’s objectives and key drivers in terms of time, cost and quality. Other factors such as risk allocation should also be considered.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What procurement options are you familiar with?

A
  • Traditional procurement
  • Design and build
  • Management contracting
  • Construction management.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Traditional Procurement?

A
  • The traditional procurement route involves separating design from construction. The employer first appoints consultants to design the project in detail, contractors are then invited to submit tenders based on a fully operational scheme.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the key advantages? (Traditional Procurement)

A
  • The employer retains control of the design
  • The design is largely finalized before the contractors tender for the build, this means the employer knows exactly what they are getting
  • All tenderers produce a submission based on the same information (tender returns easier to compare)
  • Assuming the design is robust, reasonable price certainty is achieved at contract award
  • Minimal built-in contractor risk premium (unlike design and build)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the key disadvantages? (Traditional Procurement)

A
  • The overall project duration may be longer than design and build
  • Zero or limited contractor builder input
  • Design risk is retained by the employer, any changes post contract will be a variation or compensation event
  • Dual point of responsibility (employer for design and contractor for construction)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When might traditional procurement be appropriate?

A
  • The employer may have specific or detailed design requirements
  • Cost certainty is important
  • The shortest overall programme is not the employer’s main priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is Design and Build?

A

The contractor is responsible for completing the design and executing the construction phase of the project. This is a completely different approach to delivering a project via traditional procurement, where the client appoints consultants to undertake the design and then a contractor is appointed to construct the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the key advantages? (Design and Build)

A
  • Single point of responsibility for design and construction (contractor)
  • Earlier commencement on site is possible (if design and construction can be overlapped)
  • Benefit of contractor’s experience harnessed during design (buildability input)
  • Design and construction risk rest with the contractor
  • Provides more cost certainty than traditional procurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the key disadvantages? (Design and Build)

A
  • The design is only as good as the employer’s requirements
  • More complex to compare tender returns
  • Employer changes can be difficult to value and expensive
  • the employer may have less control over aesthetics and quality
  • The contractor will build in risk premiums into their tender returns
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

When might design and build be appropriate?

A
  • Where there is need to make an early start on site (D&B has the potential to overlap design and construction)
  • Where the employer wishes to minimize their risk profile
  • For technically complex projects, the design will benefit from the contractor’s buildability input.
  • Where retaining control of the design is not the priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What additional insurances might be needed under a D&B contract?

A

The contractor and their design team will have design responsibility, therefore, it is likely additional professional indemnity insurance (PII) will be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are employer’s requirements (ERs)?

A

The expression employer’s requirements is used to describe the document(s) produced by the employer to set out its requirements in relation to the project and this is what the design and construction of the works will be based on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are contractors proposals (CPs)?

A

CP takes precedence if conflict with ERs

  • CPs are prepared by the contractor which responds to the employer’s requirements.
  • In this document(s), the contractor will set out a more detailed design (based on the employer’s requirements), which will require further development throughout the course of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Which procurement route poses the least risk to the employer?

A

Design and build, this is because design risk is transferred to the contractor.

26
Q

What is Construction Management?

A

The employer directly appoints multiple subcontractors (known as trade contractors) instead of employing a single main contractor. The single feature that makes construction management unique, particularly from management contracting, is that the employer places individual contracts with separate specialist trade contractors themselves.

27
Q

What are the key advantages? (Construction Management)

A
  • Speed to get to site
  • Overall project duration reduced by overlapping design and construction
  • The construction manager can contribute to the design and project planning processes
  • Changes in the design can be accommodated without paying a premium
  • Prices may be lower due to direct contracts with trade contractors
  • The employer has means of redress with trade contractors through direct contractual links.
28
Q

What are the key disadvantages? (Construction Management)

A
  • Price certainty not achieved until the last trade package is let
  • The procurement route requires an informed, experienced and proactive employer to work
  • Wider spans of control - the employer has a lot of consultants and contractors to manage.
29
Q

When might construction management be appropriate?

A
  • The employer is experienced in construction and has the suitable resources to manage the project.
  • the employer wants to achieve an early start on site.
  • the employer wants the flexibility to make minor changes to the design/specification throughout the process with minimal impact on time or finances
  • the project is technically complex and requires detailed engagement of specialist consultants and trade contractors.
30
Q

Which is the riskiest procurement route for the employer?

A

Construction management. This is because the employer places individual contracts direct with each trade contractor and the construction manager carries no risk (barring professional negligence)

31
Q

What is Management Contracting?

A
  • The employer appoints a management contractor to manage the entire building process who in turn appoints trade contractors to carry out the construction works
  • The management contractor is usually paid a fee percentage based on construction costs
  • The management contractor has a direct contractual link with the trade contractors and is responsible for the overall construction works.
32
Q

What are the key advantages? (Management Contracting)

A
  • Overall project duration can be reduced by overlapping design and construction
  • The management contractor will provide buildability input
  • Single point of responsibility (management contractor)
  • Trade packages are let competitively and transparently
  • There can be considerable flexibility in the design, with changes being made throughout the construction process
33
Q

What are the key disadvantages? (Management Contracting)

A
  • Price certainty not achieved until the last trade package is let.
  • Requires an informed and proactive employer to be successful
  • Depending on how the construction manager is remunerated, there may be a built-in disincentive for the management contractor to minimize costs.
34
Q

What is a Framework Agreement?

A
  • A framework agreement is an umbrella agreement that a party enters with one or more suppliers (who may be contractors, suppliers or consultants) to establish governing terms.
  • A framework usually sets a strategic partnering relationship for the procurement of goods, works or services.
35
Q

How long can a framework be?

A

Typically, a framework agreement lasts for 5 years. however this is determined by the buyer. They can range between 2 and 10 years.

36
Q

What are the key advantages? (Framework Agreement)

A
  • Framework agreements help develop stronger relationships between the parties involved and encourage long term collaboration and co-operation
  • Time saving (can speed up the procurement of goods and services)
  • Repeat work and continuity of delivery
  • Rates and prices are usually agreed upfront
37
Q

What are the key disadvantages? (Framework Agreement)

A
  • The contractor, suppliers or consultants can become complacent
  • Bidders will invest time and money to be awarded onto a framework and then potentially not receive any work through them
  • May be restrictive to new suppliers who offer innovative, new, solutions with the changing nature and evolving nature of technologies for example.
38
Q

Why might the employer choose a framework agreement to procure goods and services?

A
  • Employers that are continually commissioning construction works might want to reduce procurement timescales, learning curves and other risks by using framework agreements
  • A framework allows the employer to invite tenders from suppliers of goods and services on a call-off basis as and when required.
39
Q

What’s the difference between a framework agreement and a contract?

A
  • A framework agreement rarely provides any specific commitment in terms of project and value of works. It is more focused around being an approved supplier.
  • A contract is usually a specific fee, with project scope and timelines allowing you to quote a tailor your product/service for the specific job at hand.
40
Q

What is Project Partnering?

A
  • Partnering is a broad term used to describe a collaborative management approach that encourages openness and trust between the contracting parties.
  • There is more opportunity for building working relationships, finding improvements and planning investment
  • Ownership of risk is spread between the parties and a collaborative approach is encouraged to delivering the solution and overcoming problems
41
Q

What are the key advantages or partnering?

A
  • The overall construction and design programme can be shortened
  • The likelihood of conflict is reduced
  • Improved communication and mutual objectives
  • Improved customer satisfaction
  • Improved value for the employer
  • Improved buildability
  • Better predictability in terms of time and cost
42
Q

What are the key disadvantages of partnering?

A
  • Less opportunity to understand what other contractors/potential partners have to offer
  • Difficult to find a strong partner which the same objectives, ethics, attitude etc.
43
Q

What is Tendering?

A

Tendering is the process by which the employer invites the contractors to place a bid for work on a construction project. The overall objective is to obtain a price for the works.

44
Q

What is the difference between procuring and tendering?

A
  • Procurement is the overall act of obtaining goods and services from external sources and deciding the strategy on how these goods are to be acquired
  • Tendering is a phase in the procurement strategy and deals with obtaining a price through a bidding process and deciding how a contractor is appointed.
45
Q

What documents were included within your tender pack?

A
  • Invitation to tender (ITT), including cover letter with tender return information.
  • Form of tender
  • Contract conditions and employer’s amendments
  • Instruction to bidders including how errors will be dealt with
  • Tender scoring matrix
  • Project information, drawings, specifications, surveys, planning conditions etc.
  • Pricing document
  • PCI (Pre-construction information)
  • Quality questions (such as experience and methodology)
  • Receipt of tender
46
Q

What is a bona fide tender?

A
  • A bid submitted in good faith, complete and in prescribed form which meets the conditions of the bidding requirements.
  • Confirmation that the supplier has not colluded with another party when compiling the tender.
47
Q

What is a PQQ (Pre-Qualification Questionnaire)

A

pre-qualification questionnaire sets out a series of questions for potential tenderers to answer regarding their level of experience, capacity and financial standing etc. prior to being invited to tender.

48
Q

What is the purpose of a PQQ?

A

The pre-qualification questionnaire has the effect of reducing the number of potential tenderers to those that are genuinely appropriate for the project. This saves a great deal of time for potential tenderers who would not have any realistic change of winning the contract.

49
Q

What might the PQQ ask for?

A
  • Company details
  • Details of insurance cover
  • Financial information
  • Relevant experience
  • Information about technical and professional ability
  • Information capability and capacity
  • Health and safety policy and records
  • Quality assurance policy
  • Environmental management policy
  • Equal opportunities policy
  • References
50
Q

Would you open a later tender submission for a school project?

A

The tender should be discarded on the basis the project is funded by the public sector.

51
Q

What is the danger of accepting a very low tender submission?

A
  • The contractor may be trying to ‘buy’ the project to recover their costs with variations and/or claims.
  • It could indicate the contractor is in a poor financial or cash flow position and they are eager to win the work at any cost.
  • Areas of the project may not be priced accurately, potential for an adversarial relationship to develop post contract.
52
Q

How do you deal with qualifications within the tender submission?

A
  • Procedures associated with qualifications should be outlined in the tender instructions.
  • If the qualifications are unauthorized, it might invalidate the tender (leading to disqualification)
  • The employer team and contractor should look to resolve the qualifications prior to signing the contract. Any outstanding matters should clearly be documented in the contract to avoid future disputes.
53
Q

How would you deal with errors identified in the tender submissions?

A

JCT have produced a tendering practice note where two options are suggested to deal with errors, one of these options is usually drafted into the tender pack.

Alternative 1: The tenderer should be given details of the errors and afforded the opportunity of confirming or withdrawing their tender.

Alternative 2: The tenderer should be given the opportunity of confirming their offer or amending it to correct genuine errors.

54
Q

On what grounds would you advise the client to re-tender?

A
  • Not enough tenderers returned tenders
  • The tendering procedure is compromised for some reason
  • If tender were not at the cost level required and it was believed that re-tendering to different tenderers would provide a different result
  • Design changes or VE has been carried out that has significantly changed the design that was originally tendered on
55
Q

How could you reduce the risk of contractors pulling out of the tendering process?

A
  • Ensure the tender information is as accurate as possible
  • Ensure the tender period is long enough (extend if required)
  • Go through the PQQ (pre-qualification questionnaire ) to ensure the correct tenders are selected.
  • Check the contractor have time capacity to complete the tender
56
Q

On what grounds would you advise your client to re-tender the project?

A
  • Not enough tenders returned
  • The tender procedure was compromised in some way (potential fraud, collusion, bid-rigging etc).
  • Significant design, methodology or programme changes after issuing the tender documents.
57
Q

What information is typically included in the tender analysis report?

A
  • List of tenders received
  • Initial tender return totals
  • Any qualifications identified
  • Post-tender adjustments
  • Revised tender sum
  • Issues to be resolved
  • Comparison of tender returns
  • Comparison with pre-tender estimate
  • Recommendation
58
Q

If the tender was not received on time, but the works were delayed and did not commence until a few months later, what would you need to check?

A

Check the form of tender, this would should how long the price (the offer) was valid for (for example, 60 or 90 days after the tender return date).

59
Q

If the contractor (in their tender return) put a cost against an item and marked it as provisional, what would you do?

A

I would seek further information from the contractor and request this to be removed, subject to the tender instructions, this may invalidate the submission.

60
Q

If you think the delivery programme is tight, how can you give comfort to the contractor regarding liquidated damages (to avoid them excessively pricing in their tender sum)?

A

The contract can be amended to include a liquidated damage free period. For example, damages would not be levied for the first 3 weeks or levied at 50% for a defined period.

61
Q

What is the purpose of a pre-tender estimate?

A
  • A pre-tender estimate (PTE) is the last cost check of the project before it is issued to tender. The design should be sufficiently developed at this stage; therefore, the PTE should be an accurate reflection of the works.
  • The estimate can then be used to compare against the tender submissions.
62
Q

What happens if the tender prices are higher than the pre-tender estimate?

A
  • This could be down to market conditions or some other external factor such as COVID-19 or Brexit.
  • The employer’s team should reconcile the tenders against the pre-tender estimate to identify where the major differences are.
  • The team could look to value engineer the project if the prices are over budget.