Construction Technology and Environmental Services Flashcards

1
Q

What is buildability?

A

Practical knowledge of how things work - Designers may not know best method of construction and contractor is there to convert design aspirations into best-fit in terms of value, Life Cycle Cost.
E.g. pre-cast steps at Headwall.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain benefits of pre-fabricated construction

A
  • Time reduction to construct on site / programme accuracy
  • money saving
  • Quality management / accuracy
  • Just in time deliveries
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain SUDDS

A

Sustainable Urban Drainage System (pourous material / attenuation) - reduces stress on exisitng drainage
Designed to allow sustained surface water to drain.

Examples are permeable pavings, swales and lagoons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What SUDDS do you have on your project?

A
  • Tobermore’s Hydropave system used on all driveways and non-adoptable road sections. A permeable hard-wearing block which is 100% recyclable and harvests 100% of the water used.
  • Swales for run off from the main and a lagoon for the adoptable road storm water.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does an Air Source Heat Pump Work?

A

An air source heat pump has two components; an outside and inside connected by a loop of pipe filled with refrigerant. Air pulled in from the outside and as circulated through compressor converts refrigerant liquid into gas (endothermic reaction) and circulates through a condenser which forces the gas back into a liquid (exothermic) where it releases energy through a heat exchanger to heat central heating system or hat water. Refrigerant then returns to outward facing unit to repeat cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are benefits of the ASHPs

A
  • cheaper to run over whole life cycle of system (20 years) - small amount electric to run / parts should last for whole life
  • Reduces CO2 emissions of the asset
  • Works on reduced operating temperatures - The refrigerant boiling point can be as low as -20 degreesC.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why did you use ASHPs on your project?

A

Condition (18) of planning permission required a scheme for the project to secure at least10% of predicted energy requirement from renewable/low-carbon sources.

ASHP reduced overall scheme consumption by 165k kWh/year compared to baseline boilers (DER). which was an improvement of 55% against baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are disadvantages of ASHPs

A
  • Higher capital installation costs
  • Requires exterior space to install unit
  • Requires building envelope to be thermally efficient (well insulated)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does a Ground and Air Source Heat Pump compare

A

Ground source:
- same lifespan (20 years)
- improved coefficient due to consistent temperature underground
- lower running costs
- no planning permission required

  • Higher/more intrusive installation costs
  • Requires larger outdoor area to lay pipework.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Government position on ASHPs

A

Government Heat and Buildings Strategy:
- Part of Net-Zero by 2050.
- Gas boilers banned from new builds 2025
- All Gas Boiler installations phased out by 2035
- Grants for ASHP/GSHP from 2022-2025

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Explain SAP Calculations

A

Standard Assessment Procedure (SAP) basis of compliance with Part L1A (overheating) of Build Regs 2014.
- SAP Calcs determine a Dwelling Emission Rate (DER) which compares value of energy requirements of similar dwelling to determine compliance with a Target Emissions Rate (TER)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What was Dame Judith Hackett Report?

A

Grenfell enquiry -
- Building Regs converted into manual
- Integrated into full PDF.
- All approved docs searchable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Building Act (1984)

A

Primary statute and Informs the Building Regs (2010)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Construction Skills Certification Scheme (CSCS)

A

CSCS cards provide proof that individuals working on construction sites have the appropriate training and qualifications for the job they do on site.

By ensuring the workforce are appropriately qualified the card plays its part in improving standards and safety on UK construction sites.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is CSCS Legal Requirement

A

No, although lots of principal contractors require on projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Difference between End-Bearing and Friction Pile

A
  • End-Bearing designed to transfer load at toe of pile once solid ground is penetrated
  • Friction Pile transfers its load along the entire shaft using friction between the pile and soil to achieve the required load when a solid layer cannot be penetrated.
17
Q

Explain bored vs driven piling

A
  • Bored = installed by auguring into the ground forming a hole into which concrete can be poured, thereby casting the pile in position.
  • Driven = hammered pre-cast into ground using vibration
18
Q

What is substructure?

A

All structure below the superstructure i.e. all structure below ground level including the ground floor bed

19
Q

What is Superstructure?

A

All internal and external structure above the substructure
Made up of primary (ext walls, stairs, roof, structural walls) and secondary (suspended ceilings / raised floors, balustrades, doors) elements and finishes (tiles, paint, stair nosings)

20
Q

What is the External Envelope?

A

The materials and components that form the external shell or enclosure of a building
May be load or non-load bearing

21
Q

What are the Building Regulations?

A
  • Statutory instruments that sets out the minimum performance standards for the design and construction of buildings
  • Supported by the Approved Documents A to R and other codes of practice
22
Q

What are the approved documents?

A
  • Part A: Structure
  • Part B: Fire safety
  • Part C: Site preparation and resistance to contaminants and moisture
  • Part D: Toxic substances
    Part E: Resistance to the passage of sound
  • Part F: Ventilation
  • Part G: Sanitation, hot water safety and water efficiency
  • Part H: Drainage and waste disposal
  • Part J: Heat producing appliances and Fuel storage system
  • Part K: Protection from falling, collision and impact
  • Part L: Conservation of fuel and power
  • Part M: Access to and use of buildings
  • Part N: Glazing - Safety in relation to impact, opening and cleaning
  • Part P: Electrical safety
  • Part O - Overheating
  • Part Q: Security - Dwellings
  • Part R: Physical infrastructure for high-speed electronic communication networks
  • Part S - infrastructure for electric charging points
  • Regulation 7: Materials and workmanship
23
Q

What are British Standards?

A
  • Publications issued by the British Standards Institution – prefixed BS
  • They give recommended min standards for materials, components, design and construction practices
    Identified by Kitemark
24
Q

What is a Modern Method of Construction?

A

MMC’s focuses on off-site manufacturing methods such as mass-production and factory assembly to improve the way assets are constructed.

MMC Definition framework sets out 7 categories including pre-manufacturing 2d/3d structural/non-structural systems to traditional building product led site labour reduction.

25
Q

What is ‘pre-manufacturing’

A

‘pre-manufacture’ encompasses processes executed away from final workface, includes off sit factories and near-site / pop-up factories on site.

26
Q

Can you give me an example of MMC?

A
  • Cross Laminated Timber (CLT) - planed and kiln dried timber usually, spruce, pine or larch and layered and glued at 90 degree angles - then pressed together.
  • Modular construction: Offsite factory assembly - example being bathroom/shower pods / corridor cassettes / internal walls which are delivered to site and installed/2nd fixed.
27
Q

What does the RICS publish on MMC?

A

RICS Research Paper Sept 2018: “MMC - A forward-thinking solution to the housing crisis”

  • Sets out construction industry 6% GSP / 10% Employment
  • benefits of MMC
  • Key recommendations include Govt should favour MMC in public infrastructure schemes - consider social value (build-to-rent / homelessness) - promote upskilling and implement in low employment areas.
28
Q

What is the Govt doing on MMC?

A