Processes Flashcards
According to the Project Management Institute (PMI)®, a good project manager spends how much time communicating?
90 percent
100 percent
75 percent
50 percent
90%
According to PMI, a good project manager spends up to 90 percent of their time communicating. Communication skills are essential for a successful project manager.
Status review meetings are an important tool for informing stakeholders (and others) of the status of the project. All of the following are true regarding status review meetings except for which one?
- They are a form of communication and include verbal and written material.
- Face-to-face meetings are more effective for team members than status review meetings because you’ll learn of potential risks and problems more quickly.
- You might have multiple status review meetings, each intended for different audiences.
- Verbally communicating at a status meeting is less complicated and more easily understood than written communication.
Face-to-face meetings are effective, but this statement is not true regarding status review meetings.
You are a project manager for Lightning Bolt Enterprises using a hybrid model to manage projects. Your new project involves the research and development of a new type of rechargeable battery. The project objectives should include which of the following?
- Quantifiable criteria, including elements such as cost, schedule, and quality measures
- A brief summary of the product description, including measurable, quantifiable product requirements that will help measure project success
- Quantifiable criteria derived from value engineering, value analysis, or function analysis
- A description of the business need that brought about this project
- Quantifiable criteria, including elements such as cost, schedule, and quality measures
The project objectives should include quantifiable criteria that can be used to help measure project success. Project objectives should include schedule, cost, and quality measurements.
You have decomposed the deliverables for your project as follows: Project Management, Design, Build, and Test. The Design deliverable is further decomposed to include these deliverables: product design document, blueprints, and prototype. Adequate cost and schedule estimates have been applied to all the deliverables. Which of the following has occurred?
Steps 1, 2, and 3 of decomposition have been performed for all the deliverables with the exception of the Design deliverable.
All the steps of decomposition have been performed.
Steps 1, 2, 3, and 4 of decomposition have been performed for all the deliverables.
Steps 1, 2, and 3 of decomposition have been performed for the Design deliverable.
Steps 1, 2, and 3 of decomposition have been performed for the Design deliverable.
The five steps of decomposition are to identify major deliverables, organize the WBS, decompose the WBS components into lower-level components, assign identification codes, and validate the WBS. No mention was made in the question of assigning identification codes or validating the correctness of decomposition, so not all of the steps have been performed. The first three steps of the decomposition process for the Design deliverable have been performed
Which of the following statements are true? Select 3
A highly adaptive life cycle has continuous involvement and frequent feedback from stakeholders. A highly predictive life cycle has reduced risk and costs due to detailed plans. A highly predictive life cycle contains requirements that are ambiguous. A highly adaptive life cycle performs Initiating activities regularly throughout the project.
A highly predictive (waterfall) life cycle typically has detailed specifications, while a highly adaptive life cycle (Agile) has requirements that are progressively elaborated. All other statements are true.
You are a project manager for Community Trends, a nonprofit organization. Your project has come about because of a social need. You’re calculating performance measurements and using actual costs to date, and you assume that ETC work will be completed at the budgeted rate. You know the following information: BAC = 900, ETC = 65, PV = 500, EV = 475, and AC = 425. Which of the following is the correct expected total cost at completion, given this situation?
875 804 850 379
Since EAC is based on actual costs to date and assuming ETC work will be completed at the budgeted rate, the equation to use for EAC is EAC = AC + (BAC – EV). In this case, your formula looks like this: $425 + ($900 – $475) = $850.
Which of the following characteristics do all project life cycles share?
Degree of uncertainty
Degree of planning
Degree of work sequencing
Degree of unfinished work
Degree of planning
According to the Agile Practice Guide, all project life cycles share the element of planning. What differs across predictive, iterative, incremental, and Agile life cycles is the degree to which planning is done, and when.
You are using the critical chain method to construct your schedule, and there are variances in your critical path tasks. Which of the following is true?
Delays to the noncritical path tasks won’t cause any further issues for the critical path.
You should compare the amount of buffer needed to what’s remaining to help assess if the schedule is on track.
Your schedule is not at risk yet, but you should monitor both critical and noncritical path tasks for further delays or variances.
You should use preventive actions to get the project back on track.
If the critical path tasks have variances, your schedule is at risk. You will use corrective actions at this point (not preventive actions) to get the project back on track, such as adjusting the amount of buffer. Significant delays to noncritical-path tasks can make them become part of the critical path.
Midway through the delivery of development services, a customer requested that new requirements be incorporated. When asked to submit a change request to modify the terms of the contract, the customer refused and insisted that the changes be implemented at no cost. After multiple discussions, neither party changed their stance on the situation. What technique will the project manager likely use to address this situation?
Conflict management
Inspection
Claims administration
Alternative dispute resolution
Claims administration is a tool and technique of the Control Procurements process. Claims administration involves addressing contested changes between the buyer and seller, which then converts into a claim.
A project manager works with the project team to identify lessons learned. The information captured will then be archived and summarized within the project’s final report. What activity is the project team engaged in?
Conducting a project meeting Updating the lessons learned register Capturing work performance information Administrative closure
Administrative closure
The project team is performing administrative closure activities associated with the Close Project or Phase process. While information captured will be added to the lessons learned register, administrative closure is a broader choice that captures additional activities noted in the question, such as archiving information and creating the final report.
Which of the following describes who is responsible for the quality assurance of the project?
Project manager and project team members Project team members, project manager, and stakeholders Project manager Stakeholders
The project team members, project manager, and the stakeholders are all equally responsible for the quality assurance of the project.
A project manager for a software development project has collected the work performance data and used the requirements documentation and requirements traceability matrix to generate the work performance information regarding variances in the project work compared to the baseline. What process is the project manager performing?
Validate Scope Control Scope Direct and Manage Project Work Manage Quality
To answer this question correctly, it is important to understand how work performance data is transformed into work performance information. Work performance data is produced as a result of project execution. The work performance data can then be analyzed during various controlling processes to produce work performance information (see the image below). Work performance information is only produced as an output during the Monitoring and Controlling Process Group. In this scenario, the question suggests that a variance analysis has been performed using work performance data in order to produce work performance information. Thus, it can be concluded that the process underway is part of the Monitoring and Controlling Process Group, and the two answer choices representing executing processes can be eliminated.
Both the Validate Scope and Control Scope processes produce work performance information as an output. However, only the Control Scope process uses variance analysis to produce work performance information regarding variances in the project work compared to the scope baseline. Therefore, of the available choices, the project manager must be executing the Control Scope process.
What action can a project manager take if the selected risk response strategy turns out not to be fully effective?
Actively accept the risk
Develop and implement a fallback plan
Update the risk register with the outcome
Document and respond to a secondary risk
A fallback plan, also referred to as a contingency plan, is a risk response strategy that is used when the initial response is not fully effective.
How are quality improvements implemented?
By submitting a change request and/or taking a corrective action
By submitting a change request and/or implementing a preventive action
By completing quality audits
By completing a quality audit and identifying gaps or shortcomings in the process
By submitting a change request and/or taking a corrective action
Completing a quality audit may lead you to the conclusion that a change request is needed, but you must submit a change request and/or take corrective action to implement the quality improvement.
The characteristics of project life cycles vary and should be considered when determining which life cycle is the best fit for a project. Match the delivery life cycle approach based on where it falls on the continuum when considering frequency of delivery and degree of change.
Predictive and iterative life cycles tend to have low frequencies of delivery, whereas incremental and agile have a high frequency of finished deliverables; both predictive and incremental experience few changes, while iterative and Agile experience very frequent changes based on customer feedback.
Which of the following project management documents records challenges, problems, realized risks, and opportunities?
Risk register Project documents Issue log Lessons learned register
The lessons learned register, created out of the Manage Project Knowledge process, records information about situations that have occurred within the project, including recording challenges, problems, realized risks and opportunities, and other information relevant for future reference. While “project documents” is a technically accurate answer, “lessons learned register” is a more specific answer.
The project processes are iterative, are results oriented, and interact with each other. Shewhart and Deming developed a concept that reflects this idea. Which of the following is the name of this cycle?
Strategize-Justify-Choose-Execute-Control
Plan-Do-Check-Act
Initiate-Requirements-Execute-Close
Select-Plan-Monitor-Act
The Plan-Do-Check-Act cycle was developed by Shewhart and later refined by Deming. It reflects the iterative, results-oriented, and interactive nature of the project process groups.
You are managing a project to develop a new robot for a mining rescue company. You are currently performing a monitoring and controlling project activity, and you have discovered that some of the project work has not been performed according to the plan. If these issues are not fixed before the next customer inspection, your project might be canceled. You have analyzed the situation, and the corrective action will only require a minor adjustment to a configuration element. What should you do first?
Implement the corrective actions
Delay the scheduled customer inspection
Submit a change request
Consult the project sponsor
All of the available answers seem like possible options in this scenario, but the question is specifically asking what you should do ‘first’. Although you have already analyzed the situation and you know what corrective actions are required, you must follow the proper change control procedure. A configuration element is a project artifact that has been placed under configuration control. Any change to a configuration element should be formally controlled and will require a change request. Since the question describes a situation requiring a change to a configuration element, the first thing you should do is submit a change request and have it approved before you can implement the changes.
The Project Integration Management Knowledge Area is concerned with which of the following?
- Identifying the people, groups, or organizations that could impact or be impacted by the project to analyze stakeholder expectations and their impact on the project
- Ensuring timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and ultimate disposition of project information
- Identifying, combining, unifying, and coordinating the various processes and project management activities
- Ensuring the project includes all the work required, and only the work required, to complete the project successfully
The Project Integration Management Knowledge Area is the only Knowledge Area that has processes across all five process groups. It contains the high-level processes that bring the results of the remaining Knowledge Areas together, unifying and coordinating all project management activities.
Emma is a project manager working on a project that will require a specially engineered machine. Several manufacturers can make the machine to the specifications Emma needs. She will use purchase price as the sole criterion for choosing from among the vendors. Which of the following is true regarding this question?
Emma will include delivery and setup charges as part of the purchase price criterion. Emma must use purchase price alone as the sole criterion for evaluation because multiple vendors are involved. Emma will review the procurement documents and teaming agreements as some of the inputs to this process. Emma will use the advertising tool and technique of this process to let vendors know about this opportunity
When using price alone as a criterion for selection, there should be more than one vendor who can supply the goods or services you are procuring. However, that doesn’t mean you can’t use additional criteria for source selection. You should include costs such as delivery and setup in the purchase price criterion.
Which of the following best describes overall project risk?
The effect of uncertainty on the project as a whole, arising from all sources of uncertainty.
An uncertain event or condition that, if it occurs, has a negative effect on one or more project objectives.
The effect of uncertainty on a project objective, arising from all sources of uncertainty.
An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
According to the PMBOK® Guide, there are two levels of risk: individual project risk and overall project risk. An overall project risk is the effect of uncertainty on the project as a whole, arising from all sources of uncertainty.
You work within a team that uses a feature-driven development approach to manage software projects. As the senior project manager on the team, you know from experience the criticality of communication. You often coach other project managers on the various elements of communication, which are incorporated within the models of communication exchange. Which of the following best explains these communication elements?
- The elements of communication include senders, receivers, and messages, and the communication model includes encode, transmit, acknowledge, and feedback/ response.
- The elements of communication include encode, transmit, acknowledge, and feedback/response, and the communication model includes verbal and written.
- The elements of communication include encode, transmit, acknowledge, and feedback/response, and the communication model includes senders, receivers, and messages.
- The elements of communication include senders, receivers, and messages, and the communication model includes verbal and written.
The elements of communication involve senders, receivers, and messages. The communication model, a tool and technique of the Manage Communications process, includes encoding, decoding, acknowledging, and feedback/response. Verbal and written are forms of communication.
Your project has kicked off, and you are beginning a series of overview sessions with key users to determine requirements for a new enterprise resource software implementation. One of your stakeholders is exceptionally contentious and throws obstacles up at every turn. One of the problems she has described does seem to be legitimate. There is an issue with the data from the legacy system that needs to be resolved before moving forward. The PMO you report to practices phase sequencing and requires closure of each phase before the next phase can begin. What is this process called?
Phase exit Stage review Gate exit Phase review
Remember that all questions on the exam will refer to specific terminology used in the PMBOK® Guide – Sixth Edition. Although the other options presented may seem correct, the PMBOK® Guide calls this process by any of these names: stage gates, phase reviews, phase gates, phase exit, or kill points.
A project manager facilitated a meeting with the product manager and project team to discuss the results of the latest iteration. As part of the meeting, the project manager also reviewed the budget consumed to date on the project, highlighting appraisal costs. Which of the following best describes appraisal costs?
Costs expended to examine the product or process and make certain the requirements are being met
Costs associated with satisfying customer requirements by creating a product without defects
Costs when things don’t go according to plan
Costs that occur externally, when the customer determines that the requirements have not been met
Appraisal costs are associated with the cost of quality and are the costs expended to examine the product or process and make certain the requirements are being met. Inspection and testing are examples of appraisal costs.