Definitions and Terminologies Flashcards
This shows you a projected completion date based on the latest project date.
Burndown graph
This is an example of a parametric estimating
Dollars per module
Rough order of magnitude (ROM) estimate is made during which process group?
Initiating
What is an output of Determine Budget process?
Cost baseline
Value analysis is performed to get:
A less costly of doing the same work. It decreases cost while maintaining the same scope
These are not required to obtain estimates:
Change requests
Which estimating method tends to be most costly for creating a project cost estimate?
Bottom-up estimating
Does team velocity impact cost of the project
Yes
Which of the following are all items included in the cost management plan?
- Specifications for how estimates should be stated
- rules for measuring cost performance
- the level of accuracy needed for estimates
Earned value analysis is the basis for:
Performance reporting
The difference between the cost baseline and the cost budget can be described as:
The management reserves
The range on a control chart Is usually calculated based on
-3 or +3 sigma
During the Identify Risk process, The risk register includes:
- List of identified risks
- risk owners
- risk responses
The estimated value of work that’s completed/accomplished is called:
EV
The current actual cost incurred For the completed work is called:
Actual cost
The current forecast at work to finish the project is called:
ETC
The amount that was originally budgeted For the total project up for this called:
BAC
The six inputs to Monitor and control project work are:
- Project management plan
- Project documents
- Work performance information
- Agreements
- EEF
- OPA