Framework Flashcards

1
Q

Many project managers have seen a graph that shows “Influence of Stakeholders” starting out high and declining as the project progresses. In contrast, it also shows the “Cost of Changes” starting out low and increasing as the project progresses. What is the key insight a project manager should gain from this graph?

Make changes as early in the project as possible.
Set aside money for expected changes at the end of the project.
Stakeholder influence is not important at the end of the project.
Place the project on hold until all changes are made

A

Make changes as early in the project as possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following techniques used in adaptive lifecycles helps in minimizing scope creep?

User stories
Time-boxing
Iterations
User epics

A

Time-boxing - periods are durations during which the team works steadily toward completion of a goal. Time-boxing helps to minimize scope creep as it forces the teams to process essential features first, then other features when time permits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A first-time project manager was assigned to a project that had a duration of three months. In order to get a head start on the project, the manager took an older, completed the project and incorporated all the tools, techniques, and checklists in their entirety from that project into the current one. The older project was completed in 14 months’ time and was remarkably similar in nature. The most appropriate comment on this would be

  1. This is an excellent example of re-use of artifacts from prior projects.
  2. This is not the correct procedure. The project manager should always create processes and documents afresh for new projects.
  3. This is not correct. The project manager is violating copyright and intellectual property rights of the organization’s prior customers.
  4. This may be unnecessary. The project management team needs to decide what is appropriate for the project.
A

This may be unnecessary. The project management team needs to decide what is appropriate for the project.

The project management team needs to decide what is appropriate for the project. Since the prior project had a duration of 14 months and the current one is of 3 months’ duration, it is unlikely that the current project will have exactly the same processes applied. Some amount of tailoring will be required. The other responses are not valid. It cannot be said with certainty that the project manager will not be violating copyright and intellectual property rights of prior customers. Most organizations have clear guidelines on what information can go into their organizational assets’ database.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A project manager is spending most of the project funding in the current phase of the project. The manager is also managing various resources in the project. What is the stakeholder influence on the project now compared to earlier phases?

Less
More
Same
Cannot be determined

A

Less - Since the project manager is spending most of the money and managing resources, he or she is currently in the execution phase of the project. Spending levels reach a maximum in the execution phase. Stakeholder influences on the project decrease over the life of the project. Hence, stakeholder influence is now less than in previous phases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A single point of failure (SPOF) is the part of a system that, upon failure, stops the entire system from working or makes the system useless. Which of the following events can render a knowledge management system ineffective?

If project team is not motivated.
Knowledge is shared using a mixture of knowledge management tools and techniques.
When project knowledge cannot be classified as explicit or tacit.
Project team is geographically distributed.
A

If project team is not motivated.

The most important part of knowledge management is creating an atmosphere of trust so that people are motivated to share their knowledge. Even the best knowledge management tools and techniques will not work if people are not motivated to share what they know or don’t pay attention to what others know. None of the other choices pose a more serious threat than this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following statements is correct:

Project lifecycles and product lifecycles are interdependent.
A product lifecycle is the same as a project lifecycle.
Project lifecycles are independent of product lifecycles.
The last lifecycle for a project is generally the product's retirement.
A

Project lifecycles are independent of product lifecycles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A project consists of multiple phases. Which of the following is a valid statement and applies to each phase of the project?

  1. Each phase of the project is generally concluded with a review of the work accomplished and deliverables to determine acceptance and whether the phase should be considered closed.
  2. Each phase is generally concluded with a review of the work accomplished but is only closed if the next phase has already started.
  3. Each phase is generally concluded with a review of the work accomplished. A phase is never considered complete until the end of the project when the entire project is complete.
  4. Each phase of the project is considered complete when the project sponsor signs off on that phase of the project.
A

Each phase of the project is generally concluded with a review of the work accomplished and deliverables to determine acceptance and whether the phase should be considered closed.

A project phase is usually concluded with a review of the work accomplished and the deliverables to determine acceptance, whether extra work is still required and to decide whether the phase should be considered closed. The other options are not valid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following statements is not accurate about the initial phase of a project?

The cost associated at the beginning of the project is highest.
Staffing levels are the lowest at this stage.
Stakeholders have maximum influence during this phase.
The highest uncertainty is at this stage of the project

A

The cost associated at the beginning of the project is highest.

At the initial stage of a project, cost is typically not at its highest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You are managing a complex software development project for an external customer. You are using the waterfall approach to manage the project in line with the contractual requirements. However, you are not comfortable with this approach. You believe that customers don’t really know what they want upfront; rather, what they want emerges out of repeated two-way interactions over the course of the project. In your current situation, the waterfall approach has its emphasis on upfront requirements capture and design, followed by product development and finally the system testing. The customer will only be involved during the requirements gathering and system testing stages and will be completely out of touch during the development activities. Which of the following can help you mitigate the risk created by the waterfall approach:

Adopt an iterative life cycle.
Adopt a hybrid life cycle.
Divide the project into multiple phases and organize phase gates.
Adopt an incremental life cycle.

A

Divide the project into multiple phases and organize phase gates.

In a predictive life cycle, the project planning is completed in the early phases of the project. Although the use of the waterfall life cycle is mandated by the client, the project manager can still customize the approach to obtain benefits offered by the adaptive approaches. In this case, dividing the project into multiple phases and organizing phase gates with the customer can help achieve this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following scenarios is likely to occur in a project?

Stakeholders' influence on the project is lowest at the start of the project.
Cost and staffing levels are low at the start of the project.
Risk and uncertainty are lowest at the start of the project.
Cost of changes are the highest at the start of the project.
A

Cost and staffing levels are low at the start of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

While the five process groups are usually completed in order, they often overlap with each other throughout the project. Which two process groups usually do not overlap during the course of the project?

Initiating and Executing
Initiating and Closing
Planning and Closing
Initiating and Monitoring and Control
A

Initiating and Closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Nancy is engaged in the construction of three office buildings. Although the construction sites are in various places, she has managed each team efficiently to complete the work on time and within budget. Which of the following statements describes the effort Nancy is doing?

Construction of all three buildings is considered one project.
Construction of each building is a project because each building is separate in nature.
Construction of each building is an operational work because it is repetitive in nature.
The building construction is considered neither a project nor operational work.
A

Construction of each building is a project because each building is separate in nature.

Projects are temporary and unique, whereas operational work is repetitive. Since nancy is working to construct three unique buildings, and each has a definite beginning and a definite end, each effort is considered as a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following is least likely to be a project?

Running a campaign for a political office
Responding to a contract solicitation
An endeavor that lasts for 10 years
Regular updates of the company website

A

Regular updates of the company website

Regular updates of the company website constitute an operational activity and are clearly not a project. Responding to a contract solicitation and running a campaign are clearly projects. The endeavor lasting for ten years cannot be ruled out as a project just because of its duration. Projects can last from a few weeks to many years.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The term Progressive Elaboration incorrectly represents which of the following?

Rolling wave planning
Detailing out the product requirements developed during the initiation process.
Production of fabrication and construction drawings from the design drawings for a chemical plant.
Changes to project scope
A

The distinction between progressive elaboration and scope creep needs to be understood since the two terms are different. The changes to scope (especially in an uncontrolled manner) are called scope creep. In contrast, progressive elaboration involves building on or elaborating the output of a previous phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following statements most accurately describes a project scenario?

The influence of the stakeholders is the same all through the project.
Changes in project scope during the initial phases of the project are very expensive.
Staffing peaks during the execution phase of a project.
The next phase of a project should never start until the deliverables for the previous phase are completely reviewed and approved.

A

Staffing peaks during the execution phase of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Nancy is engaged in the construction of three office buildings. Although the construction sites are in various places, she has managed each team efficiently to complete the work on time and within budget. Which of the following statements describes the effort Nancy is doing?
Select one Mark question
Construction of each building is an operational work because it is repetitive in nature.
Construction of each building is a project because each building is separate in nature.
Construction of all three buildings is considered one project.
The building construction is considered neither a project nor operational work.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Nancy is engaged in the construction of three office buildings. Although the construction sites are in various places, she has managed each team efficiently to complete the work on time and within budget. Which of the following statements describes the effort Nancy is doing?
Select one Mark question
Construction of each building is an operational work because it is repetitive in nature.
Construction of each building is a project because each building is separate in nature.
Construction of all three buildings is considered one project.
The building construction is considered neither a project nor operational work.

A

Projects are temporary and unique, whereas operational work is repetitive. Since nancy is working to construct three unique buildings, and each has a definite beginning and a definite end, each effort is considered as a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

As an external vendor, you are managing a complex software project on a time-and-materials (T&M) contract. One of your team members reports a breakthrough in automating some of the testing activities. This may result in cost savings to the project and completion of the project one month ahead of schedule. Which of the following actions would you take?
Select one Mark question
Communicate the current status and inform the customer you will incorporate some additional features to use up the savings in cost and time since it was budgeted.
This is confidential information within your project team and there is no need to share with the customer. The savings will be additional profits on the project.
Communicate the current status to the customer and indicate the potential changes to cost and schedule.
Communicate the savings in cost and time to the customer. At the end of the project, notify your billing department that they need to prepare an invoice for 50 percent of the cost saved.

A

A project manager should always communicate an accurate statement of the project status. There could be subsequent actions to determine how the savings could be best put to use, whether there could be any cost sharing, etc.—but these would need to be done following the appropriate procedure. [pmi code of ethics and professional responsibility] [project framework]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
Control Schedule is part of which Project Management process group?
Select one Mark question
	Executing
	Initiating
	Monitoring and controlling
	Planning
A

Control schedule is part of the monitoring and controlling process group.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Projects, portfolios, and programs are different entities in an organization. Which of the following choices states a correct relationship between them?
Select one Mark question
A portfolio consists of a collection of projects or programs that are grouped together to achieve strategic business objectives. The projects or programs need not be directly related.
A program is a collection of projects that are grouped together for convenience. It may include unrelated work if the work is under the same business division.
A project is a collection of programs and portfolios that are grouped together to achieve the project objectives.
A program consists of a collection of projects or portfolios that are grouped together to achieve strategic business objectives.

A

A portfolio is a collection of projects or programs that are grouped together to achieve a strategic business objective. Portfolio management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation and that the management of the portfolio is aligned with organizational strategies. The projects or programs need not be directly related. A program is a collection of projects with common objectives, so unrelated work cannot be grouped together under a program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

David was required to investigate a business problem and describe the higher-level needs of the business as a whole. David’s final reports describes in detail the features, functions and characteristics of the product that will meet the business and stakeholder requirements. What is wrong with David’s report?
Select one Mark question
David was asked to analyze the business requirements, but he focused on the solution requirements.
David was asked to analyze the functional requirements, but he focused on the non-functional requirements.
David was asked to analyze the solution requirements, but he focused on the business requirements.
David was asked to analyze the non-functional requirements, but he focused on the functional requirements.

A

David was asked to analyze the business requirements but he focused on the solution requirements. Business requirements describe the higherlevel needs of the organization as a whole, such as the business issues or opportunities. While the solution requirements describes in detail the features, functions and characteristics of the product that will meet the business and stakeholder requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A first-time project manager was assigned to a project that had a duration of three months. In order to get a head start on the project, the manager took an older, completed the project and incorporated all the tools, techniques, and checklists in their entirety from that project into the current one. The older project was completed in 14 months’ time and was remarkably similar in nature. The most appropriate comment on this would be:
Select one Mark question
This may be unnecessary. The project management team needs to decide what is appropriate for the project.
This is not correct. The project manager is violating copyright and intellectual property rights of the organization’s prior customers.
This is not the correct procedure. The project manager should always create processes and documents afresh for new projects.
This is an excellent example of re-use of artifacts from prior projects.

A

The correct response is that this may be unnecessary. The project management team needs to decide what is appropriate for the project. Since the prior project had a duration of 14 months and the current one is of 3 months’ duration, it is unlikely that the current project will have exactly the same processes applied. Some amount of tailoring will be required. The other responses are not valid. It cannot be said with certainty that the project manager will not be violating copyright and intellectual property rights of prior customers. Most organizations have clear guidelines on what information can go into their organizational assets’ database.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The term Progressive Elaboration incorrectly represents which of the following?
Select one Mark question
Detailing out the product requirements developed during the initiation process.
Changes to project scope
Production of fabrication and construction drawings from the design drawings for a chemical plant.
Rolling wave planning

A

The distinction between progressive elaboration and scope creep needs to be understood since the two terms are different. The changes to scope (especially in an uncontrolled manner) are called scope creep. In contrast, progressive elaboration involves building on or elaborating the output of a previous phase.

23
Q

You are managing a complex software development project for an external customer. You are using the waterfall approach to manage the project in line with the contractual requirements. However, you are not comfortable with this approach. You believe that customers don’t really know what they want upfront; rather, what they want emerges out of repeated two-way interactions over the course of the project. In your current situation, the waterfall approach has its emphasis on upfront requirements capture and design, followed by product development and finally the system testing. The customer will only be involved during the requirements gathering and system testing stages and will be completely out of touch during the development activities. Which of the following can help you mitigate the risk created by the waterfall approach:
Select one Mark question
Adopt an incremental life cycle.
Adopt a hybrid life cycle.
Adopt an iterative life cycle.
Divide the project into multiple phases and organize phase gates.

A

In a predictive life cycle, the project planning is completed in the early phases of the project. Although the use of the waterfall life cycle is mandated by the client, the project manager can still customize the approach to obtain benefits offered by the adaptive approaches. In this case, dividing the project into multiple phases and organizing phase gates with the customer can help achieve this.

24
Q
While the five process groups are usually completed in order, they often overlap with each other throughout the project. Which two process groups usually do not overlap during the course of the project?
Select one Mark question
	Initiating and Closing
	Initiating and Executing
	Planning and Closing
	Initiating and Monitoring and Control
A

Throughout the project, the different process groups are often conducted at the same time except for the initiating and closing groups, which are separated by the other three groups.

25
Q

Many project managers have seen a graph that shows “Influence of Stakeholders” starting out high and declining as the project progresses. In contrast, it also shows the “Cost of Changes” starting out low and increasing as the project progresses. What is the key insight a project manager should gain from this graph?
Select one Mark question
Set aside money for expected changes at the end of the project.
Make changes as early in the project as possible.
Place the project on hold until all changes are made.
Stakeholder influence is not important at the end of the project.

A

Changes should be made as early as possible in the project to avoid additional cost and delays. The influence of stakeholders is high at the start of the project and low towards the end. In contrast, the cost of making changes in a project is low at the start of a project and high towards the end.

26
Q

Which of the following statements is not accurate about the initial phase of a project?
Select one Mark question
The highest uncertainty is at this stage of the project.
Staffing levels are the lowest at this stage.
The cost associated at the beginning of the project is highest.
Stakeholders have maximum influence during this phase.

A

At the initial stage of a project, cost is typically not at its highest.

27
Q

Which of the following statements most accurately describes a project scenario?
Select one Mark question
The influence of the stakeholders is the same all through the project.
Changes in project scope during the initial phases of the project are very expensive.
Staffing peaks during the execution phase of a project.
The next phase of a project should never start until the deliverables for the previous phase are completely reviewed and approved.

A

Staffing is typically highest during the execution phase of the project. The other three responses may not hold true. Projects can move forward into subsequent phases without the deliverables of the prior phase being completely approved; this is known as fast tracking. Changes during the initial phases of the project are the least expensive. The influence of the stakeholders is highest during the start of the project and declines as the project moves to completion.

28
Q
A project manager estimated that a project would require 4375 personhours of effort. The project ended up using 6250 person-hours of effort. The difference between these two figures is a:
Select one Mark question
	Variance
	Control Limit
	Standard Deviation
	Threshold
A

Variance is a quantifiable deviation, departure, or divergence away from a known baseline of expected value.

29
Q

What BEST describes the role of the project team members?
Select one Mark question
To perform the project’s work
To approve the change requests
To authorize the project
To accept ultimate responsibility for the project’s success

A

Project team members are responsible for performing the actual project work. They work with the project manager to complete project activities and achieve the goals of the project. The project manager is assigned by an organization to achieve specific project objectives. While the sponsor authorizes the project, ultimate responsibility for the project’s success lies with the project manager and the project sponsor.

30
Q
A project manager scheduled a review at the end of a phase, with the objective of obtaining authorization to close the current project phase and initiate the next phase. Which of the following is an incorrect way of describing this review?
Select one Mark question
	Stage gate
	Phase planning
	Phase gate
	Kill point
A

Stage gates, phase gates and kill points all refer to a phase end review with the objective of obtaining authorization to close the current phase and start the next one. This is a retrospective review of the current phase. Phase planning, on the other hand, is performed early during the planning phase of the project.

31
Q

A single point of failure (SPOF) is the part of a system that, upon failure, stops the entire system from working or makes the system useless. Which of the following events can render a knowledge management system ineffective?
Select one Mark question
Knowledge is shared using a mixture of knowledge management tools and techniques.
If project team is not motivated.
Project team is geographically distributed.
When project knowledge cannot be classified as explicit or tacit.

A

The most important part of knowledge management is creating an atmosphere of trust so that people are motivated to share their knowledge. Even the best knowledge management tools and techniques will not work if people are not motivated to share what they know or don’t pay attention to what others know. None of the other choices pose a more serious threat than this.

32
Q
Project stakeholders are individuals and organizations who are actively involved in the project or who have an interest in it. Which of the following is not an internal stakeholder?
Select one Mark question
	Competitor
	Project Manager
	Project Sponsor
	Program Manager
A

The competitors are affected by the project but are not actively involved in the project. Competitors are external project stakeholders.

33
Q
Which of the following is not a PMBOK Knowledge Area?
Select one Mark question
	Communications management
	Execution management
	Integration management
	Procurement management
A

Execution management is not a pmbok knowledge area. Note that execution is a process group.

34
Q
A project manager is spending most of the project funding in the current phase of the project. The manager is also managing various resources in the project. What is the stakeholder influence on the project now compared to earlier phases?
Select one Mark question
	Less
	More
	Same
	Cannot be determined
A

Since the project manager is spending most of the money and managing resources, he or she is currently in the execution phase of the project. Spending levels reach a maximum in the execution phase. Stakeholder influences on the project decrease over the life of the project. Hence, stakeholder influence is now less than in previous phases.

35
Q
PMBOK recognizes five process groups typical of nearly all projects. Which of the following is not one of them?
Select one Mark question
	Pre-Inception
	Planning
	Executing
	Monitoring and Controlling
A

Pre-inception is not a pmbok process group.

36
Q

Which of the following is the correct logical sequence of the five process groups?
Select one Mark question
Initiating, Planning, Executing, Monitoring and Controlling, Closing
Initiating, Monitoring and Controlling, Planning, Executing, Closing
Planning, Monitoring and Controlling, Initiating, Executing, Closing
Planning, Initiating, Executing, Monitoring and Controlling, Closing

A

The logical sequence of the five process groups is: initiating, planning, executing, monitoring and controlling, and closing.

37
Q
A \_\_\_\_\_\_ is a collection of projects or programs grouped together for strategic business needs.
Select one Mark question
	Array
	Management System
	Enterprise
	Portfolio
A

A portfolio is a collection of projects or programs. It helps facilitate efficient management.

38
Q
Which of the following are short, textual descriptions of required functionality often developed during a requirements gathering workshop:
Select one Mark question
	User stories
	Histograms
	Fishbone diagrams
	Decision trees
A

User stories are short, textual descriptions of required functionality often developed during a requirements gathering workshop. The rest of the choices are graphical formats.

39
Q
During the execution of a project, a large number of defects were discovered. The project manager ensured that the issues, defect resolution, and action item results were logged into a defects database. What would the defect database be considered a part of?
Select one Mark question
	Organizational Process Assets
	Change Requests
	Expert Judgment
	Deliverables
A

Issue and defect management databases are considered part of the organizational process assets. These databases typically contain historical issue and defect status, control information, issue and defect resolution, and action item results.

40
Q
Which of the following is not a project competing constraint?
Select one Mark question
	Risk
	Procurement
	Resource
	Budget
A

Six competing project constraints are scope, quality, schedule, budget, resources and risk. Procurement is not a project competing constraint.

41
Q
Which of the following components of a project scope statement is useful in reducing scope creep?
Select one Mark question
	Exclusions
	Deliverables
	Acceptance criteria
	Scope description
A

Project exclusions identifies what is excluded from the project. Explicitly stating what is out of scope for the project helps manage stakeholders’ expectation and can reduce scope creep. Other choices cannot help more in this regard.

42
Q

Which of the following scenarios is likely to occur in a project?
Select one Mark question
Stakeholders’ influence on the project is lowest at the start of the project.
Cost of changes are the highest at the start of the project.
Risk and uncertainty are lowest at the start of the project.
Cost and staffing levels are low at the start of the project.

A

Cost and staffing levels are low at the start of the project. The other statements are incorrect.

43
Q
Which of the following is an enterprise environmental factor?
Select one Mark question
	Configuration management knowledge base
	Change control procedures
	Historical information
	Commercial databases
A

Commercial databases are considered enterprise environmental factors. The other choices are organizational process assets.

44
Q

Which of the following statements is correct?
Select one Mark question
A collection of unrelated programs can constitute a portfolio.
A program need not consist of projects.
A program is a group of unrelated projects.
The scope of a portfolio is typically smaller than that of a program.

A

A portfolio refers to a collection of projects or programs that are grouped together to facilitate their effective management. The projects or programs need not be directly related or interdependent.

45
Q

A project consists of multiple phases. Which of the following is a valid statement and applies to each phase of the project?
Select one Mark question
Each phase is generally concluded with a review of the work accomplished but is only closed if the next phase has already started.
Each phase of the project is considered complete when the project sponsor signs off on that phase of the project.
Each phase is generally concluded with a review of the work accomplished. A phase is never considered complete until the end of the project when the entire project is complete.
Each phase of the project is generally concluded with a review of the work accomplished and deliverables to determine acceptance and whether the phase should be considered closed.

A

A project phase is usually concluded with a review of the work accomplished and the deliverables to determine acceptance, whether extra work is still required and to decide whether the phase should be considered closed. The other options are not valid.

46
Q
Collect Requirements, Develop Schedule, and Perform Qualitative Risk Analysis are all part of what process group?
Select one Mark question
	Monitor and Controlling
	Scope Planning
	Planning
	Executing
A

All activities listed are planning activities.

47
Q

The resource optimization technique during the Control Schedule process allows a project manager to:
Select one Mark question
Schedule activities considering both the resource availability and the project time.
Schedule training sessions for the project team members to optimize their performance.
Provide monetary incentives to project team members to boost their performance.
Allow overtime so that team members get motivated to work during nonworking hours.

A

Resource optimization technique during the control schedule process allows a project manager to schedule activities considering both the resource availability and the project time. Other choices are invalid.

48
Q
Kate has been asked to conduct the feasibility of a new CRM system. So far, the business has been relying on its traditional manual customer relationship management processes, but now it is struggling to keep up with the competition. In this scenario, the business’ requirement of acquiring a state-of-the-art CRM system to boost its customer relations management capabilities is an example of:
Select one Mark question
	Business requirements
	Project requirements
	Functional requirements
	Non-functional requirements
A

Business requirements describe the higher-level needs of the organization as a whole, such as the business issues or opportunities. Other choices are much lower level requirements.

49
Q

Which of the following statements is correct:
Select one Mark question
Project lifecycles and product lifecycles are interdependent.
A product lifecycle is the same as a project lifecycle.
Project lifecycles are independent of product lifecycles.
The last lifecycle for a project is generally the product’s retirement

A

Project life cycles are independent of product life cycles, which may be produced by a project.

50
Q
The transition from one phase to another within a project's lifecycle (e.g., from design to manufacturing) is typically marked by:
Select one Mark question
	Decision tree
	Constraint
	Kill point
	Monte Carlo
A

The transition from one phase to another within a project’s lifecycle typically involves, and is usually defined by, some form of technical transfer or handoff. This is also called a kill point.

51
Q
Fill in the blank. \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_ indicates that planning and documentation are iterative or ongoing activities.
Select one Mark question
	Iterative elaboration
	Progressive elaboration
	Waterfall development
	Progressive management
A

Progressive elaboration is a characteristic of projects. It allows a project management team to manage the project to a greater level as the project evolves.

52
Q

Which of the following is least likely to be a project?
Select one Mark question
Responding to a contract solicitation
Running a campaign for a political office
An endeavor that lasts for 10 years
Regular updates of the company website

A

Regular updates of the company website constitute an operational activity and are clearly not a project. Responding to a contract solicitation and running a campaign are clearly projects. The endeavor lasting for ten years cannot be ruled out as a project just because of its duration. Projects can last from a few weeks to many years.

53
Q

A project manager is managing a research project. Typically, research projects are not clearly defined and involve a lot of uncertainty. The project has four phases in which a phase can only start when its previous phase is complete. What project lifecycle and phase-to-phase relationship should the project manager use for this project?
Select one Mark question
Iterative lifecycle with sequential phase to phase relationship
Predictive lifecycle with overlapping phase to phase relationship
Predictive lifecycle with sequential phase to phase relationship
Iterative lifecycle with overlapping phase to phase relationship

A

The project manager should use the iterative life cycle since project phases and activities will most probably be repeated as the project team’s understanding of the project and requirements increases. Further, since any project phase can only start once its previous phase has been completed, the phase-to-phase relationship should be sequential.

54
Q

Configuration management tool selection should be based on the needs of the project stakeholders including organizational and environmental considerations and/or constraints. Which of the following is not a key configuration management consideration while selecting an appropriate configuration management tool for a project?
Select one Mark question
Identification and selection of configuration items.
Procedures for accepting and rejecting change requests.
Configuration item verification and audit.
Recording and reporting of configuration item status.

A

Procedures for accepting and rejecting change requests are related to change management rather than configuration management.

55
Q
Which of the following techniques used in adaptive lifecycles helps in minimizing scope creep?
Select one Mark question
	Time-boxing
	Iterations
	User stories
	User epics
A

Time-boxed periods are durations during which the team works steadily toward completion of a goal. Time-boxing helps to minimize scope creep as it forces the teams to process essential features first, then other features when time permits.